Courts Alterations, Columbus Courthouse
Closed Solicitation Posted
- Solicitation number
- 47PE0220R0003
- Agency
- Region 4 Public Buildings Service, General Services Administration
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Place of performance
- Columbus GA 31901 USA
Notice details come from SAM.gov. Updated .
About this opportunity
The General Services Administration Public Buildings Service Region 4 is soliciting proposals to provide design and construction services for courts alterations at the U.S. Post Office and Federal Courthouse located in Columbus, Georgia. Offerors must complete the design phase within 60 calendar days of the notice to proceed and finish construction within 120 calendar days thereafter. Proposals are due by September 24, 2020 and will be evaluated based on technical acceptability and price, with award intended for the lowest priced technically acceptable offer. A pre-bid site visit is scheduled for August 5, 2020 and questions are due by August 12, 2020.
The estimated price range for the project is between $250,000 and $500,000. The NAICS code for this procurement is 236220 for commercial and institutional building construction. There is no set-aside designation. The successful offeror must furnish performance and payment bonds valued at 100% of the agreed contract price within 10 days of award. Liquidated damages of $380.59 per day may be assessed for any project completion delays at the place of performance, which is 120 12th Street in Columbus, Georgia.
Notice text
7 versions
Update #7 · Latest ·
Amendment 0006 - The purpose of Amendment 0006 is to provide you with responses to questions submitted after the site visit for this project. Questions submitted after the cut off date of 09/14/2020 @1:00PM were not responded too. As a reminder, your proposal is due on 09/24/2020 @3:00PM (EST)>
This is an unofficial notice reqarding the change of the Proposal Due Date from 09/21/2020 @1:00PM (EST) to 09/24/2020 @3:00 PM. The official Amendment 0005 document will be posted later today.
Amendment 0004- A SITE VISIT is now scheduled for 09/10/2020 @10:30-12:00PM and the proposal due date changed from 09/16/2020 to 09/21/2020. Two documents were revised with changes highlighted in bold red font; Reguest for Proposal and the SAT GC LPTA SOL R0003. IMPORTANT ! Only 2 people per company is allowed to attend the site visit and Masks are MANDATORY, no exception!
Amendment 0003 - The purpose of this amendment is to extend the proposal due date from 08/28/2020 to 09/16/2020. Amendment 0004 will be issued next week with a SITE VISIT Date for this project.
Amendment 0002 - The purpose of this amendment is to correct dates listed in the SAT GC LPTA document.
NOTE: The Site Visit scheduled for 11/05/2020 has been cancelled. Review the details in Amendment 0001
REQUEST FOR PROPOSAL (RFP)
RFP Issue Date: July 29, 2020
Proposal Due Date: August 28, 2020 /1:00 PM EST
Issued By: Wanda George-James, Contracting Officer
U.S. general Services Administration PBS, Acquisition Division (4PQG) 77 Forsyth Street, Atlanta, GA 30303 (404)772-8075 (cell) wanda.george-james@gsa.gov
Reference Document: Purchase Request, EQ4PPG-20-0003
Solicitation #: 47PE0220R0003
Project Title: Courts Alterations, Columbus Courthouse
Location of Work: U.S. Post Office & Federal Courthouse
Address: 120 12th Street , Columbus, GA 31901
Estimated Price Range: Between $250,000 and $500,000
Period of Performance: Design Phase - 60 Calendar Days (after NTP)
Construction Phase - 120 Calendar Days (after Design Phase)
Site Visit/ Pre-Bid Meeting: August 05, 2020 ( Tenative. subject to change)
Time - 10:30 AM
Place - Columbus, GA (address shown above)
POC – Shonda Piper-Cameron, GSA Project Manager
(404) 431-0121 (Cell): (404) 331-0847 (Office)
email: shonda.piper-cameron@gsa.gov
General Information
You are invited to submit a proposal for the performance of the above referenced work. The Statement of Work dated 07/22/2019 is included with all other documents.
Proposal Submission: You are requested to submit your proposal electronically to Tyrone McClain, email :tyrone.mcclain@gsa.gov on or before the proposal due date of August 28, 2020@ 1: 00PM (EST).
Request for Clarifications: All questions and requests for clarifications should be submitted in writing by 1:00 PM, August 12, 2020. Please submit requests and inquiries to Wanda George-James, Contracting Officer at wanda.george-james@gsa.gov and Contract Specialist, Tyrone McClain at tyrone.mcclain@gsa.gov.
Certificate of Insurance - Successful Offeror will be required to submit a Certificate of Insurance in accordance with FAR Clause 52.228.5 within 10 days of NTP.
Bid Guarantee: A Bid Guarantee in the amount of 20% of the Bid price not to exceed $3million dollars is required and should be submitted along with the Offeror’s Proposal. Failure to furnish a bid guarantee in the proper form and amount, by the time set for receipt of proposals, may be cause for rejection of the proposal.
Performance and Payment Bonds (FAR 52.228-15) - The successful Offeror shall be required to provide a Performance and Payment Bond for this requirement. The amount of the Performance and Payment Bond shall be 100 percent of the agreed upon price. Submission of the Performance and Payment Bonds are required within ten (10) days of the award. The performance and payment Bonds shall provide for the full contract performance period plus a one-year period.
Liquidated Damages: Offeror will assessed $380.59 a day of liquidated damages for project completion delays.
Award: The Government intends to award a firm fixed-price contract resulting from this solicitation (RFP) to the responsible Offeror whose proposal represents the best value from the selection of the technically acceptable proposal with the lowest evaluated price.
This request for proposal does not commit the Government to pay any cost incurred in the preparation or submission of a proposal.
Update #6 ·
This is an unofficial notice reqarding the change of the Proposal Due Date from 09/21/2020 @1:00PM (EST) to 09/24/2020 @3:00 PM. The official Amendment 0005 document will be posted later today.
Amendment 0004- A SITE VISIT is now scheduled for 09/10/2020 @10:30-12:00PM and the proposal due date changed from 09/16/2020 to 09/21/2020. Two documents were revised with changes highlighted in bold red font; Reguest for Proposal and the SAT GC LPTA SOL R0003. IMPORTANT ! Only 2 people per company is allowed to attend the site visit and Masks are MANDATORY, no exception!
Amendment 0003 - The purpose of this amendment is to extend the proposal due date from 08/28/2020 to 09/16/2020. Amendment 0004 will be issued next week with a SITE VISIT Date for this project.
Amendment 0002 - The purpose of this amendment is to correct dates listed in the SAT GC LPTA document.
NOTE: The Site Visit scheduled for 11/05/2020 has been cancelled. Review the details in Amendment 0001
REQUEST FOR PROPOSAL (RFP)
RFP Issue Date: July 29, 2020
Proposal Due Date: August 28, 2020 /1:00 PM EST
Issued By: Wanda George-James, Contracting Officer
U.S. general Services Administration PBS, Acquisition Division (4PQG) 77 Forsyth Street, Atlanta, GA 30303 (404)772-8075 (cell) wanda.george-james@gsa.gov
Reference Document: Purchase Request, EQ4PPG-20-0003
Solicitation #: 47PE0220R0003
Project Title: Courts Alterations, Columbus Courthouse
Location of Work: U.S. Post Office & Federal Courthouse
Address: 120 12th Street , Columbus, GA 31901
Estimated Price Range: Between $250,000 and $500,000
Period of Performance: Design Phase - 60 Calendar Days (after NTP)
Construction Phase - 120 Calendar Days (after Design Phase)
Site Visit/ Pre-Bid Meeting: August 05, 2020 ( Tenative. subject to change)
Time - 10:30 AM
Place - Columbus, GA (address shown above)
POC – Shonda Piper-Cameron, GSA Project Manager
(404) 431-0121 (Cell): (404) 331-0847 (Office)
email: shonda.piper-cameron@gsa.gov
General Information
You are invited to submit a proposal for the performance of the above referenced work. The Statement of Work dated 07/22/2019 is included with all other documents.
Proposal Submission: You are requested to submit your proposal electronically to Tyrone McClain, email :tyrone.mcclain@gsa.gov on or before the proposal due date of August 28, 2020@ 1: 00PM (EST).
Request for Clarifications: All questions and requests for clarifications should be submitted in writing by 1:00 PM, August 12, 2020. Please submit requests and inquiries to Wanda George-James, Contracting Officer at wanda.george-james@gsa.gov and Contract Specialist, Tyrone McClain at tyrone.mcclain@gsa.gov.
Certificate of Insurance - Successful Offeror will be required to submit a Certificate of Insurance in accordance with FAR Clause 52.228.5 within 10 days of NTP.
Bid Guarantee: A Bid Guarantee in the amount of 20% of the Bid price not to exceed $3million dollars is required and should be submitted along with the Offeror’s Proposal. Failure to furnish a bid guarantee in the proper form and amount, by the time set for receipt of proposals, may be cause for rejection of the proposal.
Performance and Payment Bonds (FAR 52.228-15) - The successful Offeror shall be required to provide a Performance and Payment Bond for this requirement. The amount of the Performance and Payment Bond shall be 100 percent of the agreed upon price. Submission of the Performance and Payment Bonds are required within ten (10) days of the award. The performance and payment Bonds shall provide for the full contract performance period plus a one-year period.
Liquidated Damages: Offeror will assessed $380.59 a day of liquidated damages for project completion delays.
Award: The Government intends to award a firm fixed-price contract resulting from this solicitation (RFP) to the responsible Offeror whose proposal represents the best value from the selection of the technically acceptable proposal with the lowest evaluated price.
This request for proposal does not commit the Government to pay any cost incurred in the preparation or submission of a proposal.
Update #5 ·
Amendment 0004- A SITE VISIT is now scheduled for 09/10/2020 @10:30-12:00PM and the proposal due date changed from 09/16/2020 to 09/21/2020. Two documents were revised with changes highlighted in bold red font; Reguest for Proposal and the SAT GC LPTA SOL R0003. IMPORTANT ! Only 2 people per company is allowed to attend the site visit and Masks are MANDATORY, no exception!
Amendment 0003 - The purpose of this amendment is to extend the proposal due date from 08/28/2020 to 09/16/2020. Amendment 0004 will be issued next week with a SITE VISIT Date for this project.
Amendment 0002 - The purpose of this amendment is to correct dates listed in the SAT GC LPTA document.
NOTE: The Site Visit scheduled for 11/05/2020 has been cancelled. Review the details in Amendment 0001
REQUEST FOR PROPOSAL (RFP)
RFP Issue Date: July 29, 2020
Proposal Due Date: August 28, 2020 /1:00 PM EST
Issued By: Wanda George-James, Contracting Officer
U.S. general Services Administration PBS, Acquisition Division (4PQG) 77 Forsyth Street, Atlanta, GA 30303 (404)772-8075 (cell) wanda.george-james@gsa.gov
Reference Document: Purchase Request, EQ4PPG-20-0003
Solicitation #: 47PE0220R0003
Project Title: Courts Alterations, Columbus Courthouse
Location of Work: U.S. Post Office & Federal Courthouse
Address: 120 12th Street , Columbus, GA 31901
Estimated Price Range: Between $250,000 and $500,000
Period of Performance: Design Phase - 60 Calendar Days (after NTP)
Construction Phase - 120 Calendar Days (after Design Phase)
Site Visit/ Pre-Bid Meeting: August 05, 2020 ( Tenative. subject to change)
Time - 10:30 AM
Place - Columbus, GA (address shown above)
POC – Shonda Piper-Cameron, GSA Project Manager
(404) 431-0121 (Cell): (404) 331-0847 (Office)
email: shonda.piper-cameron@gsa.gov
General Information
You are invited to submit a proposal for the performance of the above referenced work. The Statement of Work dated 07/22/2019 is included with all other documents.
Proposal Submission: You are requested to submit your proposal electronically to Tyrone McClain, email :tyrone.mcclain@gsa.gov on or before the proposal due date of August 28, 2020@ 1: 00PM (EST).
Request for Clarifications: All questions and requests for clarifications should be submitted in writing by 1:00 PM, August 12, 2020. Please submit requests and inquiries to Wanda George-James, Contracting Officer at wanda.george-james@gsa.gov and Contract Specialist, Tyrone McClain at tyrone.mcclain@gsa.gov.
Certificate of Insurance - Successful Offeror will be required to submit a Certificate of Insurance in accordance with FAR Clause 52.228.5 within 10 days of NTP.
Bid Guarantee: A Bid Guarantee in the amount of 20% of the Bid price not to exceed $3million dollars is required and should be submitted along with the Offeror’s Proposal. Failure to furnish a bid guarantee in the proper form and amount, by the time set for receipt of proposals, may be cause for rejection of the proposal.
Performance and Payment Bonds (FAR 52.228-15) - The successful Offeror shall be required to provide a Performance and Payment Bond for this requirement. The amount of the Performance and Payment Bond shall be 100 percent of the agreed upon price. Submission of the Performance and Payment Bonds are required within ten (10) days of the award. The performance and payment Bonds shall provide for the full contract performance period plus a one-year period.
Liquidated Damages: Offeror will assessed $380.59 a day of liquidated damages for project completion delays.
Award: The Government intends to award a firm fixed-price contract resulting from this solicitation (RFP) to the responsible Offeror whose proposal represents the best value from the selection of the technically acceptable proposal with the lowest evaluated price.
This request for proposal does not commit the Government to pay any cost incurred in the preparation or submission of a proposal.
Update #4 ·
Amendment 0003 - The purpose of this amendment is to extend the proposal due date from 08/28/2020 to 09/16/2020. Amendment 0004 will be issued next week with a SITE VISIT Date for this project.
Amendment 0002 - The purpose of this amendment is to correct dates listed in the SAT GC LPTA document.
NOTE: The Site Visit scheduled for 11/05/2020 has been cancelled. Review the details in Amendment 0001
REQUEST FOR PROPOSAL (RFP)
RFP Issue Date: July 29, 2020
Proposal Due Date: August 28, 2020 /1:00 PM EST
Issued By: Wanda George-James, Contracting Officer
U.S. general Services Administration PBS, Acquisition Division (4PQG) 77 Forsyth Street, Atlanta, GA 30303 (404)772-8075 (cell) wanda.george-james@gsa.gov
Reference Document: Purchase Request, EQ4PPG-20-0003
Solicitation #: 47PE0220R0003
Project Title: Courts Alterations, Columbus Courthouse
Location of Work: U.S. Post Office & Federal Courthouse
Address: 120 12th Street , Columbus, GA 31901
Estimated Price Range: Between $250,000 and $500,000
Period of Performance: Design Phase - 60 Calendar Days (after NTP)
Construction Phase - 120 Calendar Days (after Design Phase)
Site Visit/ Pre-Bid Meeting: August 05, 2020 ( Tenative. subject to change)
Time - 10:30 AM
Place - Columbus, GA (address shown above)
POC – Shonda Piper-Cameron, GSA Project Manager
(404) 431-0121 (Cell): (404) 331-0847 (Office)
email: shonda.piper-cameron@gsa.gov
General Information
You are invited to submit a proposal for the performance of the above referenced work. The Statement of Work dated 07/22/2019 is included with all other documents.
Proposal Submission: You are requested to submit your proposal electronically to Tyrone McClain, email :tyrone.mcclain@gsa.gov on or before the proposal due date of August 28, 2020@ 1: 00PM (EST).
Request for Clarifications: All questions and requests for clarifications should be submitted in writing by 1:00 PM, August 12, 2020. Please submit requests and inquiries to Wanda George-James, Contracting Officer at wanda.george-james@gsa.gov and Contract Specialist, Tyrone McClain at tyrone.mcclain@gsa.gov.
Certificate of Insurance - Successful Offeror will be required to submit a Certificate of Insurance in accordance with FAR Clause 52.228.5 within 10 days of NTP.
Bid Guarantee: A Bid Guarantee in the amount of 20% of the Bid price not to exceed $3million dollars is required and should be submitted along with the Offeror’s Proposal. Failure to furnish a bid guarantee in the proper form and amount, by the time set for receipt of proposals, may be cause for rejection of the proposal.
Performance and Payment Bonds (FAR 52.228-15) - The successful Offeror shall be required to provide a Performance and Payment Bond for this requirement. The amount of the Performance and Payment Bond shall be 100 percent of the agreed upon price. Submission of the Performance and Payment Bonds are required within ten (10) days of the award. The performance and payment Bonds shall provide for the full contract performance period plus a one-year period.
Liquidated Damages: Offeror will assessed $380.59 a day of liquidated damages for project completion delays.
Award: The Government intends to award a firm fixed-price contract resulting from this solicitation (RFP) to the responsible Offeror whose proposal represents the best value from the selection of the technically acceptable proposal with the lowest evaluated price.
This request for proposal does not commit the Government to pay any cost incurred in the preparation or submission of a proposal.
Update #3 ·
Amendment 0002 - The purpose of this amendment is to correct dates listed in the SAT GC LPTA document.
NOTE: The Site Visit scheduled for 11/05/2020 has been cancelled. Review the details in Amendment 0001
REQUEST FOR PROPOSAL (RFP)
RFP Issue Date: July 29, 2020
Proposal Due Date: August 28, 2020 /1:00 PM EST
Issued By: Wanda George-James, Contracting Officer
U.S. general Services Administration PBS, Acquisition Division (4PQG) 77 Forsyth Street, Atlanta, GA 30303 (404)772-8075 (cell) wanda.george-james@gsa.gov
Reference Document: Purchase Request, EQ4PPG-20-0003
Solicitation #: 47PE0220R0003
Project Title: Courts Alterations, Columbus Courthouse
Location of Work: U.S. Post Office & Federal Courthouse
Address: 120 12th Street , Columbus, GA 31901
Estimated Price Range: Between $250,000 and $500,000
Period of Performance: Design Phase - 60 Calendar Days (after NTP)
Construction Phase - 120 Calendar Days (after Design Phase)
Site Visit/ Pre-Bid Meeting: August 05, 2020 ( Tenative. subject to change)
Time - 10:30 AM
Place - Columbus, GA (address shown above)
POC – Shonda Piper-Cameron, GSA Project Manager
(404) 431-0121 (Cell): (404) 331-0847 (Office)
email: shonda.piper-cameron@gsa.gov
General Information
You are invited to submit a proposal for the performance of the above referenced work. The Statement of Work dated 07/22/2019 is included with all other documents.
Proposal Submission: You are requested to submit your proposal electronically to Tyrone McClain, email :tyrone.mcclain@gsa.gov on or before the proposal due date of August 28, 2020@ 1: 00PM (EST).
Request for Clarifications: All questions and requests for clarifications should be submitted in writing by 1:00 PM, August 12, 2020. Please submit requests and inquiries to Wanda George-James, Contracting Officer at wanda.george-james@gsa.gov and Contract Specialist, Tyrone McClain at tyrone.mcclain@gsa.gov.
Certificate of Insurance - Successful Offeror will be required to submit a Certificate of Insurance in accordance with FAR Clause 52.228.5 within 10 days of NTP.
Bid Guarantee: A Bid Guarantee in the amount of 20% of the Bid price not to exceed $3million dollars is required and should be submitted along with the Offeror’s Proposal. Failure to furnish a bid guarantee in the proper form and amount, by the time set for receipt of proposals, may be cause for rejection of the proposal.
Performance and Payment Bonds (FAR 52.228-15) - The successful Offeror shall be required to provide a Performance and Payment Bond for this requirement. The amount of the Performance and Payment Bond shall be 100 percent of the agreed upon price. Submission of the Performance and Payment Bonds are required within ten (10) days of the award. The performance and payment Bonds shall provide for the full contract performance period plus a one-year period.
Liquidated Damages: Offeror will assessed $380.59 a day of liquidated damages for project completion delays.
Award: The Government intends to award a firm fixed-price contract resulting from this solicitation (RFP) to the responsible Offeror whose proposal represents the best value from the selection of the technically acceptable proposal with the lowest evaluated price.
This request for proposal does not commit the Government to pay any cost incurred in the preparation or submission of a proposal.
Update #2 ·
NOTE: The Site Visit scheduled for 11/05/2020 has been cancelled. Review the details in Amendment 0001
REQUEST FOR PROPOSAL (RFP)
RFP Issue Date: July 29, 2020
Proposal Due Date: August 28, 2020 /1:00 PM EST
Issued By: Wanda George-James, Contracting Officer
U.S. general Services Administration PBS, Acquisition Division (4PQG) 77 Forsyth Street, Atlanta, GA 30303 (404)772-8075 (cell) wanda.george-james@gsa.gov
Reference Document: Purchase Request, EQ4PPG-20-0003
Solicitation #: 47PE0220R0003
Project Title: Courts Alterations, Columbus Courthouse
Location of Work: U.S. Post Office & Federal Courthouse
Address: 120 12th Street , Columbus, GA 31901
Estimated Price Range: Between $250,000 and $500,000
Period of Performance: Design Phase - 60 Calendar Days (after NTP)
Construction Phase - 120 Calendar Days (after Design Phase)
Site Visit/ Pre-Bid Meeting: August 05, 2020 ( Tenative. subject to change)
Time - 10:30 AM
Place - Columbus, GA (address shown above)
POC – Shonda Piper-Cameron, GSA Project Manager
(404) 431-0121 (Cell): (404) 331-0847 (Office)
email: shonda.piper-cameron@gsa.gov
General Information
You are invited to submit a proposal for the performance of the above referenced work. The Statement of Work dated 07/22/2019 is included with all other documents.
Proposal Submission: You are requested to submit your proposal electronically to Tyrone McClain, email :tyrone.mcclain@gsa.gov on or before the proposal due date of August 28, 2020@ 1: 00PM (EST).
Request for Clarifications: All questions and requests for clarifications should be submitted in writing by 1:00 PM, August 12, 2020. Please submit requests and inquiries to Wanda George-James, Contracting Officer at wanda.george-james@gsa.gov and Contract Specialist, Tyrone McClain at tyrone.mcclain@gsa.gov.
Certificate of Insurance - Successful Offeror will be required to submit a Certificate of Insurance in accordance with FAR Clause 52.228.5 within 10 days of NTP.
Bid Guarantee: A Bid Guarantee in the amount of 20% of the Bid price not to exceed $3million dollars is required and should be submitted along with the Offeror’s Proposal. Failure to furnish a bid guarantee in the proper form and amount, by the time set for receipt of proposals, may be cause for rejection of the proposal.
Performance and Payment Bonds (FAR 52.228-15) - The successful Offeror shall be required to provide a Performance and Payment Bond for this requirement. The amount of the Performance and Payment Bond shall be 100 percent of the agreed upon price. Submission of the Performance and Payment Bonds are required within ten (10) days of the award. The performance and payment Bonds shall provide for the full contract performance period plus a one-year period.
Liquidated Damages: Offeror will assessed $380.59 a day of liquidated damages for project completion delays.
Award: The Government intends to award a firm fixed-price contract resulting from this solicitation (RFP) to the responsible Offeror whose proposal represents the best value from the selection of the technically acceptable proposal with the lowest evaluated price.
This request for proposal does not commit the Government to pay any cost incurred in the preparation or submission of a proposal.
Update #1 ·
REQUEST FOR PROPOSAL (RFP)
RFP Issue Date: July 29, 2020
Proposal Due Date: August 28, 2020 /1:00 PM EST
Issued By: Wanda George-James, Contracting Officer
U.S. general Services Administration PBS, Acquisition Division (4PQG) 77 Forsyth Street, Atlanta, GA 30303 (404)772-8075 (cell) wanda.george-james@gsa.gov
Reference Document: Purchase Request, EQ4PPG-20-0003
Solicitation #: 47PE0220R0003
Project Title: Courts Alterations, Columbus Courthouse
Location of Work: U.S. Post Office & Federal Courthouse
Address: 120 12th Street , Columbus, GA 31901
Estimated Price Range: Between $250,000 and $500,000
Period of Performance: Design Phase - 60 Calendar Days (after NTP)
Construction Phase - 120 Calendar Days (after Design Phase)
Site Visit/ Pre-Bid Meeting: August 05, 2020 ( Tenative. subject to change)
Time - 10:30 AM
Place - Columbus, GA (address shown above)
POC – Shonda Piper-Cameron, GSA Project Manager
(404) 431-0121 (Cell): (404) 331-0847 (Office)
email: shonda.piper-cameron@gsa.gov
General Information
You are invited to submit a proposal for the performance of the above referenced work. The Statement of Work dated 07/22/2019 is included with all other documents.
Proposal Submission: You are requested to submit your proposal electronically to Tyrone McClain, email :tyrone.mcclain@gsa.gov on or before the proposal due date of August 28, 2020@ 1: 00PM (EST).
Request for Clarifications: All questions and requests for clarifications should be submitted in writing by 1:00 PM, August 12, 2020. Please submit requests and inquiries to Wanda George-James, Contracting Officer at wanda.george-james@gsa.gov and Contract Specialist, Tyrone McClain at tyrone.mcclain@gsa.gov.
Certificate of Insurance - Successful Offeror will be required to submit a Certificate of Insurance in accordance with FAR Clause 52.228.5 within 10 days of NTP.
Bid Guarantee: A Bid Guarantee in the amount of 20% of the Bid price not to exceed $3million dollars is required and should be submitted along with the Offeror’s Proposal. Failure to furnish a bid guarantee in the proper form and amount, by the time set for receipt of proposals, may be cause for rejection of the proposal.
Performance and Payment Bonds (FAR 52.228-15) - The successful Offeror shall be required to provide a Performance and Payment Bond for this requirement. The amount of the Performance and Payment Bond shall be 100 percent of the agreed upon price. Submission of the Performance and Payment Bonds are required within ten (10) days of the award. The performance and payment Bonds shall provide for the full contract performance period plus a one-year period.
Liquidated Damages: Offeror will assessed $380.59 a day of liquidated damages for project completion delays.
Award: The Government intends to award a firm fixed-price contract resulting from this solicitation (RFP) to the responsible Offeror whose proposal represents the best value from the selection of the technically acceptable proposal with the lowest evaluated price.
This request for proposal does not commit the Government to pay any cost incurred in the preparation or submission of a proposal.
Attachments
Show all 22
Notice history
| Notice | Type | Posted |
|---|---|---|
| Courts Alterations, Columbus Courthouse | Solicitation | |
| Courts Alterations, Columbus Courthouse | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity