Definitive Contract 89503320CWA000017
Award Date 5/6/20
Potential Completion Date 7/31/20
Potential Value $215K
Federal Agency
Ultimate Awardee
Not listed PSC Category
Federal Contract Vehicle
- Not listed
Set-Aside Type
8(a) Sole Source
Extent Competed
Not Available for Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Folsom, CA 95630, USA
Solicitation Procedures
Only One Source
Number Of Offers Received
1
Legislative Mandate
Service Contract Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- <p>This is a $1,360,611.48 firm fixed price definitive contract awarded by the Department of Energy Western Area Power Administration to Canyon Power Solutions, LLC, a self-certified small disadvantaged, economically disadvantaged woman-owned small business. The contract is for the Folsom Substation Transformer KV4A Replacement project located in Folsom, California, and has a completion date of May 31, 2019. The contract was set aside for small businesses.</p>
- This is a $738,602.67 Firm Fixed Price contract awarded by the Western Area Power Administration (WAPA), a civilian agency within the Department of Energy, to AMT Diversified Construction, a small disadvantaged and woman-owned small business. The contract is for the Olinda Station Service Upgrades project, which involves upgrading the electrical infrastructure at the Olinda Substation in Folsom, California. This contract was set aside for small businesses under NAICS code 237130, Electric...
- The Western Area Power Administration awarded a $103,424.34 firm fixed price Blanket Purchase Agreement call to Civil Design & Engineering Inc. (Cd&E) for construction inspection services at Folsom Station Service in Folsom, California. This contract award represents Modification P0005, which executed a closeout deobligation of remaining funds under the underlying BPA. The award was made on April 20, 2023, with an ultimate completion date of June 30, 2025. This engagement was not...
- <p>This is a $293,041.42 firm fixed-price purchase order awarded by the Department of Energy Western Area Power Administration to Daniel Wagner Construction Inc., an SBA-certified 8(a) program participant and minority-owned small disadvantaged business. The contract is for facility repairs, with a performance location in Folsom, California. The contract was awarded on September 21, 2020 and is scheduled for completion on June 18, 2021. No set-aside designation was used for this procurement.</p>
- The Department of Energy Western Area Power Administration awarded a $369,499 firm-fixed price construction contract to Utility Construction Company, Inc. for the Folsom Substation Rating Upgrades project. The work involves replacing and upgrading existing line jumpers, disconnect switches, fittings, hardware, expansion tubes and associated equipment at the Folsom and Roseville Substations in California to meet transmission line rating requirements. This project was set aside for small...
- <p>The Department of Energy's Western Area Power Administration (WAPA) awarded a $141,260.72 firm fixed price purchase order to Power Systems Distributing, a woman-owned small business, for the provision of materials needed for the Carr-Keswick Transmission Line Structure 4/4 Replacement Project. The contract, which has a completion date of February 1, 2021, was awarded on July 21, 2020 under a total small business set-aside.</p>
- The Western Area Power Administration awarded Civil Design & Engineering Inc. (Cd&E) a $509,250.36 firm fixed price Blanket Purchase Agreement call for construction inspection services related to the Tracy Cluster 9 Breaker Replacement project in Byron, California. This modification represents a closeout deobligation of remaining funds and extends the period of performance through October 31, 2024, to accommodate construction delays. The contract was originally awarded on February 7,...
- <p>The Department of Energy Western Area Power Administration awarded a definitive, firm-fixed-price contract valued at $428,945.00 to Outback Contractors, Inc., a for-profit, woman-owned subchapter S corporation, for the CARR-KESWICK 4/4 STEEL POLE FOUNDATION project. The contract has a completion date of December 30, 2021 and does not have a set-aside designation. The contract is for the delivery of the specified steel pole foundations and is being performed in Folsom, CA.</p>
- The Western Area Power Administration (WAPA), Sierra Nevada Region, awarded a contract modification to Civil Design & Engineering Inc. (Cd&E) valued at $259,756.71 under a Blanket Purchase Agreement (BPA) call with firm fixed pricing. The contract modification serves to de-obligate excess funds and close out the expired contract, which was originally awarded on September 30, 2020, with an ultimate completion date of September 29, 2021. The primary deliverable under this contract is...
- This is a Definitive Contract awarded by the Western Area Power Administration (WAPA), a civilian agency under the U.S. Department of Energy, to Site Work Solutions, a HUBZone Certified Small Disadvantaged Business. The $239,194.55 Firm Fixed Price contract is for asphalt repair, sealcoating, and helipad striping services at WAPA's Folsom, CA office. The contract has a set-aside designation for HUBZone firms and a completion date of June 30, 2024. Site Work Solutions is a Native American-owned...
The Department of Energy Western Area Power Administration awarded a $214,662.91 firm fixed price definitive contract to Patterson Taber General Engineering, Inc., an 8(a) certified Small Business Administration program participant, to construct and complete engineered concrete caisson foundations for structures on two 230 kilovolt transmission lines in Folsom, California. The contract has a completion date of July 31, 2020.
Generated 3/22/24, 1:57 AM
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00001 | Supplemental Agreement for work within scope | $0 | 6/16/20 | |
| Not listed | Not listed | $214.7k | 5/6/20 |