About this opportunity
This solicitation from the Department of Veterans Affairs seeks repair and replacement services for three air handling units at the VA Western New York Healthcare System facility in Buffalo, New York. The scope of work includes replacing exhaust fans, steam humidifiers, preheat coils, duct silencers, filters and piping insulation across two air handlers serving the emergency department and intensive care units. For a third unit serving the surgical intensive care unit, the contractor must install a new fan array. Proposals will be evaluated on technical qualifications, past performance and price. The period of performance is 180 days from award.
The solicitation is set aside 100% for Service-Disabled Veteran-Owned Small Businesses. The primary NAICS code is 238220 - Plumbing, Heating, and Air-Conditioning Contractors with a PSC code of R499. The estimated value is between $100,000 and $250,000. Interested vendors must attend a pre-bid site visit on June 21, 2022, with questions due by June 29th and proposals due July 6th, to be conducted electronically through SAM.gov. All work will be performed at the VA Western New York Healthcare System facility located at 3495 Bailey Avenue in Buffalo, New York.
Notice text
2 versions
Update #2 · Latest ·
This solicitation notice is to inform potential offerors that the Buffalo, NY VA Medical Center posted a solicitation (36C24222B0049) on June 6, 2022,to provide urgent repairs to the air handling units (AHU) 1 and 2 in the E-Wing and the AHU that serves the Surgical Intensive Care Unit (SICU). All work to be perform at the Buffalo, NY VA Medical Center.
General scope of work includes:
Repair of Air Handling Units for Emergency Department and ICU
To perform urgent repairs to Air Handling Units (AHU) 1 and 2 in E Wing and the AHU that serves the SICU. The air handling systems for E wing were designed and installed around 1977. These two units need urgent repairs in order to continue to serve in a reliable manner. The Buffalo VAMC has purchased the exhaust fan but has no safe way to remove and replace the exhaust fan for AHU 1. AHU 2 needs the pre heat coils replaced and there are also significant amounts of degradation to the drain pans, sound attenuators, piping, and filter racks. Both units have been without humidification for quite some time.
The SICU s AHU fan wall is original and in need of replacement. WNYVAMC has procured the fan wall and it needs to be installed.
shut off before the control valve.
VA will run the control wire and program the valve.
It has been determined that there are enough qualified Service-Disabled Veteran Own Small Business (SDVOSB) firms that are capable of performing under NAICS Code 238220, "Plumbing, Heating, and Air Conditioning Contractors", with a size standard of $16.5M. Therefore, this procurement is 100% set-aside for a SDVOSB. The magnitude of the project is between $100,000 and $250,000. There was a prebid site visit 6/21/222. RFIs were due 6/29/2022 by 12 noon and there were no RFIs submitted. Bid bonding will be required to respond to this IFB. IFB are due July 6, 2022 by 11AM at which time there will be a BID Opening Teams meeting.
OBTAINING SOLICITATION MATERIAL
Solicitation materials consisting of the information for bid details, specifications, drawings, and contract forms will be available on http://www.beta.sam.gov in electronic format only. These should be available on or about June 6, 2022.
SOLICITATION AMENDMENTS: Amendments to the solicitation will be posted at http://www.beta.sam.gov. Paper copies of the amendments will NOT be individually mailed. No other notification of amendments will be provided. Bidders are reminded that they are responsible for obtaining and acknowledging all amendments to this solicitation by the time of bid opening.
Once the solicitation is released, bids will be accepted electronically only, due to ongoing safety concerns regarding the COVID -19 pandemic.
Please send all correspondence or inquiries by email only to the Contracting Officer. Contact Information:
Idalia Algarin, Contracting Officer
Idalia.Algarin@va.gov
2875 Union Road, Suite 3500
Cheektowaga, NY 14227
Update #1 ·
Statement of Work (SOW)
Project 528 21 110 E Wing Air Handler Repairs
General Information
1.1 Contract Title
Repair of Air Handling Units for Emergency Department and ICU
Contracting Officer Representative (COR)
Christopher Herby Project Engineer Facilities Engineering
Buffalo VAMC, 3495 Bailey Ave. Buffalo, NY 14215 (C) 716 445 1334
Christopher.Herby@va.gov
Purpose
The purpose of this contract is to acquire the services and necessary components to replace and repair aging components on the air handlers that feed the Emergency Department and Intensive Care Units.
Background
The intent of this work is to perform urgent repairs to Air Handling Units (AHU) 1 and 2 in E Wing and the AHU that serves the SICU. The air handling systems for E wing were designed and installed around 1977. These two units need urgent repairs in order to continue to serve in a reliable manner. The Buffalo VAMC has purchased the exhaust fan but has no safe way to remove and replace the exhaust fan for AHU 1. AHU 2 needs the pre heat coils replaced and there are also significant amounts of degradation to the drain pans, sound attenuators, piping, and filter racks. Both units have been without humidification for quite some time.
The SICU s AHU fan wall is original and in need of replacement. WNYVAMC has procured the fan wall and it needs to be installed.
The Buffalo VAMC requires a Contractor to perform services necessary to accomplish this goal.
Applicable Documents
The following documents are applicable to this Scope of Work (SOW) to the extent specified herein. While every effort has been made to ensure the completeness of this list, document users are cautioned that they must meet all specified requirements of documents cited in sections 0 of this SOW, whether or not they are listed here.
Non Government Publications
All work shall be accomplished in strict accordance with the latest codes and standards. The consultant shall review and include any/all applicable standards and codes, including, but not limited to applicable NFPA standards, NEC, JCAHO, OSHA, ANSI, ASHRAE, and any other codes.
The following documents of the exact revision listed below form a part of this document to the extent specified herein.
2.2 Order of Precedence
In the event of a conflict between the text of this document and the references cited herein, the text of this document takes precedence. Nothing in this document, however, supersedes applicable laws and regulations unless a specific exemption has been obtained.
Requirements
The Contractor shall provide personnel, material, tools, equipment, services, facilities, and basic consumables to perform, accomplish, and deliver the required services and materials detailed in this scope of work. They shall provide shop drawings for all work for review and approval by VA COR prior to starting work. A lifting and rigging plan will be required and submitted for VA approval.
3.1 Services
The Contractor shall:
3.1.1 Exhaust Fan 1
All work that requires AHU to be non operational is to be completed after normal working hours (0700 1600) or on weekends.
This is Government Furnished Equipment (GFE).
Work with the COR to schedule shut down with the HVAC and electric shop to lock out and verify the system is de energized.
VA electricians will disconnect and reconnect the power to the fan.
Remove existing axial fan and dispose of.
Assemble new motor, sheaves, and belts to new fan.
Supply rigging and bracing as required to safely remove old fan from a height of approximately 8 feet and install new fan. Approximate weight is 1425 lbs. 750 fan, 600 lbs. motor and 75 lbs. belts and sheaves.
Procure, fabricate, and/or repair any defective parts identified during the installation.
Perform final inspections and tests required to ensure proper operation and function of AHU 1 exhaust fan and motor assembly.
3.1.2 Steam Humidification
AHU 1
All work that requires AHU to be non operational is to be completed after normal working hours (0700 1600) or on weekends.
Provide and install new steam humidifier.
Original Design Conditions: 40,000 CFM/ 100% outside air/ 144 /72 deg. F. @ 40% RH/ horizontal air flow/ 196#/hr. @ 15 PSI steam.
Demo existing steam humidifier and relocate the new humidifier from before the fan wall to after.
Repair original humidifier penetrations in AHU shell.
Include new hand shut off valve, DDC steam control valve to replace existing pneumatic valve, trap, Y strainer, unions, and approximately 30 each of supply and condensate piping with insulation from the hand shut off before the control valve.
VA will run the control wire and program the valve.
AHU 2
All work that requires AHU to be non operational is to be completed after normal working hours (0700 1600) or on weekends.
Demo existing steam humidifier.
Provide and install new steam humidifier in existing location.
Design: 12,000 CFM/ 100% outside air/ 96 / deg. F. @ 40% RH/ horizontal air flow/ 61#/hr. @ 15 PSI steam.
Include hand shut off valve, DDC steam control valve to replace existing pneumatic valve, trap, Y strainer, unions and approximately 10 of supply and condensate piping with.
Replace insulation on supply and condensate piping.
VA will run the control wire and program the valve.
3.1.3 Other Services
AHU 1
Replace existing fiberglass insulation on chill water piping with new. Provide new labels for Supply and Return. Contractor to verify pipe size and lengths. See attached photos with stopping points.
AHU 2
.
All work that requires AHU to be non operational is to be completed after normal working hours (0700 1600) or on weekends.
Demo and replace 16 gauge stainless steel filter frames:
(8) 24x24 after filter sections with foam gaskets
Final measurements to be made by contractor before fabrication.
Replace clean flow duct silencers and floor under the filter and silencer section:
48 h x 96 w, constructed of 16 gauge 304 stainless steel.
Final measurements to be made by the contractor before ordering/fabrication.
Seal all seams and edges.
Replace preheat coils (2) and drain pan supplied by the VA. Glycol reclaimed by contractor.
Replace piping to the floor drains.
Replace glycol three way valve supplied by VA, contractor to include new fittings. VA to isolate and lockout.
VA will run control wire and program the valve.
SICU AHU Fans
All work that requires AHU to be non operational is to be completed after normal working hours (0700 1600) or on weekends.
New fan wall is Government Furnished Equipment.
Work with COR to schedule shut down with HVAC and electric shop to lock out and verify the system is de energized.
VA electricians will disconnect and reconnect the power.
Disassemble and remove existing fans and motor, prep area for fan cubes.
Assemble and install fan cubes and backdraft dampers.
Fabrication will be required to complete the installation; contractor is responsible to verify all measurements and perform all fabrication needed.
Procure, fabricate, and/or repair any defective parts identified during the installation.
Perform final inspections and tests required to ensure proper operation and function of fan and motor assembly.
3.2 Materials
Materials provided by Contractor are as required based upon the outcome of the inspection, (see 3.1).
3.3 Security Requirements
The Contractor shall coordinate access to the building 1 E Wing and the ICU mechanical space with the COR (Christopher Herby), the VAWNYHS Maintenance and Operations Supervisor (Mark Parsons), and/or HVAC Shop Supervisor (Corey Fitzery).
3.4 Risk Control
Not Applicable.
4.0 Delivery
4.1 Schedule
All work to be completed within 180 days of contract award.
4.2 Location
VA Western New York Healthcare System Buffalo VA Medical Center
3495 Bailey Avenue
Buffalo, NY 14215
5 Government Furnished Information, Materials, & Equipment
Government Furnished Information (GFI)
Government Furnished Materials (GFM)
Chicago Blower, motor, and belt drive system
Pre Heat coils and drain pan
SICU fan cubes and backdraft dampers
Government Furnished Information (GFE)
Attachments
| File | Type | Posted |
|---|---|---|
| Pre Bid Attendance 528-21-110 E-Wing AHU.pdf | ||
| 36C24222B0049 0001.docx | DOCX document | |
| 528-21-110 - PICTURES - Service - E-Wing AHU Repairs 25MAR22 02.pdf | ||
| 36C24222B0049.docx | DOCX document | |
| WAGE DETERMINATION.pdf | ||
| 528-21-110 E-Wing AHU Repair Specifications.pdf |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Z1DA--528-21-110 buffalo e-wing AHU repairs | Solicitation | |
| Z1DA--528-21-110 buffalo e-wing AHU repairs | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity