Cooling tower replacement project at united states mint philadelphia

Ended Definitive Contract Awarded Last action

Contract number
2031JG19C00034
Awardee
Awarding agency
Obligated
$2,121,995

Award facts

Opportunity
  • 2031JG19R00004 Solicitation number
Contract value 100% obligated
$2,121,995.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Philadelphia, PA 19114, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00009 $29,648
Change Order P00008 · The purpose of this modification is to 1) extend the end date of the period of performance form 30 SEP 2020 to 31 OCT 2020; 2) incorporate changes to allow… $8,179
Change Order P00007 · The purpose of this modification is to address costs incurred during the cooling tower overflow on 20 AUG 2020. $88,912
Supplemental Agreement for work within scope P00006 $22,435
Supplemental Agreement for work within scope P00005 · The purpose of this modification is formally incorporate the removal of the ACM wall panels from the scope of work. -$196,917
Supplemental Agreement for work within scope P00004 · The purpose of this modification is to update the contract for the new piping to be installed with the same diameter as the existing piping. $16,700
Supplemental Agreement for work within scope P00002 · The purpose of this modification is to reduce the value of the contract to reflect the nonexistent water tower bypass line. -$4,287
Supplemental Agreement for work within scope P00003 · The purpose of this modification is to update the contract for the new piping to be installed with the same diameter as the existing piping. $6,936
Supplemental Agreement for work within scope P00001 · The purpose of this modification is to reroute the existing electrical connections. $44,799
Original award $2,105,590

About this award

This federal contract was awarded by the Department of the Treasury United States Mint to Fluidics Inc., a commercial construction and facilities services company operating as a Honeywell Authorized Dealer. The $2,121,995.00 firm fixed price contract was for the Cooling Tower Replacement Project at the United States Mint facility in Philadelphia, Pennsylvania. The project was completed by November 30, 2020. Fluidics Inc. has a history of delivering HVAC infrastructure upgrades, maintenance, and repair services at various United States Mint locations, including a 5-year, $2.7 million contract for the William Penn Annex East building and a $130,000 project to upgrade exhaust systems in the Philadelphia Mint's die shop. No set-aside designation was used for this contract award.

Quick answers

Who was awarded contract 2031JG19C00034?

2031JG19C00034 was awarded to Fluidics Inc. by United States Mint (Department of the Treasury) on September 26, 2019.

How much is contract 2031JG19C00034 worth?

The government has obligated $2,121,995 on 2031JG19C00034.

Was contract 2031JG19C00034 competed?

The extent of competition for 2031JG19C00034 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award