CA YOSE 1022(1) Valley Day-Use Parking Phase II

Pre-Solicitation Posted

This opportunity was awarded. See the award notice from , or the latest solicitation from .

Solicitation number
6982AF22B000004
Agency
Federal Highway Administration Department of Transportation
Responses due
Not on record
Set-aside
No set-aside

Opportunity facts

NAICS code
237310 Highway, Street, and Bridge Construction
PSC
Y1LB Construction Of Highways, Roads, Streets, Bridges, And Railways
Place of performance
Yosemite National Park, California 95389, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This pre-solicitation notice is for the CA YOSE 1022(1) Valley Day-Use Parking Phase II project located in Yosemite Valley within Yosemite National Park, California. The Department of Transportation Federal Highway Administration will construct a new 250-space parking lot and improve drainage and paving in an existing 350-space lot. The project aims to increase day-use parking capacity and improve pedestrian access and safety. The estimated cost is between $3-5 million and construction is scheduled from March to August 2022.

There is no set-aside designation. The project involves approximately 3,000 tons of asphalt pavement, 2,500 tons of aggregate, 11,000 square yards of roadbed reconditioning and other materials. The cost estimate is $3-5 million and construction will occur between March and August 2022. Questions are due by January 2022, with bids opening in February and anticipated award also in February.

Notice text

CA YOSE 1022(1) Valley Day-Use Parking Phase II

THIS PROJECT WILL BE ADVERTISED AS FULL AND OPEN

THIS IS NOT A REQUEST FOR BID - PLANS AND SPECIFICATIONS ARE NOT AVAILABLE.

PROJECT DESCRIPTION:   The CA FTNP/NPS YOSE 1022(1) Valley Day-Use Parking Phase II Project is located in Yosemite Valley within Yosemite National Park (YNP), CA.

This project will consist of the construction of a 250-space parking lot adjacent to the existing Yosemite Village Store parking lot in a portion of the space formally occupied by the Concessioner General Office building which was removed in 2021.  This parking lot will be located adjacent to the new Yosemite Valley Welcome Center. The project includes drainage improvements and paving of the unpaved portions of the 350-space Valley Day-Use South parking lot originally constructed in 2017, within Yosemite Valley in Yosemite National Park, CA.  This project increases the day-use parking capacity at the primary arrival point for incoming motorists who have no campsite or hotel reservations and improves pedestrian circulation and access from the parking lots to the visitor center in the Yosemite Village area.

The project will improve visitor experience and safety by providing additional day-use parking and pedestrian connections to the YNP Village walking mall and Visitor Center areas within Yosemite Valley.  All of the work is occurring in cultural and natural resource sensitive areas and there are numerous environmental constraints that will affect the construction schedule and type of operations. 

This project includes the following elements: 

Schedule A:  North Parking Lot

Option X:  South Parking Lot

SIGNIFICANT QUANTITIES:

  • 3,000 tons of asphalt concrete pavement, type 1,
  • 2,500 tons of roadway aggregate,
  • 11,000 square yards of roadbed reconditioning,
  • 1,000 cubic yards of roadway embankment,
  • 2,000 linear feet of concrete curb,
  • 1,500 linear feet of concrete gutter, and
  • 400 square yards of concrete sidewalk

MISCELLANEOUS:   General scope of improvement is to pulverize the existing section and place a 3-inch HACP section on the reclaimed 6 inches of pulverized existing material, raising the vertical profile of the road by 3 inches for the entire 7-mile corridor and minor shoulder widening (1-foot paved). Proposed improvements also include minor alignment and grade changes, signing and striping enhancements, drainage improvements, and other safety improvements.

COST RANGE:  The proposed project is estimated at a cost between $3,000,000 and $5,000,000.

CONSTRUCTION DURATION:  Construction is anticipated between  March 2022 and August 2022

ADDITIONAL INFORMATION:

Anticipated Advertisement:  January 2022

Anticipated Bid Opening:  February 2022

Anticipated Award: February 2022

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
CA YOSE 1022(1) Valley Day-Use Parking Phase II Award Award Notice
CA YOSE 1022(1) Valley Day-Use Parking Phase II Latest solicitation Solicitation
CA YOSE 1022(1) Valley Day-Use Parking Phase II This notice Pre-Solicitation
CA YOSE 1022(1) Valley Day-Use Parking Phase II Original Pre-Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity