Niobrara river structure 183 additional riprap protection, FT. Randall - on'eill 115-KV transmission line, nebraska (urgent & compelling)

Ended Definitive Contract Awarded

Contract number
89503420CWA000039
Awardee
Awarding agency
Obligated
$110,175

Award facts

Contract value 100% obligated
$110,175.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
238910 Site Preparation Contractors
PSC
Z1PZ Maintenance Of Other Non-Building Facilities
Set-aside
No set-aside
Competition
Not Competed · 1 offer Only One Source
Pricing
Firm Fixed Price
Place of performance
O'Neill, NE 68763, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

About this award

This is a Firm Fixed Price definitive contract awarded by the Department of Energy Western Area Power Administration to John Prouty Construction, Inc., a for-profit Subchapter S Corporation, for additional riprap protection on the Niobrara River Structure 183 along the Ft. Randall - O'Neill 115-kV transmission line in Nebraska. The contract, which does not have a set-aside designation, has a potential value of $110,175.00 and a completion date of September 30, 2020. The contract was awarded on August 4, 2020 under the urgent and compelling acquisition authority.

Quick answers

Who was awarded contract 89503420CWA000039?

89503420CWA000039 was awarded to John Prouty Construction, Inc. by Western Area Power Administration (Department of Energy) on August 4, 2020.

How much is contract 89503420CWA000039 worth?

The government has obligated $110,175 on 89503420CWA000039.

Was contract 89503420CWA000039 competed?

The extent of competition for 89503420CWA000039 was not competed. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award