- The U.S. Smithsonian Institution awarded a $224,133.46 firm-fixed-price definitive contract to Kunkel Construction, Inc., a for-profit construction company, to provide construction services for supplementary works for the Gamboa Refurbishment of Facilities Project in Panama. The contract has an expected completion date of December 31, 2024 and was awarded on May 15, 2023. Kunkel Construction has previously performed similar construction, refurbishment, and facilities repair work for the...
- The Smithsonian Institution awarded a $1.33M firm fixed-price definitive contract to Kunkel Construction, Inc. on September 16, 2024, for the construction of a maintenance shop located in Gamboa, Republic of Panama. The work encompasses demolition, reconstruction, and new construction of the facility, including installation of electrical, plumbing, HVAC, security, and fire protection systems. The contract carries an ultimate completion date of July 4, 2026, allowing the contractor...
- The Smithsonian Institution awarded Kunkel Construction, Inc., a for-profit construction company, a definitive, firm fixed price contract valued at $255,146.32 to provide service, labor, material, and transport for floor repairs at the STRI Gamboa Building 056 in Panama. This contract has no set-aside designation and is expected to be completed by March 5, 2022. Based on the prime contractor's past performance, Kunkel Construction has previously delivered construction, refurbishment, and...
- Kunkel Construction, Inc. has been awarded a definitive, firm fixed price contract valued at two hundred sixteen thousand two hundred one dollars and sixty-three cents ($216,201.63) by the Smithsonian Institution to refurbish dormitories at the Smithsonian Tropical Research Institute, Biological Control Institute, dormitory D in Panama. The contract has no set aside designation and work is expected to be completed by February 26, 2024. As prime contractor, Kunkel Construction will provide all...
- This contract was awarded by the Smithsonian Institution to Kunkel Construction, Inc., a for-profit construction company, to provide construction services for a fire protection system at the Culebra Project in Panama. The definitive, firm fixed price contract has a potential value of $1,438,645.74 and a completion date of June 15, 2024. No set-aside designation was used for this award. Based on information about Kunkel Construction's prior federal contract awards, the company has experience...
- The U.S. Smithsonian Institution awarded a $373,301.22 firm fixed price definitive contract to Kunkel Construction, Inc., a for-profit construction company, to furnish labor, transport, and materials for the refurbishment of dormitories F and B at the Smithsonian Tropical Research Institute (STRI) and Biological Control Institute (BCI) facilities in Panama. This contract does not have a set-aside designation. Based on Kunkel Construction's prior prime contract awards from the Smithsonian...
- The Smithsonian Institution awarded a $320,794.65 definitive contract to Kunkel Construction, Inc. for replacement of security fences at STRI's sites on September 10, 2024, under no set-aside and firm fixed-price terms. Place of performance is Panama. The ultimate completion date is August 14, 2026. Kunkel Construction operates as a for-profit construction company headquartered in Panama and performs work exclusively at Smithsonian Tropical Research Institute and Biological Control Institute...
- The Smithsonian Institution awarded a $324.7K definitive contract on April 24, 2026, to Kunkel Construction, Inc., a Panama-based construction and facilities maintenance firm, for service, labor, material, and transport to support general maintenance operations at the Smithsonian Tropical Research Institute (STRI) Tupper Sites. The contract carries a firm fixed-price structure with no set-aside designation, allowing Kunkel Construction to compete as an open-market contractor. The work is...
- This federal contract award to Kunkel Construction, Inc. is for $5,108,272.49 to provide construction services for the Tupper Building and site improvements at the Tupper Center in Panama City, Panama. The contract is a definitive, firm-fixed price contract awarded by the Smithsonian Institution, a civilian federal agency. No set-aside designation was used. Based on Kunkel Construction's prior federal contract awards with the Smithsonian, the company has experience providing construction,...
- The Smithsonian Institution awarded a $4.63 million definitive contract to Kunkel Construction, Inc. for refurbishment of Building 56 at the Smithsonian Tropical Research Institute in Gamboa, Panama, on December 11, 2024, under a firm fixed-price structure with no set-aside. The originating solicitation, posted July 9, 2024, sought proposals for demolition and reconstruction of the facility. Place of performance is Panama. The contract ceiling is $4,632,417.78, with an ultimate completion date...
This is a definitive, firm-fixed price contract awarded by the Smithsonian Institution to Kunkel Construction, Inc., a for-profit construction company, to provide construction services for the Amphibian Rescue Center Phase III project in Gamboa, Republic of Panama. The contract has a potential value of $486,764.87 and a completion date of November 16, 2023. No set-aside designation was used for this award. Based on the information provided, Kunkel Construction has previously performed construction, refurbishment, repair, and maintenance services at Smithsonian facilities in Panama, including dormitory renovations, facility repairs, and fire protection system installation at the Smithsonian Tropical Research Institute and the Biological Control Institute.
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00007 | Change Order | $474 | 8/16/23 | |
| P00006 | Change Order | $10.3k | 4/3/23 | |
| P00005 | Change Order | $33.7k | 2/8/23 | |
| P00004 | Change Order | $0 | 11/17/22 | |
| P00003 | Change Order | $16.7k | 6/7/22 |