This effort consists of up to three phases that encompass stirling power convertor design, fabrication, and performance verification. In addition to stirling convertor design and hardware, the…

Ended Definitive Contract Awarded Last action

Contract number
80GRC017C0007
Awardee
Awarding agency
Obligated
$3,611,523

Award facts

Contract value 87% obligated
  • $4,097,782.40 Current, with exercised options
  • $4,147,221.86 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 99 offers Negotiated Proposal / Quote
Pricing
Cost Plus Fixed Fee
Place of performance
Richland, WA 99354, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00032 $0
Funding Only Action P00033 · Stirling power convertor design, fabrication, and performance verification. -$264,697
Exercise an Option P00031 $279,748
Other Administrative Action P00030 · Stirling power convertor design, fabrication & performance verification. Supporting analyses, models, manufacturing drawings, design review document, test… $0
Funding Only Action P00029 · Three phases that encompass stirling power convertor design, fabrication, and performance verification. In addition to stirling convertor design and hardware,… $13,273
Other Administrative Action P00028 · Develop and test a flight-ready version of GE global research center's megawatt inverter developed under a previous NASA research announcement (NRA) silicon… $0
Other Administrative Action P00027 · MOD 27 extends period of performance $0
Other Administrative Action P00026 · Modification 21 adding $500,000.00 of funding to contract $0
Other Administrative Action P00025 · Modification 25 extends the with a no contract extension to DEC 31, 2020. $0
Other Administrative Action P00024 · Modification 24 is a no cost extension $0
Other Administrative Action P00023 $0
Other Administrative Action P00022 $0
Funding Only Action P00021 $500,000
Other Administrative Action P00020 $0
Other Administrative Action P00019 $100,000
Other Administrative Action P00017 · This convertor development effort is in support of NASA's science mission directorate and its need for higher-efficiency radioisotope power systems. The… $513,624
Other Administrative Action P00018 $50,000
Other Administrative Action P00016 $0
Funding Only Action P00014 $500,000
Other Administrative Action P00013 $0
Novation Agreement P00012 -$10,456
Funding Only Action P00011 $600,000
Other Administrative Action P00009 $0
Other Administrative Action P00006 $0
Other Administrative Action P00015 · This convertor development effort is in support of NASA's science mission directorate and its need for higher-efficiency radioisotope power systems. The… $0
Other Administrative Action P00002 · Dynamic power NRA $0
Modification $0
Other Administrative Action P00007 $27,000
Funding Only Action P00008 $0
Other Administrative Action P00003 $0
Other Administrative Action P00001 · Dynamic power NRA $0
Other Administrative Action P00005 · This MOD constitutes the base award. All subsequent mods will operate as follows: MOD 6= MOD 1 and so on. $803,031
Other Administrative Action P00004 $0
Funding Only Action P00010 · Dynamic power NRA $500,000
Show all 34

About this award

NASA's Glenn Research Center awarded a $4.15 million cost-plus-fixed-fee definitive contract to American Superconductor Corp for Stirling power convertor design, fabrication, and performance verification on July 3, 2017, with completion targeted for September 2, 2022.

The effort encompasses up to three phases of Stirling convertor design and hardware development, supported by analyses, models, manufacturing drawings, design review documents, test support equipment, logbooks, experimental data, and plans for performance verification and flight maturation. Place of performance is Richland, WA.

In FY2021, the contract invoiced $249 thousand across 944 contractor hours (0.5 FTEs) at a derived government-paid rate of $264.02 per hour. American Superconductor self-performed all reported work with no subcontractors engaged in that fiscal year.

Description

This effort consists of up to three phases that encompass stirling power convertor design, fabrication, and performance verification. In addition to stirling convertor design and hardware, the contractor shall provide supporting analyses, models, manufacturing drawings, design review documents, test support equipment (TSE), log books, experimental data, and plans for performance verification and flight maturation.

Quick answers

Who was awarded contract 80GRC017C0007?

80GRC017C0007 was awarded to American Superconductor Corp by Glenn Research Center (National Aeronautics and Space Administration) on July 3, 2017.

How much is contract 80GRC017C0007 worth?

The government has obligated $3,611,523 on 80GRC017C0007. Its current value, with exercised options, is $4,097,782. Its potential value, with all options, is $4,147,222.

Was contract 80GRC017C0007 competed?

The extent of competition for 80GRC017C0007 was full and open competition. The government received 99 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award