B-1 Bomb Rack Unit (BRU) - 56 Modification

Pre-Solicitation Posted

This opportunity was awarded. See the award notice from , or the latest solicitation from .

Solicitation number
FA8107-18-R-0007
Agency
AFLCMC Tinker AFB Lifecycle Management Center, Department of Defense
Responses due
Not on record
Set-aside
No set-aside

Opportunity facts

NAICS code
336411 Aircraft Manufacturing
PSC
Not on record

Notice details come from SAM.gov. Updated .

Notice text

5 versions

Update #5 · Latest ·

Added: Jun 22, 2018 11:46 am  

SYNOPSIS


1.            Action Code: Unknown


2.            Date: 22 Jun


3.            Year: 2018


4.            Contracting Office Zip Code:  73145


5.            Product or Service Code:  R - Professional, Administrative, and Management Support


6.            Contracting Office Address:  3001 Staff Drive, Post 2AG85B, Tinker AFB, OK


7.            Subject:  B-1 Bomb Rack Unit (BRU) - 56 Modification


8.            Proposed Solicitation Number:  FA8107-18-R-0007


9.            Estimated Solicitation Open Date:  11 Jul 18


                Estimated Closing Response Date: 10 Sep 18 (60 days)


10.          Contracting Officer:  Kristen A Carter


11.          Contract Award & Solicitation Number:  Not Applicable


12.          Contract Award Dollar Amount:  TBD


13.          Contract Line Item Numbers (CLINs) are described below.


14.          Anticipated Contract Award Date:  Apr 19


15.          Contractor:  TBD


16.          Description:


A single award, definitive C-type contract vehicle is contemplated.  The overall period of performance for this effort is four and a half years.   There will be two phases of this acquisition.  The first phase is Engineering & Manufacturing Development (EMD).  The second phase is the production phase.  This phase will not start until EMD has been approved.  Cost-Plus-Fixed-Fee (CPFF), Firm-Fixed-Price (FFP), and Cost Reimbursable (CR) CLINs are anticipated for contract type. 


Supply:  Non-Commercial


The Air Force intends to solicit and issue a contract for the B-1 Bomb Rack Unit (BRU) - 56 Modification at Tinker AFB, OK.  The Contractor shall provide all requirements listed in accordance with (IAW) the Statement of Work (SOW) and Systems Requirements Document (SRD).


Estimated Period of Performance:


EMD: Apr 19 - Apr 21


                Production: May 21 - Sep 23


17.          Place of Contract Performance:  TBD


18.          Set-Aside Status:  N/A - This is Full & Open Competition


19.          NAICS Code:  336411


SAM Registration is required.


CLIN Details:


Line Item: 0001


NSN: R425 Engineering & Manufacturing Development (EMD)


 


Description: The Contractor shall provide EMD IAW SOW section 9.1. The contractor shall adhere to all the requir...


Supp. Description: The EMD phase includes modifying a quantity of 40 units per SOW 3.7.


Quantity: 1.0000 LO


 


Delivery: 30 APR 2019 Beginning On or Before


Quantity: 1.00


Unit of Issue: LO


 


Line Item: 0002


NSN: R425 Engineering & Manufacturing Development (EMD)


 


Description: The Fixed Fee portion of EMD is paid to the contractor when the successful completion of EMD has bee...


Quantity: 1.0000 LO


 


 


Line Item: 0003


NSN: R425 Travel for EMD


 


Description: Travel will be required as described in the SOW section 3.9. All travel will be on a Cost Reimburse...


Quantity: 1.0000 LO


 


Delivery: 30 APR 2019 Beginning On or Before


Quantity: 1.00


Unit of Issue: LO


 


Line Item: 0004


NSN: R425 Data for EMD


 


Description: In accordance with the Contract Data Requirements Lists (CDRLS) identified in the attached SOW, the ...


Quantity: 1.0000


 


Delivery: 30 APR 2019 Beginning On or Before


Quantity: 1.00


Unit of Issue: LO


 


Line Item: 0005


NSN: R425 Over and Above (O&A) for EMD


 


Description: IAW SOW section 3.8, O&A is defined as unforeseen circumstances not specifically addressed in the SO...


Quantity: 1.0000 LO


 


Delivery: 30 APR 2019 Beginning On or Before


Quantity: 1.00


Unit of Issue: LO


 


Line Item: 1001


NSN: R425 Production - Option I


 


Description: The Contractor shall adhere to the production requirements IAW SOW 11.1.


Supp. Description: The Government estimates a delivery rate of up to 40 each modifications per month; however, the deli...


Quantity: 1,004.0000 EA


 


Delivery: 01 MAY 2021 Beginning On or Before


Quantity: 1004.00


Unit of Issue: EA


 


Line Item: 1002


NSN: R425 Training - Option I


 


Description: In accordance with SOW section 7.0, the Contractor shall provide training to USAF personnel for the...


: 0.0000


 


 


Line Item: 1002AA


NSN: R425 Aircrew Training - Option I


 


Description: The Contractor shall provide aircrew training to include the Multi-Function Display (MFD) format cha...


Quantity: 1.0000 LO


 


Delivery: 01 MAY 2021 Beginning On or Before


Quantity: 1.00


Unit of Issue: LO


 


Line Item: 1002AB


NSN: R425 Load Crew Training - Option I


 


Description: The Contractor shall provide load crew training consisting of classroom instructions followed by han...


Quantity: 1.0000 LO


 


Delivery: 01 MAY 2021 Beginning On or Before


Quantity: 1.00


Unit of Issue: LO


 


Line Item: 1002AC


NSN: R425 Maintenance Training - Option I


 


Description: The Contractor shall provide maintenance procedures to include disassembly/reassembly of the rack wi...


Quantity: 1.0000 LO


 


Delivery: 01 MAY 2021 Beginning On or Before


Quantity: 1.00


Unit of Issue: LO


 


Line Item: 1003


NSN: R425 Travel - Option I


 


Description: Travel will be required as described in the SOW section 3.9. All travel will be on a Cost Reimburse...


Quantity: 1.0000 LO


 


Delivery: 01 MAY 2021 Beginning On or Before


Quantity: 1.00


Unit of Issue: LO


 


Line Item: 1004


NSN: R425 Data - Option I


 


Description: In accordance witht he Contract Data Requirements Lists (CDRLS) identified in the attached SOW, the ...


Quantity: 1.0000


 


Delivery: 01 MAY 2021 Beginning On or Before


Quantity: 1.00


Unit of Issue: LO


 


Line Item: 1005


NSN: R425 Over and Above (O&A) - Option I


 


Description: IAW SOW section 3.8, O&A is defined as unforeseen circumstances not specifically addressed in the SO...


Quantity: 1.0000 LO


 


Delivery: 01 MAY 2021


Quantity: 1.00


Unit of Issue: LO


 


Duration of Contract Period: Two years for EMD and two and a half years for Production


 


Electronic procedure will be used for this solicitation.


 

Update #4 ·

Added: Jun 04, 2018 11:40 am  

AMENDMENT 4


The attached Q&A addresses additional questions that were submitted via e-mail as part of the Pre-Solicitation Conference. 


Questions regarding this announcement shall be submitted by e-mail to the following Contracting Officer, Kristen Carter, kristen.carter@us.af.mil.  Verbal questions will not be accepted.  Questions shall not contain any proprietary information.  All answers to the questions will be posted to the FedBizOpps website. 

Update #3 ·

Added: May 31, 2018 2:40 pm  

AMENDMENT 3


The Government held a Pre-Solicitation Conference on May 23, 2018.  The questions that were asked during the Pre-Solicitation Conference or submitted via e-mail have all been reviewed.  The attached Q&A addresses those questions.


Please make sure to provide all questions to the Contracting Officer NTL 1 Jun 18 by 4:00 Central Standard Time (CST). 


Questions regarding this announcement shall be submitted by e-mail to the following Contracting Officer, Kristen Carter, kristen.carter@us.af.mil. Verbal questions will not be accepted.  Questions shall not contain any proprietary information.  All answers to the questions will be posted to the FedBizOpps website. 

Update #2 ·

Added: May 25, 2018 1:59 pm

  AMENDMENT 2


The Government held a Pre-Solicitation Conference on May 23, 2018.  The Pre-Solicitation Conference was held via Telecom.  Please make sure to provide all questions to the Contracting Officer NTL 1 Jun 18 by 4:00 Central Standard Time (CST).  Answers to the Questions will be posted to FedBizOpps as quickly as possible.


Please note that the CDRLs and GFE attachments will be posted at a later date. 


This amendment is to amend the DRAFT RFP and Pre-Solicitation charts.  The below have been changed in each document.


DRAFT RFP - The Government has updated the date and time shown on the front page under Section 9.  All Questions need to be submitted in writing to the Contracting Officer, Kristen Carter, by 1 Jun 18 by 4:00 Central Standard Time. 


Pre-Solicitation Charts - The Government has corrected charts 11 and 51.


Chart 11 - Title has been changed to state Contract Requirements instead of Contractor Requirements.  Also, under the EMD phase it has been corrected to state modify 40 bomb racks instead of 44 bomb racks.


Chart 51 - The CLIN Structure has been updated to reflect the structure that is currently on the Draft RFP.


Questions regarding this announcement shall be submitted by e-mail to the following Contracting Officer, Kristen Carter, kristen.carter@us.af.mil.  Verbal questions will not be accepted.  Questions shall not contain any proprietary information.  All answers to the questions will be posted to the FedBizOpps website. 

Update #1 ·

Added: May 18, 2018 10:58 am  

THIS IS A DRAFT REQUEST FOR PROPOSAL (RFP) ONLY.  This request does not constitute a Request for Proposal (RFP) or a promise to issue an RFP in the future.  This request does not commit the U.S. Government to contract for any supply or service.  Furthermore, the Air Force is not at this time seeking proposals and will not accept unsolicited proposals.  Not responding to this request does not preclude participation in any future RFP, if any is issued.  If a solicitation is released, it will be synopsized on the FedBizOpps website.  It is the responsibility of the potential responders to monitor this site for additional information pertaining to this requirement. 


DRAFT RFP


The Government will hold a Pre-Solicitation Conference on May 23, 2018.  The Pre-Solicitation Conference will be held via Telecom.  Please fill out the registration form by May 22, 2018 and return to Kristen Carter at kristen.carter@us.af.mil. 


Please note that the CDRLs and GFE attachments will be posted at a later date. 


Questions regarding this announcement shall be submitted by e-mail to the following Contracting Officer, Kristen Carter, kristen.carter@us.af.mil.  Verbal questions will not be accepted.  Questions shall not contain any proprietary information.  All answers to the questions will be posted to the FedBizOpps website. 

Attachments

Files attached to this notice, newest first
File Type Posted
Additional_Q&A.docx DOCX document
Q&A_from_Pre-Solicitation_Conference.docx DOCX document
Revised_DRAFT_RFP_-_FA810718R0007.pdf PDF
BRU-56_Draft_RFP_Teleconference_Slides_-_24_May_18.pptx PPTX presentation
BRU-56_Draft_RFP_Teleconference_Slides_-_23_May_18.pptx PPTX presentation
BRU_SRD.pdf PDF
DRAFT_RFP_-_FA810718R0007.pdf PDF
Section_M_-_Evaluation_Factors_for_Award.pdf PDF
Section_L_-_Instructions_to_Offerors.pdf PDF
Pre-Solicitation_Conference_-_Rev.docx DOCX document
Pricing_Matrix_B-1_BRU-56_DRAFT_-_Protected-R2.xlsx XLSX spreadsheet
BRU-56_SOW.pdf PDF
Presolicitation_Conference_Registration_Form.xlsx XLSX spreadsheet
Show all 13

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
B-52 BRU-56 Modification Solicitation Award Award Notice
B-52 BRU-56 Modification Solicitation Latest solicitation Solicitation
B-1 Bomb Rack Unit (BRU) - 56 Modification This notice · Original Pre-Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity