Notice text

5 versions

Update #5 · Latest ·

Added: Aug 19, 2016 12:02 pm 8/19/2016:  This amendment is to post results of the Bid Opening held at 11:00 am on August 19, 2016. 

Update #4 ·

Added: Aug 10, 2016 1:36 pm 8/10/16:  Amendment W911WN-16-B-8004-0001 is issued to provide answers to questions received after the scheduled site visit, and to provide a copy of the site visit sign-in sheet.

Update #3 ·

Added: Jul 21, 2016 12:44 pm ATTENTION: For companies new to the Army Corps of Engineers, Pittsburgh District, the link below will take you to a training Powerpoint slide presentation which will provide information essential to new contractors to help them navigate our bidding process. It will also help them to make their bid-no bid decision as it contains information on what will be required on a Post-Award performance basis - submittals, timelines, deadlines & milestones, necessary paperwork you need to supply, etc. This will help you capture everything needed in your bid so that there are no surprises later on. This training is not mandatory to be considered qualified to bid; it is meant as a means to assist you in becoming better prepared to work with the Corps of Engineers, Pittsburgh District. You can access the training using the link below:
http://www.lrp.usace.army.mil/Portals/72/docs/SmallBusiness/Solving%20the%20Mystery%20-Understanding%20USACE%20Pittsburgh%20Contracting%20Process.pptx
You may give feedback on the training package to the District's small business specialist using the email address of LRP.SBO@usace.army.mil

The date for receipt of quotes/bids/proposals remains as establihed in the original solicitation, and as amended (if any). This is strictly a notice for information only.

Update #2 ·

Added: Jun 29, 2016 10:14 am Modified: Jul 20, 2016 9:29 pmTrack Changes Project Information:

The project area is located on the left bank of the West Fork River within the corporate limits of the Town of Worthington, Marion County, WV. A sanitary sewer line was placed underground near the bank in 1993. Since then, the riverbank has eroded several feet, creating an over-steepening of the bank. Erosion encroached to within 5ft of the estimated location of the sanitary pipeline in some locations. The sewage collection pipeline is a vacuum system. If a break occurs, then the vacuum suction will be lost and the potential for untreated sanitary discharge into the environment could occur.

To address the issues associated with streambank erosion along the north bank of the West Fork River, this project proposes to use a combination of riprap (rock) and bioengineering bank stabilization (brush layering) techniques along a 1,350-foot stretch of the West Fork River. The bank will be graded to a slope of between 2:1 (H:V) and 3:1. Riprap will be installed along the toe of the streambank. Native vegetation will be installed with turf reinforcement matting above the riprap. Existing mature Maple Trees will be preserved to the maximum extent possible.


It is anticipated that a net cut (spoil) will be produced from the installation of riprap and brush layering. This material will be disposed of at a nearby disposal site owned by the Town of Worthington located across the West Fork River.


This acquisition will be a 100% HUBZone small business set-aside. NAICS code is 238910, Site Preparation. All responsible HUBZone small business bidders are encouraged to participate. The Invitation for Bid (IFB) will be issued online only through the Federal Business Opportunities website; therefore, requests for hardcopies of the specifications and drawings will not be honored.


In order to receive notification of any amendments to this solicitation, interested vendors must register as such on the FBO.gov website. If you are not registered, the Government is not responsible for providing notification of any changes to the solicitation. Contractors must be actively registered in the System for Award Management (SAM) database before receiving any contract award (go to www.sam.gov to register).

An organized site visit has been scheduled for Wednesday, August 3, 2016 at 10:00 am.  Please download soliciation for details and instructions for attendance.

Update #1 ·

Added: Jun 29, 2016 10:14 am Project Information:

The project area is located on the left bank of the West Fork River within the corporate limits of the Town of Worthington, Marion County, WV. A sanitary sewer line was placed underground near the bank in 1993. Since then, the riverbank has eroded several feet, creating an over-steepening of the bank. Erosion encroached to within 5ft of the estimated location of the sanitary pipeline in some locations. The sewage collection pipeline is a vacuum system. If a break occurs, then the vacuum suction will be lost and the potential for untreated sanitary discharge into the environment could occur.

To address the issues associated with streambank erosion along the north bank of the West Fork River, this project proposes to use a combination of riprap (rock) and bioengineering bank stabilization (brush layering) techniques along a 1,350-foot stretch of the West Fork River. The bank will be graded to a slope of between 2:1 (H:V) and 3:1. Riprap will be installed along the toe of the streambank. Native vegetation will be installed with turf reinforcement matting above the riprap. Existing mature Maple Trees will be preserved to the maximum extent possible.


It is anticipated that a net cut (spoil) will be produced from the installation of riprap and brush layering. This material will be disposed of at a nearby disposal site owned by the Town of Worthington located across the West Fork River.


This acquisition will be a 100% HUBZone small business set-aside. NAICS code is 238910, Site Preparation. All responsible HUBZone small business bidders are encouraged to participate. The Invitation for Bid (IFB) will be issued approximately July 14, 2016 online only through the Federal Business Opportunities website; therefore, requests for hardcopies of the specifications and drawings will not be honored.


In order to receive notification of any amendments to this solicitation, interested vendors must register as such on the FBO.gov website. If you are not registered, the Government is not responsible for providing notification of any changes to the solicitation. Contractors must be actively registered in the System for Award Management (SAM) database before receiving any contract award (go to www.sam.gov to register).

Attachments

Files attached to this notice, newest first
File Type Posted
BidResults_W911WN-16-B-8004.pdf PDF
W911WN-16-B-8004-0001.pdf PDF
Attachment_2_-_Drawings.pdf PDF
Attachment_1_-_Technical_Specifications_20_July_2016.pdf PDF
W911WN-16-B-8004.pdf PDF
Attachment_4_-_Price_Schedule.pdf PDF
Attachment_3_-_Wage_Determination_WV56_7.1.16.pdf PDF

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity