Pump House Stabilization

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
1240LT24Q0020
Agency
Forest Service Department of Agriculture
Responses due
Set-aside
Total Small Business

Opportunity facts

NAICS code
238290 Other Building Equipment Contractors
PSC
Z2JZ Repair Or Alteration Of Miscellaneous Buildings
Place of performance
Halsey, Nebraska 69142, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation seeks quotes to stabilize a pump house building located on the Bessey Nursery Complex in Halsey, Nebraska. The USDA Forest Service is soliciting quotes to stabilize the existing pump house structure using push piers or equivalent methods to prevent further movement by March 15, 2024. Quotes will be evaluated based on price, past performance, capacity, management capabilities, and a completed technical approach questionnaire, with price being the most important factor. Quotes are due by January 26, 2024 and shall include pricing for mobilization and stabilization work.

This is a total small business set-aside under NAICS code 238990 for specialty trade contractors. The place of performance is the Bessey Nursery Complex located two miles west of Halsey in Thomas County, Nebraska. A pre-proposal site visit is scheduled for January 19, 2024. The construction period runs from January 29 to March 15, 2024.

Notice text

3 versions

Update #3 · Latest ·

01/09/2024 - Additional information - I have received an answer for requests for pump house drawings and a geo-technical report. I have attached what the COR has provided me.

From the COR: 

"We did not have any geo-technical survey or report conducted of the site. The work site is located in the sandhills, so sand is the predominate soil type. I have attached a single report from Web Soil Survey, but there are numerous reports that can be generated on the site. Also, the lat/long for the pumphouse is 41.901722, -100.306267 so that potential bidders are can generate reports at their discretion.

We also do not have as-built drawings for the existing pumphouse, we were not given any by the contractor that initially installed the building. It is a precast concrete structure that is approximately 11’ wide by 12’ long and 10’ tall with 4” thick walls and a 5” thick floor. "

01/09/2024 - AMENDMENT 0001 - The purpose of this amendment is to change the site visit date from January 12th, 2024 at 1300 (MT) to January 19th at 1300 (MT) / 1400 (CT) due to concerns with weather conditions and COVID community levels. There are no other changes. The due date for offers is not extended.


PROJECT NAME: PUMP HOUSE STABILIZATION

DESCRIPTION OF WORK: WORK FOR THIS PROJECT CONSISTS OF STABILIZE THE BESSEY NURSERY PUMP HOUSE USING PUSH PIERS OR EQUIVALENT, TO PREVENT THE BUILDING FROM MOVING. THERE ARE 3 EXISTING WATERLINES THAT RUN OUT THE SOUTH AND EAST SIDE OF THE BUILDING ALONG WITH ELECTRICAL LINES.

LOCATION: THIS PROJECT IS LOCATED ON THE BESSEY NURSERY COMPLEX ON THE NEBRASKA NATIONAL FORESTS AND GRASSLANDS LOCATED TWO (2) MILES WEST OF HALSEY, NEBRASKA. (THOMAS COUNTY, NE)

PRE-PROPOSAL SITE VISIT SCHEDULED? YES, SEE SECTION L.

SEND PROPOSALS TO WESTLEY.BISSON@USDA.GOV. DO NOT MAIL PROPOSALS. 

*REMEMBER TO INCLUDE THE COMPLETED J.3 EXPERIENCE QUESTIONNAIRE WITH YOUR PROPOSAL

Update #2 ·

01/09/2024 - AMENDMENT 0001 - The purpose of this amendment is to change the site visit date from January 12th, 2024 at 1300 (MT) to January 19th at 1300 (MT) / 1400 (CT) due to concerns with weather conditions and COVID community levels. There are no other changes. The due date for offers is not extended.


PROJECT NAME: PUMP HOUSE STABILIZATION

DESCRIPTION OF WORK: WORK FOR THIS PROJECT CONSISTS OF STABILIZE THE BESSEY NURSERY PUMP HOUSE USING PUSH PIERS OR EQUIVALENT, TO PREVENT THE BUILDING FROM MOVING. THERE ARE 3 EXISTING WATERLINES THAT RUN OUT THE SOUTH AND EAST SIDE OF THE BUILDING ALONG WITH ELECTRICAL LINES.

LOCATION: THIS PROJECT IS LOCATED ON THE BESSEY NURSERY COMPLEX ON THE NEBRASKA NATIONAL FORESTS AND GRASSLANDS LOCATED TWO (2) MILES WEST OF HALSEY, NEBRASKA. (THOMAS COUNTY, NE)

PRE-PROPOSAL SITE VISIT SCHEDULED? YES, SEE SECTION L.

SEND PROPOSALS TO WESTLEY.BISSON@USDA.GOV. DO NOT MAIL PROPOSALS. 

*REMEMBER TO INCLUDE THE COMPLETED J.3 EXPERIENCE QUESTIONNAIRE WITH YOUR PROPOSAL

Update #1 ·

PROJECT NAME: PUMP HOUSE STABILIZATION

DESCRIPTION OF WORK: WORK FOR THIS PROJECT CONSISTS OF STABILIZE THE BESSEY NURSERY PUMP HOUSE USING PUSH PIERS OR EQUIVALENT, TO PREVENT THE BUILDING FROM MOVING. THERE ARE 3 EXISTING WATERLINES THAT RUN OUT THE SOUTH AND EAST SIDE OF THE BUILDING ALONG WITH ELECTRICAL LINES.

LOCATION: THIS PROJECT IS LOCATED ON THE BESSEY NURSERY COMPLEX ON THE NEBRASKA NATIONAL FORESTS AND GRASSLANDS LOCATED TWO (2) MILES WEST OF HALSEY, NEBRASKA. (THOMAS COUNTY, NE)

PRE-PROPOSAL SITE VISIT SCHEDULED? YES, SEE SECTION L.

SEND PROPOSALS TO WESTLEY.BISSON@USDA.GOV. DO NOT MAIL PROPOSALS. 

*REMEMBER TO INCLUDE THE COMPLETED J.3 EXPERIENCE QUESTIONNAIRE WITH YOUR PROPOSAL

Attachments

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
Pump House Stabilization Award Award Notice
Pump House Stabilization This notice · Latest solicitation Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity