SPE7M1-16-r-0013

Awarded Award Notice Posted

Solicitation number
SPE7M1-16-R-0013
Agency
Land and Maritime Defense Logistics Agency, Department of Defense
Awarded
to Hydraulic Technology, Inc.
Set-aside
No set-aside

Opportunity facts

Contract number
SPE7M816C0016 Federal contract award
NAICS code
333911 Pump and Pumping Equipment Manufacturing
PSC
Not on record

Notice details come from SAM.gov. Updated .

Notice text

Added: Dec 17, 2015 10:20 am  

***Sources Sought***


 


 


This is not a request for either a quote or proposal. This announcement is considered market research in accordance with FAR Part 10.


 


NO SOLICITATION IS BEING ISSUED AT THIS TIME.


 


 


PUMP UNIT, RECIPROCATING


 


Review the below NSN and provide us with any sources that are able to manufacture the item. Also, provide the location of the manufacturer (city and state OR country, if applicable). Please provide the POCs for these manufacturers, if available. Please complete and return the attached Market Survey.


 


All of this information can be submitted to Philip Nightingale at Philip.Nightingale@dla.mil, Phone (614) 692-7677. Thank you for your time and cooperation.


 


         NSN                                    Item                   Material is made IAW drawings listed below


4320014128596              Repair Kit, Compress


 


Responses to this Request for Information (RFI) are not considered offers and cannot be accepted by the Government to form a binding contract. This RFI is for market research purposes only. Any information submitted is at the company's own expense. The Government will not reimburse respondents for any costs associated with submission of capability statements in connection with the market survey. Any information provided is voluntary. Acquisition of this part is restricted to source(s) specified on the source control drawing. Alternate offers will not be accepted. Offerors who are interested in qualifying their product for purpose of future acquisitions must contact the cognizant design activity specified on the source controlled drawings.


 





IAW BASIC DRAWING NR 98752 8611320



 



REVISION NR F DTD 07/22/2005



 



PART PIECE NUMBER: 8611320-150



 



 


IAW REFERENCE DRAWING NR 98752 8611323



 



REVISION NR C DTD 07/02/1997



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 8611324



 



REVISION NR D DTD 07/20/1993



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 8611325



 



REVISION NR C DTD 07/17/1997



 



PART PIECE NUMBER:



 



 


 


 


 


IAW REFERENCE DRAWING NR 98752 8611325



 



REVISION NR C DTD 07/03/1997



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 8611331



 



REVISION NR B DTD 01/08/1996



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 8611331



 



REVISION NR B DTD 01/08/1996



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 8611334



 



REVISION NR DTD



 



PART PIECE NUMBER:



 



 


 


 


IAW REFERENCE DRAWING NR 98752 8611335



 



REVISION NR A DTD 11/27/1995



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 8611348



 



REVISION NR B DTD 07/03/1997



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 8719896



 



REVISION NR DTD



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 8611346



 



REVISION NR DTD 06/12/1989



 



PART PIECE NUMBER:



 



 


 


 


IAW REFERENCE DRAWING NR 98752 8611348



 



REVISION NR E DTD 02/02/2001



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 8611321



 



REVISION NR E DTD 07/08/1999



PART PIECE NUMBER:



 


IAW REFERENCE DRAWING NR 98752 8611321



REVISION NR B DTD 07/03/1997



PART PIECE NUMBER:



 


IAW REFERENCE DRAWING NR 98752 8611322



REVISION NR C DTD 07/11/1999



PART PIECE NUMBER:



 


IAW REFERENCE DRAWING NR 98752 8611322



REVISION NR B DTD 07/12/1999



PART PIECE NUMBER:



 


IAW REFERENCE DRAWING NR 98752 8611326



REVISION NR D DTD 07/11/1999



PART PIECE NUMBER:



 


IAW REFERENCE DRAWING NR 98752 8611328



REVISION NR B DTD 02/17/2010



PART PIECE NUMBER:



 


IAW REFERENCE DRAWING NR 98752 8611328



REVISION NR C DTD 07/11/1999



PART PIECE NUMBER:



 


IAW REFERENCE DRAWING NR 98752 8611332



REVISION NR D DTD 04/26/2000



PART PIECE NUMBER:



 


IAW REFERENCE DRAWING NR 98752 8611332



REVISION NR B DTD 03/21/1996



PART PIECE NUMBER:



 


IAW REFERENCE DRAWING NR 98752 93107916



REVISION NR DTD



PART PIECE NUMBER:



 


IAW REFERENCE DRAWING NR 98752 93107916



REVISION NR DTD



PART PIECE NUMBER:



 


 


 


 


 


 


IAW REFERENCE DRAWING NR 98752 93107920



REVISION NR DTD



PART PIECE NUMBER:



 


IAW REFERENCE DRAWING NR 98752 93107920



REVISION NR DTD



PART PIECE NUMBER:



 


IAW REFERENCE DRAWING NR 98752 93107921



REVISION NR DTD



PART PIECE NUMBER:



 



IAW REFERENCE DRAWING NR 98752 8611327



 



REVISION NR C DTD 06/02/1997



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 8611330



 



REVISION NR A DTD 12/01/1995



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 8611333



 



REVISION NR A DTD 11/27/1995



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 8611343



 



REVISION NR A DTD 11/01/1995



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 8611343



 



REVISION NR A DTD 01/08/1996



 



PART PIECE NUMBER:



 



 


 


IAW REFERENCE DRAWING NR 98752 8611344



 



REVISION NR B DTD 01/11/1996



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 93107914



 



REVISION NR DTD



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 93107915



 



REVISION NR DTD



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 93107915



 



REVISION NR DTD



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 93107917



 



REVISION NR DTD



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 93107918



 



REVISION NR DTD



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 93107919



 



REVISION NR DTD



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 93107922



 



REVISION NR DTD



 



PART PIECE NUMBER:



 



 


IAW REFERENCE DRAWING NR 98752 8611346



 



REVISION NR B DTD 11/29/1995



PART PIECE NUMBER:



 


IAW REFERENCE DRAWING NR 98752 93107911



REVISION NR A DTD 07/07/1999



PART PIECE NUMBER:



 


IAW REFERENCE DRAWING NR 98752 8611320



REVISION NR H DTD 10/15/2008



PART PIECE NUMBER: FIND NO. 150



 


IAW REFERENCE DRAWING NR 98752 8611357



REVISION NR C DTD 12/29/1995



PART PIECE NUMBER:



 


IAW REFERENCE DRAWING NR 98752 200415485



REVISION NR C DTD 09/05/2008



PART PIECE NUMBER:



 


IAW REFERENCE DRAWING NR 98752 8611329



REVISION NR B DTD 02/16/2010



PART PIECE NUMBER:



 


IAW REFERENCE DRAWING NR 98752 93107912



REVISION NR DTD



PART PIECE NUMBER:



 


IAW REFERENCE DRAWING NR 98752 93107912



REVISION NR DTD 12/15/1993



PART PIECE NUMBER:



 


IAW REFERENCE DRAWING NR 98752 93107923



REVISION NR DTD 12/07/1995



PART PIECE NUMBER:



 





 



 



 



 



 



 



 



 



 







ITEM DESCRIPTION:



PUMP UNIT, RECIPROCATING.



FULL AND OPEN COMPETITION APPLY



***



Configuration Change Management - Engineering Change Proposal, Requests



for Variance (Deviation or Waiver) February 2015



1. Requirements



A. The Configuration Change Management section of SAE EIA-649-1



Configuration Management Requirement for Defense Contracts, Paragraph



3.3, shall be used for Configuration Control of material purchased under



this contract.



B. Furnished item(s) shall conform to the approved configuration



requirements/revision specified, unless a Pre-Production Request for



Variance (deviation) or a Post-Production Request for Variance (waiver),



is processed and approved as provided by Paragraph 3. in this Standard



Text Object (STO). Hereafter, the term #Request for Variance (RFV)#



will also include Requests for Deviations and Waivers.



2. The definitions from EIA-649-1 apply to items being procured under



this solicitation/contract, with the following clarification of



Deviation & Waiver:



A. Pre-Production RFV (previously known as deviation) requests



permission to produce a product that does not conform to contract



requirements/documentation for a limited amount of time and for



specified effectivity. (A deviation differs from an engineering change



in that an approved engineering change requires corresponding revision



of the item's current approved configuration documentation, whereas a



deviation does not.).



B. Post-Production RFV (previously known as waiver) requests



approval of product found during manufacture, or after having been



submitted for Government inspection or acceptance, that departs from



specified requirements, but nevertheless is considered suitable for use



"as is" or after repair by an approved method.



3. Contractor responsibilities.



A. An Engineering Change Proposal (ECP) is used to make permanent



changes in the Government technical data package (TDP). Pending



approval of an ECP, contractual relief should be requested in writing by



the Contractor using a RFV.



B. Refer to FAR Part 48 Value Engineering for cost saving



improvements to the Technical Data Package (TDP).



C. All ECPs submitted by the Contractor will be deemed routine.



If the Contractor considers an ECP as an emergency or urgent; they



shall include in their ECP submittal an explanation and all applicable



supporting documentation. All ECPs will be reviewed for a determination



on criticality, and, if concurred to be an emergency, the appropriate



processing time-frame negotiated with the ESAs will be followed and the



Contractor will be notified of anticipated response time.



 



D. For ECPs, Specification Change Notices (SCNs) or RFV, the



 



Contractor must submit the applicable documentation listed in



 



sub-paragraphs D.(1) through D.(4)to the Administrative Contracting



 



Officer(ACO), with an information copy to the Procuring Contracting



 



Officer (PCO). Failure to submit a complete legible package may result



 



in return of the ECP/RFV without processing.



 



(1) Documentation listed in Paragraph 3.3.1 (for ECPs), 3.3.2



 



(RFV), 3.3.3 (for SCNs) or 3.3.4 (for Notices of Revision (NORs)) of the



 



latest revision of EIA-649-1.



 



(2) DD Form 1692 (current revision) for ECP.



 



(3) DD Form 1694 (current revision) for RFV.



 



(4) DD Form 1695 (current revision) for NOR.



 



4. DLA#s responsibilities:



 



A. Upon receipt of the ECP or RFV, the PCO will ensure that the



 



applicable product specialist receives the copy from DCMA.



 



B. Within five (5) working days from the date of receipt of the



 



Contractor's ECP or RFV from DCMA, the PS must submit the requests and



 



any supporting documentation via a 339 to the appropriate Engineering



 



Support Activity (ESA), when applicable.



 



C. Routine ECPs will be processed within 90 days from receipt by



 



the ESA. RFVs will be evaluated and processed within 30 days from



 



receipt by the ESA or as negotiated with the ESA.



 



(1) The contractor will be notified in writing of approval by



 



the return of an approved copy of the ECP or RFV. Approval will be



 



reflected by signature of the contracting activity or a review activity



 



specifically identified in the contract.



 



(2) The contractor will be notified in writing of disapproval



 



including reason(s) for disapproval.



 



5. For an approved RFV or an approved ECP, when the request affects the



 



Contract, a modification will be issued to the contract incorporating



 



the applicable requirement changes. Only a Contracting Officer is



 



authorized to issue a modification incorporating the approved RFV and/or



 



ECP.



 



6. Questions regarding the status of previously submitted ECP or RFV



 



should be directed to the PCO.



 



7. The submission of an ECP or RFV by the Contractor does not affect



 



the required delivery date of the contract. If a delivery date change



 



is needed, it must be negotiated with the Contracting Officer and



 



documented via modification to the contract.



 



8. The period of time for evaluation and approval/disapproval of an ECP



 



and/or a RFV, as specified in Paragraph 4. C., shall not constitute



 



excusable delay in the performance of this Contract by the Contractor or



 



in any way relieve the contractor from compliance with the contract



 



delivery schedule. The submission of an ECP and/or RFV by the



 



Contractor shall not preclude the Government from exercising its rights



 



under any clause of the Contract. (End)



 



 



***



THIS ITEM HAS TECHNICAL DATA SOME OR ALL OF WHICH IS SUBJECT TO



EXPORT-CONTROL REGULATIONS. DISTRIBUTION OF THE TECHNICAL DATA



AND ELIGIBILITY FOR AWARD ARE LIMITED TO THOSE SUPPLIERS QUALIFIED



THROUGH JCP CERTIFICATION, OR TO THOSE LICENSED BY EITHER THE



DEPARTMENTS OF STATE OR COMMERCE; OR TO FOREIGN SUPPLIERS PURSUANT TO



INTERNATIONAL AGREEMENTS.



TO APPLY FOR JCP CERTIFICATION, COMPLETE DD FORM 2345, MILITARY



CRITICAL TECHNICAL DATA AGREEMENT, FORM IS AVAILABLE AT THE WORLD WIDE



WEB ADDRESS HTTP://WWW.DLIS.DLA.MIL/JCP OR BY WRITING TO:



DLA LOGISTICS INFORMATION SERVICE



FEDERAL CENTER



74 WASHINGTON AVE., NORTH



BATTLE CREEK, MI 49037-3084



TO MANUFACTURE THIS ITEM, NON-JCP CERTIFIED SUPPLIERS MUST SUBMIT A



CURRENT MANUFACTURING LICENSE AGREEMENT, TECHNICAL ASSISTANCE AGREEMENT,



DISTRIBUTION AGREEMENT OR OFF-SHORE PROCUREMENT AGREEMENT APPROVED BY



THE DIRECTORATE OF DEFENSE TRADE CONTROLS WITH THE OFFER, UNLESS AN



EXEMPTION UNDER THE PROVISIONS OF ITAR SECTION, 125.4 EXEMPTIONS OF



GENERAL APPLICABILITY, AND/OR EAR PART 740 ARE APPLICABLE.



NON-JCP CERTIFIED SUPPLIERS SEEKING EXPORT CONTROLLED TECHNICAL



DATA ARE REQUIRED TO PROVIDE THE CONTRACTING OFFICER WITH AN



APPLICABLE AGREEMENT OR IDENTIFY WHICH ITAR/EAR EXEMPTION APPLIES TO



RECEIVE A COPY OF THE EXPORT CONTROLLED TECHNICAL DATA.



NOTE: JCP CERTIFIED CONTRACTORS WHO RECEIVE TECHNICAL DATA PURSUANT TO



THEIR DD FORM 2345 CERTIFICATION MAY NOT FURTHER DISSEMINATE SUCH DATA



UNLESS FURTHER DISSEMINATION OF THE TECHNICAL DATA IS EXPRESSLY



PERMITTED BY DODD 5230.25.



***



SINCE THIS NSN IS A NAVY FIELD LEVEL REPARABLE



ITEM CONFIGURATION CONTROL MUST BE MAINTAINED



PER MIL-STD-973.



***



DLAD 52.246-9003, MEASURING AND TEST EQUIPMENT,



APPLIES.



***



DWG NRS 93107914, 93107915, 8611321, 23, 26, 27<(>,<)>



31, 32, & 35 CALL OUT FINISH RQMTS THAT SHALL BE



EXCEPTIONED AS FOLLOWS:



"PRETREAT EXTERIOR METAL SURFACES PER MIL-C-5541



CLASS 1A, PRIMER PER MIL-P-23377 TYPE I CLASS C



OR MIL-P-85582 TYPE I CLASS C2, AND PAINT PER



MIL-C-85285 TYPE II. EXTERIOR COLOR OF ALL



COMPONENTS VISIBLE AFTER INSTALLATION, INCLUDING



CLOTH, VELCRO, ETC, SHALL APPROXIMATE DESERT



SAND, COLOR #33446 PER FED-STD-595."



NOTE: THIS DESERT SAND COLOR #33446 DOES NOT



 



SHOW AS AN APPROVED COLOR ON QPL 85285-6. THE



 



QPL, HOWEVER, IS ONLY TO BE USED TO CONTACT



 



THESE PAINT MFGRS TO SEE IF THEY CAN SUPPLY A



 



COLOR THAT APPROXIMATES DESERT SAND #33446.



 



IF THE MFGRS CAN FURNISH AN APPROXIMATE COLOR<(>,<)>



 



THEY ARE ACCEPTABLE TO FURNISH THEIR PAINT IN



 



SPITE OF THIS COLOR NOT SHOWING ON THE QPL.



 



EXCEPTION NR 2; FOR THE ID & INST PLATE DWG NR



 



8611334, LEAVE THE "SUPPLY CATALOG NO" BLANK.



 



CXCEPTION NR 3; FOR FIND N0 175 ON PARTS LIST



 



DWG NR 8611325, THE CORRECT P/N SHOULD BE READ



 



MS35207-260. FOR FIND NO 224 ON THIS SAME PARTS



 



LIST, THE CORRECT P/N SHOULD READ WPG-2 AND THE



 



MANUFACTURER FOR THIS P/N IS PASS AND SEYMOUR."



 



***



 



SAMPLING:



 



IF THE APPLICABLE (OEM OR MILITARY) DRAWING, SPECIFICATION, STANDARD, OR



 



QUALITY ASSURANCE PROVISION (QAP) SPECIFIES AN ACCEPTABLE QUALITY LEVEL



 



(AQL), IT MAY BE USED TO ESTABLISH THE AUTHORIZED SAMPLE SIZE. HOWEVER



 



THE SAMPLING ACCEPTANCE NUMBER SHALL BE REDUCED TO ZERO (0). EVEN THOUGH



 



THE ACCEPTANCE LEVEL IS ELIMINATED, THE SAMPLE SIZE REMAINS THE SAME.



 



UNLESS OTHERWISE SPECIFIED IN THE OEM OR MILITARY DRAWING,



 



SPECIFICATION, STANDARD, OR QUALITY ASSURANCE PROVISIONS (QAPs)



 



CHARACTERISTICS CLASSIFIED AS CRITICAL, MAJOR AND MINOR SHALL HAVE AN



 



ASSIGNED AQL OF 0.10, 1.0, AND 4.0 RESPECTIVELY. ASQ H1331 TABLE 1 OR



 



MIL-STD-1916 SHALL TAKE PRECEDENCE OVER MIL-STD-105 AND ASQ Z1.4. THESE



 



PLANS ACCEPT ON ZERO DEFECTS AND REJECT THE ENTIRE LOT ON ONE DEFECT. A



 



ZERO BASED SAMPLING PLAN SHALL BE USED, UNLESS OTHERWISE SPECIFIED BY



 



CONTRACT.



 



***



 



A metal casting process was identified as a means to manufacture this



 



item. Tooling is required to produce a casting. For sourcing,



 



tooling, materials or other information, please contact the appropriate



 



assistance team: (Aviation, C&E Supply Chains) DSCR.AFCAT@dla.mil; (Land



 



& Maritime Supply Chains) DSCC.cast.forge@dla.mil



 



***



 



CLASS I OZONE DEPLETING CHEMICALS ARE NOT TO BE



 



USED NOR INCORPORATED IN ANY ITEMS TO BE



 



DELIVERED UNDER THIS CONTRACT.THIS PROHIBITION



 



SUPERSEDES ALL SPECIFICATION REQUIREMENTS BUT



 



DOES NOT ALLEVIATE ANY PRODUCT REQUIREMENTS.



 



SUBSTITUTE CHEMICALS MUST BE SUBMITTED FOR



 



APPROVAL UNLESS THEY ARE AUTHORIZED BY THE



 



SPECIFICATION REQUIREMENTS.



 



***



 



"SPECIFICATION CONTROL"



 



CRITICAL APPLICATION ITEM



 


Attachments

Files attached to this notice, newest first
File Type Posted
3_Market_Survey.docx DOCX document

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
SPE7M1-16-r-0013 Latest Award Notice
SPE7M1-16-r-0013 This notice · Original Award Notice

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity