Quillayute Training Wall Repair
Awarded Award Notice Posted
- Solicitation number
- W912DW-16-Q-0047
- Agency
- ENDIST Seattle US Army Corps of Engineers, Department of Defense
- Awarded
- to Newalen, LLC
- Set-aside
- Total Small Business
Opportunity facts
- Contract number
- W912DW-16-P-0071 Federal contract award
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Not on record
- Place of performance
- LaPush, Washington 98350, United States
Notice details come from SAM.gov. Updated .
Notice text
4 versions
Update #4 · Latest ·
Added: May 16, 2016 5:34 pm
Modified: May 23, 2016 4:40 pmTrack Changes
Amendment to W912DW-16-Q-0047 Quillayute Training Wall Repair
Added Engineering Estimate to the package
Added drawing to the package
Changed status from Draft to Released RFQ.
In Section 06 13 33, para 2.1 a) 3) (a) Rough is defined as a minimum of 1/8" larger than the surface size.
Made change to Section 06 13 33, para 2.1 a) 4) (a)
Made change to Section 03 13 33, para 2.1 a) 6) (a)
Closing Date for bids is now 31 May 2016 at 2:00 PM (Pacific)
Update #3 ·
Added: May 16, 2016 5:34 pm
Modified: May 17, 2016 2:50 pmTrack Changes
Amendment to W912DW-16-Q-0047
Quillayute Training Wall Repair
Added Engineering Estimate to the package
Added drawing to the package
Changed status from Draft to Released RFQ.
Made change to Section 06 13 33, para 2.1 a) 4) (a)
Update #2 ·
Added: May 16, 2016 5:34 pm
Amendment to W912DW-16-Q-0047
Quillayute Training Wall Repair
Added Engineering Estimate to the package
Added drawing to the package
Changed status from Draft to Released RFQ.
Update #1 ·
Added: May 13, 2016 12:48 pm This project includes all material, labor, and equipment for the removal and replacement of broken and missing timber planking along the breakwater-training wall at the Quillayute River in La Push, Washington. Over time, several planks have deteriorated and broken allowing water and sediment to enter the boat basin. The objective of this project is to restore the breakwater-training wall by ensuring all missing and broken planking are replaced with new timber planking.
Attachments
| File | Type | Posted |
|---|---|---|
| A.02.01_-_Combined_Synopsis-Solicitation_-_W912DW-16-Q-0047_Amendment_3.pdf | ||
| A.02.01_-_Combined_Synopsis-Solicitation_-_W912DW-16-Q-0047_Amendment_2.pdf | ||
| A.02.01_-_Combined_Synopsis-Solicitation_-_W912DW-16-Q-0047_Ammendment.pdf | ||
| A.02.01_-_Combined_Synopsis-Solicitation_-_W912DW-16-Q-0047.pdf |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity