X:nogrn prpa 18017 design/build south grounds infrastructure
Ended Definitive Contract Awarded Last action
- Contract number
- 140P2019C0020
- Awardee
-
The Whiting-Turner Contracting Company UEI VEP4UN7LDMK5
- Awarding agency
-
National Office
National Park Service, Department of the Interior
- Obligated
- $20,677,024
Award facts
- Opportunity
-
- PRPA 18017 S Grounds Infrastructure Solicitation · 140P2018R0106 · Posted Oct 23, 2018
- Design/Build Upgrade South Grounds Infrastructure Award Notice · Posted Jul 27, 2018
- Contract value 100% obligated
- $20,677,024.00 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Set-aside
- No set-aside
- Competition
- Full and Open Competition after exclusion of sources · 1 offer Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- Washington, DC 20500, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Close Out | $107,777 | |
| Other Administrative Action | $0 | |
| Change Order | $15,465 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $289,796 | |
| Supplemental Agreement for work within scope | $72,520 | |
| Supplemental Agreement for work within scope | $112,000 | |
| Change Order | $82,438 | |
| Supplemental Agreement for work within scope | $41,700 | |
| Supplemental Agreement for work within scope | $5,250 | |
| Supplemental Agreement for work within scope | $4,828 | |
| Supplemental Agreement for work within scope | $197,000 | |
| Change Order | $100,809 | |
| Change Order | $6,000 | |
| Definitize Change Order | $1,402,534 | |
| Supplemental Agreement for work within scope | $307,985 | |
| Supplemental Agreement for work within scope | $226,837 | |
| Supplemental Agreement for work within scope | $135,198 | |
| Supplemental Agreement for work within scope | $898,918 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $346,069 | |
| Supplemental Agreement for work within scope | $200,000 | |
| Exercise an Option | $61,400 | |
| Exercise an Option | $376,900 | |
| Change Order | $0 | |
| Original award | $15,685,600 |
Show all 26
About this award
The Department of the Interior National Park Service awarded a $20,677,024.00 firm fixed price definitive contract to The Whiting-Turner Contracting Company for the "X:NOGRN PRPA 18017 DESIGN/BUILD SOUTH GROUNDS INFRASTRUCTURE" project. This contract, which has a completion date of March 31, 2023, does not have a set-aside designation. The Whiting-Turner Contracting Company is a large construction firm with expertise in federal facilities and infrastructure projects, and has been awarded prime contracts by various federal agencies, including the Coast Guard, Navy, Marine Corps, National Institutes of Health, and General Services Administration. This contract is part of the National Park Service's broader "SOUTH GROUNDS INFRASTRUCTURE" program.
Quick answers
Who was awarded contract 140P2019C0020?
140P2019C0020 was awarded to The Whiting-Turner Contracting Company by National Office (National Park Service) on May 3, 2019.
How much is contract 140P2019C0020 worth?
The government has obligated $20,677,024 on 140P2019C0020.
Was contract 140P2019C0020 competed?
The extent of competition for 140P2019C0020 was full and open competition after exclusion of sources. The government received 1 offer.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award