SEE ADDENDUM
(No Collect Calls)
W913E519R0001 20-Dec-2018
b. TELEPHONE NUMBER
601-634-2748
8. OFFER DUE DATE/LOCAL TIME
12:00 AM 25 Jan 2019
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W913E59. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
DAVITA S BALOUE
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED ORX
SMALL BUSINESS
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
ERDC CONTRACTING OFFICE
HANOVER OFFICE
72 LYME ROAD
HANOVER NH 03755-1290
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE 16. ADMINISTERED BY
SEE SCHEDULE
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
X SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
(217) 373-6773FAX:
TEL: (217) 373-7297 SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
1,250
NAICS:
333415
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF75
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
W913E519R0001
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Refrigeration Equipment Repair
FFP
By Replacement. The Contractor shall provide all supplies, supervision, labor, materials, tools and equipment, safety and quality control necessary to perform a repair by replacement of specified refrigeration equipment at the Frost Effects Research Facility (FERF) at the US Army Corps of Engineers Cold Regions and Engineering Laboratory (CRREL), Hanover, New Hampshire. If vendor choses to submit 2 solutions, 1 for water and 1 for air, the vendor shall submit 2 separate and independent proposals. The technical/price for each solution shall be independent of each other.
NET AMT
0001AA 1 Job Low Temperature Chiller
FFP
Equipment Only (does not include cost for installation/testing) FOB: Destination
0001AB 1 Job Medium Temperature Chiller
FFP
Equipment Only (does not include cost for installation/testing)
0001AC 1 Job Pumps and Valves
FFP
Equipment cost only (does not include cost for installation/testing)
0001AD
Installation of Chiller &
FFP
Testing of System
Section C - Descriptions and Specifications
DESCRIPTION OF REQUIREMENT
DESCRIPTION OF REQUIREMENT
Frost Effects Research Facility Refrigeration Equipment Repair by Replacement
USACRREL
72 LYME ROAD, HANOVER, NH
1. GENERAL
A. The Contractor shall furnish all supplies, supervision, labor, materials, tools and equipment, safety, quality control, mobilization and demobilization to perform a repair by replacement of specified refrigeration equipment at the Frost Effects Research Facility (FERF) at the US Army Corps of Engineers Cold Regions Research and Engineering Laboratory (CRREL), Hanover, New Hampshire.
The refrigeration equipment to be replaced currently is the medium temperature compressors, the low temperature compressors and their respective pumps and tank valves.
B. Overview: The replacement refrigeration equipment shall be two glycol chiller package units, with an option to bid three units. The first shall be a minimum 120 Refrigerant Tons; this may be proposed in either one 120-RT unit rated for industrial use and/or in two 60-RT units rated for industrial use at evaporator temperature of 0 ℉. The second shall be a minimum 30 Refrigerant Ton unit rated for industrial use at evaporator temperature of -47 ℉. New glycol circulating pumps shall be supplied for each unit to transfer glycol to the corresponding medium and low temperature glycol holding tanks. The project includes purchase and installation of the chiller units, all electrical connections for the units and pumps, control tie-ins to the glycol tanks, isolation valves, piping, insulation and other ancillary parts. Salient features required for the units shall be per this Description of Requirement (DOR). The glycol used in the system is Dow Norkool SLH and is an Ethylene Glycol. All references to Dow Norkool in this document are to the Ethylene Glycol variant.
The Contractor shall replace the exterior valves (total of 35 valves) in the piping for the low, medium, and high temp glycol tanks and select interior valves leading to these valves in the piping system. There are 14 x 6” Butterfly valves, 10 x 6” gate valves, 5 x 6” check valves, 1 x 5” butterfly valve, 1 x 5” check valve, 1 x 4” butterfly valve, 2 x 4” gate valves, and 1 x 4” check valve; they are pressure class 150, ANSI Class IV, tight shut-off per ANSI B16.104 and must be rated for Dow Norkool SLH (Ethylene) use. The insulation on the valves shall also be replaced. Pricing shall include the emptying of the three glycol tanks into temporary holding tank(s) and refilling of the three tanks.
Contractor shall install any external equipment on a 35x20ft government furnished concrete pad with 2ft of standoff distance from the side of the building, sheds, and external tank farm. Pad is 4,000 psi, six inches thick, reinforced with No.6 bars on 12-inch centers and has 8-10 inch in sum total of lifts.
Any equipment external to the building shall be sized for this pad.
C. Existing Conditions: The work shall comply with the requirements of all Federal, State and local codes. Any ammonia system being installed must conform with IIAR2 2014 standards for ammonia refrigeration machinery in all particulars, including ammonia alarms and emergency shutdown safety systems.
D. Point of Contact (POC) Requirement: Contractor shall identify a single point of contact with decision-making authority. His/her duties shall include, but are not limited to, ensuring contractor compliance with security, safety, scheduling, and non-smoking requirements. See Sections: 7 Safety, 8 Scheduling, 9 Security, and 10 Smoking Policy. The POC is required to be present at an initial post award conference after award of this contract. See Section 6 Post Award Conference.
E. Qualifications: Before any work takes place on site, the Contractor shall provide a copy of each employee’s licenses and certifications to the Contracting Officers Representative (COR) that pertains to the specific job to be performed in the execution of this contract. Licenses and Certifications are outlined in Section 5.
2. SUPPLIES
Refrigeration System Equipment: The Contractor shall provide the glycol chiller units, glycol circulating pumps, valves, controls, piping, hangers, supports, insulation, and other miscellaneous parts such that they work together to support the required system conditions. All equipment shall be rated for use with Dow Norkool glycol. Contractor shall submit their proposed products to the Government in their technical proposal.
A. The Contractor shall offer against one or both of the following supply procurement alternatives:
(1) Water-cooled chiller replacement strategy:
a) The Contractor shall disconnect and remove the old refrigeration chiller units, pumps, valves, and abandoned wiring and conduit. The Contractor shall transport all solid waste off of the project site and dispose of it in compliance with Federal, State and local requirements for solid waste disposal. The Government shall Field Mark the limits of the demolition activity not to exceed first sixty (60) lineal feet of the machinery room as measured from the garage access door. Contractor may refer to government provided specifications to develop worst-case estimate.
b) Glycol Chiller Units – Units shall be equipped with a micro-processor control panel with electronic user interface. Variable Frequency Drives shall be installed on the units for efficiency. The Contractor shall submit the product data and manufacturers specifications of their proposed medium and low temp chiller units that meet or exceed these specifications.
c) Medium Temp Unit: This unit shall be a 120 Refrigeration Ton (420kWr) chiller unit or two (2) 60 Refrigeration Ton (210kWr) units; the vendor may propose a larger tonnage to achieve cost savings by using standardized tonnages, but may not propose a smaller tonnage. Evaporator temperature estimated to be approximately 0 ℉. It shall be rated for industrial use, instead of commercial use.
I. Indoor Water-Cooled Unit(s): An indoor water cooled unit(s) must connect to existing process water, electrical, and power connections. A 120 RT chiller would be installed directly in place of one of two 120 RT chiller units of similar capability that are currently present, but operating off of R22 and not automated.
Alternatively, two 60 RT chillers may be installed in place of the existing 120 RT chillers as a one for one replacement in the same locations, at half the rated tonnage.
A standard single-vehicle garage door is available for access to the machinery room. Cooling water supply not to exceed 200 gallons per minute (gpm), or the contractor may propose a closed-loop cooling system.
II. Any component of the proposed water-cooled system which is located external to the building requires the contractor to be responsible for all pass-thrus and for the total footprint of all external equipment to fit within the 35x20 pad described in Section 1.B.
III. All new electrical work required for installation of chillers must be bid as part of the installation proposal, including pass-thrus for any exterior portion of the equipment.
d) Low Temp Unit: This unit shall be a 30 Refrigeration Ton (105kWr) chiller unit; the vendor may propose a larger tonnage to achieve cost savings by using standardized tonnages, but may not propose a smaller tonnage. Evaporator temperature must be within three degrees +/- of -47 ℉. It shall be rated for industrial use, instead of commercial use.
I. Indoor Water-Cooled Unit: An indoor water cooled unit must connect to existing process water, electrical, and power connections. This unit would be installed directly in place of one 17 RT chiller unit of similar capability but operating off of R22 and not automated and one 25 RT chiller unit of similar capability but operating off of R22 and not automated. A standard single-vehicle garage door is available for access to the machinery room. Cooling water supply not to exceed 150 gallons per minute), or the contractor may propose a closed-loop cooling system.
II. Any component of the proposed water-cooled system which is located external to the building requires the contractor to be responsible for all pass-thrus and for the total footprint of all external equipment to fit within the 35x20 pad described in Section 1.B.
III. All new electrical work required for installation of chillers must be bid as part of the installation proposal, including pass-thrus for any exterior portion of the equipment.
(2) Air-cooled chiller replacement strategy:
a) The Contractor shall install air-cooled skid units located external to the building. This will require splicing in new connections to the chillers into the existing system. The Government will provide a 35x20 concrete pad for mounting the units on.
b) Glycol Chiller Units – Units shall be equipped with a micro-processor control panel with electronic user interface. Variable Frequency Drives shall be installed on the units for efficiency. The Contractor shall submit the product data and manufacturers specifications of their proposed medium and low temp chiller units that meet or exceed these specifications.
c) Piping: A total of up to 140 feet of additional glycol piping sized to interface with the existing system must be supplied to hook up supply/return feeds to the outside air-cooled units. This should consist of one supply/return loop of 40 linear feet and one to two supply/return loops of 50 linear feet each to connect both units to their respective glycol supply tanks, with exact dimensions depending on the Contractor’s proposed configuration and units.
d) Insulation – All existing exterior piping and equipment to the 3 Norkool tanks shall be reinsulated due to the perforations for the new piping and general poor condition. All new, Contractor provided, equipment shall also be insulated. The insulation shall be an exterior rated rigid styrofoam designed for refrigeration cold service. A Dow/Polyguard ZeroPerm insulation system, or equal, shall be used. Includes a piping corrosion gel, vaporguard, styrofoam, and vapor barrier.
e) Medium Temp Unit: This 120 Refrigeration Ton (420kWr) of installed capacity in one 120 RT chiller unit or two 60 RT chiller units; the vendor may propose a larger tonnage to achieve cost savings by using standardized tonnages, but may not propose a smaller tonnage. Evaporator temperature estimated to be approximately 0 ℉. It shall be rated for industrial use, instead of commercial use.
I. Outdoor Skid Unit: An outdoor skid unit, air cooled and installed outside as a skid package, must run in low outside temperature environments, -30 ℉ OAT, and high outside temperature environments, 100 ℉ OAT with 85% humidity. This unit must include all necessary piping connections for system operation, incorporating new pumps and valves with interconnections outdoors near existing Glycol tanks. The Contractor is responsible for proposing the design of the interconnections between the existing system and the new skid units, as well as for the extension of electrical hookups to supply power to the units.
f) Low Temp Unit: This unit shall be a 30 Refrigeration Ton (105kWr) chiller unit; the vendor may propose a larger tonnage to achieve cost savings by using standardized tonnages, but may not propose a smaller tonnage. Evaporator temperature shall be within +/- degrees of -47 ℉. It shall be rated for industrial use, instead of commercial use.
I. Outdoor Skid Unit: An outdoor skid unit, air cooled and installed outside as a skid package, must run in low outside temperature environments, -30 ℉ OAT, and high outside temperature environments, 100 ℉ OAT with 85% humidity. This unit must include all necessary piping connections for system operation, incorporating new pumps and valves with interconnections outdoors near existing Glycol tanks. The Contractor is responsible for proposing the design of the interconnections between the existing system and the new skid units, as well as for the extension of electrical hookups to supply power to the units.
(3) Glycol Circulating Pumps – There shall be two pumps per chiller unit, piped in parallel, one to be used as a back-up. The Contractor shall submit the product data and manufacturers specifications of their proposed medium and low temp pumps that meet or exceed these specifications.
i. Medium Temp Pumps (MTP): The current pumps are 240 gpm with 74 feet of head. The new pumps shall be sized appropriately for the new system. The number of medium temperature pumps shall be two (2) if a single 120 RT chiller is proposed by the vendor for the medium temperature loop, and four (4) if two 60 RT chillers are proposed by the vendor for the medium temperature loop.
ii. Low Temp Pumps (LTP): The current pumps are 141 gpm, with 55 feet of head. The new pumps shall be sized appropriately for the new system. The number of pumps shall be two (2).
(4) Valves – The following valves must be supplied and installed: 14 x 6” Butterfly valves, 10 x 6” gate valves, 5 x 6” check valves, 1 x 5” butterfly valve, 1 x 5” check valve, 1 x 4” butterfly valve, 2 x 4” gate valves, and 1 x 4” check valve; they are pressure class 150, ANSI Class IV, tight shut-off per ANSI B16.104 and must be rated for Dow Norkool SLH (Ethylene) use.
Contractor will arrange site visit to physically inspect valves to be replaced to verify configuration before ordering.
(5) Product Data: (3) Copies of written product data, manufacturer’s specifications, and operating procedures shall be provided after the installation. Electronic copies, if available, shall also be provided to the COR.
(6) Safety Data Sheets (SDS): SDS sheets for cleaners or lubrication or any other materials intended for use on this contract.
(7) Operational Performance Requirements – The systems shall be able to cool their respective glycol tanks in less than 4 days (96 hrs), assuming 95 ℉ OAT with 95% humidity (with the Norkool inside the tank assumed to be stabilized to the outside environment at approximately 80 ℉) and target temperature of -37 ℉ inside of the low temperature glycol tank and 10 ℉ inside of the medium temperature glycol tank, with each tank being at capacity with 3,000 gallons of Dow Norkool SLH and a functional R6 insulation factor on the tanks. The installation shall be tested for acceptance by cooling the tanks in such a period of time that the curve from the test indicates performance equivalent to these requirements.
(8) Ammonia Refrigeration Systems – Ammonia refrigeration systems proposed to meet the requirements of this specification must comply in full with IIAR 2 rev 2014 and the proposed price must reflect full required hi/lo safety alarms and automated emergency shutdown integral to the unit. No unit may be proposed that has a catastrophic leak of greater than 200lbs of anhydrous ammonia from a single point of failure. The catastrophic leak is generally the largest single vessel or 50% of the total ammonia capacity of a unit. The submission from a vendor proposing an Ammonia Refrigeration System must demonstrate that no leak would ever exceed 200lbs of ammonia. Ammonia Refrigeration Systems proposed by the vendor must be capable of interfacing with standard industrial alarm systems to provide campus-wide notification and response. A vendor may submit both ammonia and non-ammonia refrigeration systems as options for the Government to evaluate.
3. INSTALLATION
A. Glycol Chiller Units: The Contractor shall furnish and install both a low temperature glycol chiller of 30 RT, and either one medium temperature glycol chiller unit of 120 RT, or two medium temperature glycol chiller units of 60 RT each, to replace the existing units in the FERF. The units shall be stand-alone chillers that can work independent of each other. Dedicated disconnect switches shall be installed at each unit.
B. Glycol Pumps and Motors: Each unit shall have two glycol circulating pumps that connect to its corresponding glycol circulation system. They shall be piped in parallel, with one a back-up. There shall be isolation valves for each pump for maintenance. Dedicated disconnect switches shall be installed at each pump. A unit includes a pump and motor coupled on a base.
C. Location – The contract may be bid to install new water-cooled units in the existing machinery room, or air cooled units external to the building. In the case of water-cooled units:
(1) Existing two (2) 120-RT Medium Temperature units and one (1) each 25-RT and 17-RT low temperature units must be removed and supporting equipment demolished to support installation of either one (1) 120-RT Medium temperature unit or two (2) 60-RT Medium temperature units, and (in both cases) one (1) 30+-RT unit. Power, water, and glycol connections must be supplied, linking to those for units being replaced.
(2) The government will provide a 35x20 concrete pad for external air-cooled units. The size shall include all manufacturer required clearances for safe maintenance and operation. This shall be provided to the Government at the Post Award Conference. Units must be piped and wired into building with cable pass-thru in walls.
(3) Electrical Feed: Repaired/replacement equipment shall be powered from the existing 480-volt 3-phase facilities.
The Contractor shall provide replacement feeder/branch circuit raceway and conductors and shall reuse the existing motor control center “buckets” with existing or replacement motor circuit protectors and motor starters and the main switchboard “MS” fused disconnects with fuse, size adjusted, as required by the replacement loads.
Any penetrations through the building walls required by the proposed equipment shall be caulked and sealed to minimize heat transfer and prevent moisture penetration into and/or through the wall. Raceways penetrating building wall shall be plugged to prevent air circulation though the raceway.
(4) All work shall comply with NFPA 70 (NEC) 2017 Edition. Existing loads and electrical supply facilities are as follows:
Equipment Name
Existing Electrical Supply Location Description Frame/Fuse Voltage/Phase
Medium Temp Chiller
(MTC1A)
Main Switchbd “MS” Fused Disconnect 600A/500A 480/3
Low Temp Chiller
(LTC1)
Main Switchbd “MS” Fused Disconnect 600A/200A 480/3
Location Description MCP Frame/Trip
Starter Size
Overload Voltage
Medium Temp Pump
MTP1A
MCC-2 Motor Controller
100/30A 2 FH45 480/3
Medium Temp Pump
MTP1B
MCC-2 Motor Controller
100/30A 2 FH45 480/3
Low Temp Pump LTP1 MCC-2 Motor Controller
100/30A 1 FH45 480/3
Low Temp Pump
LTP1A
MCC-2 Motor Controller
100/30A 2 FH45 480/3
D. Controls: The refrigeration units shall maintain the required set temperature of their respective glycol tank. The Contractor shall furnish and install new temperature sensors at each tank outflow that will provide feedback to each unit.
(1) Medium Temp Norkool Tank – This tank holds approximately 3000 gallons Norkool glycol.
The Medium Temp Unit shall be capable of maintaining glycol in the tank at a temperature of 10 ℉.
(2) Low Temp Norkool Tank – This tank holds approximately 3000 gallons Norkool glycol. The Low Temp Unit shall be capable of maintaining glycol in the tank at a temperature of -37 ℉.
E. Piping and Valves: There shall be dedicated isolation valves at the unit. The piping shall be sized for the system and pumps. Valves shall be compatible with Norkool glycol service and rated for outdoor use. An additional tee shall be installed in both pump discharge piping with shut-off valves and threaded caps. Existing piping at the tanks is 4” and 6” carbon steel, schedule 40.
F. Draining of Tank: The Contractor shall drain the high, medium, and low tanks of Norkool, store it in clean containment(s) on-site, and refill the tanks when tie-ins have been completed. The Contractor may use Government holding tanks for Norkool storage, but is required to return them in clean condition, with no residual Norkool. The tanks will be positioned by the Government at commencement of work where the Contractor requests, but additional Government support to the draining and filling operation will not be provided after placement.
G. Pressure Testing: All new piping and connections shall be pressure tested prior to filling with
Norkool.
H. Insulation: The Contractor shall insulate and seal all new piping and valves with exterior rated insulation. The insulation work is limited to the exterior of the FERF building. Insulation joints shall be properly sealed.
I. Testing: The Contractor shall perform equipment testing of the installed equipment to verify the operation of meets manufacturer’s specifications. A system test shall be performed as close to the conditions described in Section 2 A (7). Documentation shall show temperature of tank as measured during a draw-down test lasting for nine-six (96) hours at four (4) hour intervals.
J. Training: The Contractor shall provide equipment training to CRREL personnel on the operation of the chiller units. Copies of manufacturer’s recommended operating instructions and maintenance schedule shall be provided before training.
K. Availability of Government Facility As-Builts: Sheets A-2, A-1, M-2, and M-1 from the as-built drawings for the FERF, covering architectural, mechanical, and flow diagram configuration have been supplied as an appendix to this DOR to assist in Vendor scoping of the installation component;
in addition, all fourteen (14) of the FERF electrical design sheets will be scanned and uploaded as an appendix to this DOR to assist in Vendor scoping of the installation component. Both are supplied as-is. .
4. SUBMITTALS
A. General Submittals for Government Approval:
(1) Accident Prevention Plan (APP) – The APP shall be submitted and approved prior to start of work on site. See Sections 7 B APP, and 17 APP Outline.
(2) List of Contractor Personnel: Prior to or at the Post Award Conference the contractor shall submit to the COR for approval a complete list of contractor employees expected to work on the CRREL site. The contractor shall verify U.S. citizenship for all employees on the list. The list shall include the name and telephone number of the contractor POC for the contract.
5. LICENSING/CERTIFICATIONS
A. Overview: The Contractor must provide copies of their personnel’s licenses and/or certifications that pertain to this project. See Section 5 C.
B. Site Safety and Health Officer (SSHO): The Contractor shall designate one Person as the SSHO and their training, experience, and qualifications shall be in accordance with EM 385-1-1. The Contractor shall submit documentation of SSHO qualifications to the COR.
(1) The SSHO shall be present at the work site at all times while the Contractor performs work under this contract.
(2) The SSHO shall have a minimum of 2 years’ experience in similar work environments; shall have experience in personal protective equipment; and a working knowledge of safety procedures as well as Federal and State occupational safety and health regulations.
(3) The SSHO shall have at least a 10 hour OSHA Safety Class certificate.
(4) Contractor employees performing other duties on site, that are qualified, may also be the designated SSHO for this project.
C. Disciplines: Contractor shall provide a copy of each employee’s licenses and certifications to the
COR.
(1) HVAC&R Technicians – Contractor personnel performing the installation of the refrigeration equipment shall have an HVAC&R Technicians license. It shall be provided either from a reciprocal state, NATE, or other equivalent recognized certification. Refrigeration and HVAC technicians shall hold an EPA Universal Refrigerant License.
(2) Electrical – Contractor personnel accessing panels shall have NFPA 70E Compliance, Arc Flash Safety training.
(3) Equipment – Additional manufacturer’s training for specific equipment may be required to perform start-up operations in order to maintain warranties. Example: A GEA compressor would require a GEA certified technician.
6. POST AWARD CONFERENCE
A. Overview: Contractor shall attend an onsite post award conference that will be arranged by the Government representative before any work on site commences.
B. Purpose: The purpose of the conference is to ensure all requirements for submittals are met, to discuss scheduling, to review safety, security, describe how installation shall be executed, inform contractor of Government lines of authority, and to address other subjects or questions that may be raised by either the Government or contractor.
C. Requirements: Contractor POC and SSHO must be present and shall bring with them to the conference all submittals not previously submitted. See Section 1 D POC Requirement and 5 B for SSHO Requirement. Work shall not commence on site until the conference has taken place, all submittals have been approved, and there are no outstanding issues.
7. SAFETY
A. Overview: This contract is subject to the requirements of and shall be in accordance with EM 385-1- 1, U. S. Army Corps of Engineers Safety and Health Requirements Manual, OSHA 29CFR 1910 regulations covering personnel protective equipment, the CRREL Safety Office, and to any other local, state, and federal regulations that apply to the job. All contractor personnel shall maintain safe practices and procedures at all times while on the CRREL site. Materials or products which are toxic, hazardous, or otherwise pose a health risk to any personnel shall not be used.
B. Accident Prevention Plan (APP): Contractor shall submit to the COR for approval an Accident Prevention Plan (APP) which complies with EM 385-1-1 Safety and Health Requirements Manual prior to or at the post award conference. The APP must be approved by the Government before work commences on site. Minimum requirements for an APP are included in Section 17 APP Outline.
Before the start of the job, the contractor shall ensure that the APP is provided to and reviewed by each contractor employee who will work on site. No separate payment will be made for the APP.
C. Personal Protective Equipment (PPE): Contractor personnel performing work on site shall comply with EM 385-1-1 and OSHA PPE standards for protective equipment. Each specific job will be assessed and the appropriate PPE shall be used. Examples include, but are not limited to: Gloves, glasses, hard hat, face shield, steel toed shoes, and Arc Flash clothing. Contractor is required to supply his employees with proper PPE.
D. SDS Sheets: Contractor shall submit as required in section 2 A (6) SDS. NOTE: No products or equipment containing Trichloroethylene (TCE) or exposed to TCE may be used or brought on site.
E. Routes of Egress: The contractor shall ensure work does not block egress routes in the case of an emergency.
F. Safety Briefing: The CRREL Safety Office or COR will provide a safety briefing that the contractor shall ensure is reviewed by each contractor employee before starting job.
G. Fall Protection: Fall protection threshold height is 6 feet. The Contractor shall comply with EM 385-1-1 Safety and Health Requirements Manual when accessing work areas at or above that threshold. OSHA Fall Protection Training for Competent Person is acceptable.
H. Equipment: Contractor equipment used to access work areas (i.e. ladders, lifts, cranes) shall be current with manufacturer’s safety inspections and certificates. Inspection certificates must accompany any equipment used on site. Equipment shall be made available for inspection by the COR prior to start of work on site.
I. Barriers/Barricades and Signage: The Contractor shall provide barriers or barricades and signage as necessary to ensure unauthorized pedestrian or vehicle traffic cannot enter into work areas until safe to do so.
J. Portable Extension Cords: If it is necessary to use portable extension cords, they shall be sized in accordance with manufacturer ratings for the tool to be powered and protected from damage.
Portable extension cords shall be GFCI and shall meet the requirements of NPPA 70E and OSHA electrical standards.
K. Asbestos: If the Contractor encounters any material that could contain asbestos, they shall immediately report finding to COR. The material shall not be disturbed until it has been investigated and identified.
8. SCHEDULING
A. Overview: Scheduling will be discussed at the post award conference. Work shall not commence until the work schedule has been approved. Once approved, the schedule shall be strictly followed.
No changes can be made by the contractor without prior approval of the COR.
B. Completion Objective: Bid shall reflect intensity of effort required to insure system is operational no later than 31 July, 2019. The Period of Performance will be from date of award through 31 July 2019.
C. Work Hours: Unless otherwise authorized in writing by the COR, the project site will be available for activities during USACE core work hours only, from 6:00 AM to 6:00 PM, weekdays, excluding Federal holidays. The Government reserves the right to make changes to work hours/days.
9. SECURITY
A. Overview: All contractor personnel are required to follow all security regulations as directed by the CRREL Security Office, as written in this Work Statement, and as otherwise specified at the post award conference. General disruption by the contractor is limited to the immediate work site. The contractor is strictly responsible for the security of all products, materials, tools, and equipment used during the duration of this job.
B. United States Citizenship: All contractor employees entering on to the CRREL site must be U.S.
citizens.
C. Identification: All contractor employees must have a positive picture I.D. (such as a valid picture driver’s license) to enter on to the site and must be prepared to show it at any time. The Security Office may require each contractor employee to wear a badge issued by the Security Office and also to sign in and out when entering and leaving the work site. The contractor is responsible for all badges issued to his employees and shall ensure they are returned to the Security Office upon completion of the work, when leaving the site, or when otherwise directed.
D. Weapons: Weapons of any kind are prohibited on the CRREL site.
E. Access and General Protection/Security Policy and Procedures: The contractor and all associated subcontractors’ employees shall comply with applicable installation, access and local security policies and procedures. Policies and procedures will be provided by the local Security Office. The contractor workforce must comply with all personal identity verification requirements as directed by DoD, HQDA, and local policies. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
F. For contractors who do not require CAC, but require access to a DoD facility or installation:
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC- III) and Terrorist Screening Database (TSDB), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
G. iWATCH Training: The contractor and all associated subcontractors shall brief all employees on the USACE iWATCH program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 45 calendar days of contract award and within 45 days of new employees commencing performance on the contract. The contractor shall provide certification of completion to the COR within 10 days of training completion. Training documents will be provided by the Security Office.
H. Personal Security Screening: The Contractor shall pre-screen candidates using the E-Verify Program. The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements.
The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.
I. Vehicles: Contractor personnel shall wear seatbelts at all times when driving on CRREL premises.
Contractors shall obey a speed limit of 10 mph. No weapons are allowed within a vehicle on site.
10. SMOKING POLICY
A. Smoking shall comply with the CRREL Smoking Policy, which, in general, prohibits smoking on site except in a designated smoking area. Designated smoking areas will be discussed at the post award conference.
11. GOVERNMENT FURNISHED UTILITIES
A. The Government will furnish to the contractor, in reasonable quantities, water and electricity in order to successfully complete this contract. Contractor may use the sanitary facilities in the FERF.
12. CONTROL OF WASTE
A. During performance of all work on site, Contractor shall control waste and debris to ensure that it stays within the work area. Contractor shall remove waste and debris from the site and properly dispose of it on a daily basis.
13. TOOLS AND EQUIPMENT
A. Tools and equipment used under this contract shall be maintained in good condition and shall be used and stored using safe practices and procedures at all times in accordance with manufacturer’s instructions and recommendations. Tools and equipment shall be restricted to the immediate work area unless alternate arrangements are requested and approved through the COR. GFCI protection is required for portable tools and portable extension cords.
14. DAMAGE TO WORK OR SITE
A. Installation of new materials shall not cause any damage to surrounding areas or items. Contractor shall repair, at his own expense, all damages that occur to new work, the work areas, or any surrounding areas or items if damages are caused as a result of the performance of contractor work under this contract. All repairs shall be done as directed by the Government.
15. CONTRACTOR INSRUCTIONS
A. Contractor is hereby notified that NO CRREL/DPW EMPLOYEE has the authority to direct contract employees in any way to alter their contractual obligations. If the Government does desire to alter requirements, changes will be issued in writing and signed by the KO sited in your contract.
Contractor’s employees shall take no action on any change unless and until the POC receives such a contract modification.
16. INSPECTION AND JOB COMPLETION
A. Overview: This contract is subject to routine Government inspections throughout the performance of contractor work and a final Government inspection upon completion of each job.
B. Inspections: Routine Government inspections will, among other things, help ensure continuous quality assurance and more quickly identify defects. Contractor shall repair defects as directed by the Government at contractor’s own expense.
C. Job Completion: Upon contractor completion of the job, the Government will make a final inspection to confirm the following:
(1) All defects have been corrected as directed.
(2) All work has been completed.
(3) All work areas are left clean.
(4) All badges issued to contractor employees have been returned to the CRREL Security Office.
17. QUALITY ASSURANCE SURVEILLANCE PLAN - COR will coordinate for inspection and acceptance of arriving equipment. COR will coordinate for arrival of the contractor(s) to CRREL to perform installation, stand-up, calibration and testing. During the installation phase (as specified in the Contractor's submitted GANTT chart) the COR will conduct daily observations of the worksite (short 15-minute entries which do not interrupt or interfere with contractor progress) and have full access to the contractor work areas for this purpose, in coordination with the contractor. Any discrepancies unresolved during these observations will be immediately detailed for further action in coordination with the KO. These direct observations are fully supplemental to the Periodic Inspections outlined below.
Direct Observation will be assessing performance according to the attached Performance Requirements Summary Matrix.
Periodic inspection will be conducted weekly during the course of the installation and testing work (as specified in the Contractor's submitted GANTT chart) on the CRREL campus by COR and selected DPW personnel. Access to work site will be required and inspections will last up to one hour with access coordinated 24 hours in advance with Contractor. Periodic inspection will be governed by the attached Performance Requirements Summary Matrix.
COR will coordinate with two technical experts, one refrigeration operator and one controls/electronics engineer or technician to complete a 100% inspection of the installation after testing has been completed, in preparation for final acceptance.
The COR will confirm that CRREL is ready to receive the chiller-compressor sets (installation pad, glycol storage) and monitor the contractor during installation on CRREL campus. The COR will coordinate initial site visits and delivery of materials prior to commencement of installation, scheduling meetings on site as required to support activities during this phase of the contract. The Contractor will meet on a weekly basis with the COR during the installation and testing phase only, to report on progress versus cost and time metrics, and submit a written report detailing the progress during the last week and the plan for the next week at that time. The COR will notify the KO of completion and provide feedback on acceptance testing results and other observations including 100% inspection.
Analysis of the contractor's weekly progress reports will be conducted by COR and DPW Facility Engineer during weekly meetings. They will extrapolate based on standard civil engineering practice the magnitude and continued impact of any deviations from the original proposed schedule on the cost and project impacts to the laboratory and notify the KO with proposed remedies, engaging during weekly meetings with contractor based on KO directives.
The contractor shall submit weekly reports to the COR detailing progress toward objectives, comparing and contrasting with the Gantt Chart timeline proposed in the offer versus actual performance.
Ratings - Metrics and methods are designed to determine if performance exceeds, meets, or does not meet a given PRS standard. A rating scale shall be used to determine a positive, neutral, or negative outcome.
The following ratings shall be used:
Example 1:
EXCEPTIONAL: Performance significantly exceeds contract requirements to the Government’s benefit.
SATISFACTORY: Performance meets contractual requirements.
UNSATISFACTORY: Performance does not meet contractual requirements.
Example 2:
A numerical scale with numbers 1 through 10 where 1 is poor and 10 is excellent.
Documenting Performance -
Acceptable Performance - The Government shall document positive performance. Any report may become a part of the supporting documentation for fixed fee payments, award fee payments, or other actions.
Unacceptable Performance - When unacceptable performance occurs, the COR shall inform the contractor. This will normally be in writing unless circumstances necessitate verbal communication. In any case the COR shall document the discussion and place it in the COR file and courtesy copy the KO.
When the COR determines formal written communication is required, the COR shall prepare a Contract Discrepancy Report (CDR), and present it to the contractor's primary or alternate point of contact.
The contractor shall acknowledge receipt of the CDR in writing. The CDR will specify if the contractor is required to prepare a corrective action plan to document how the contractor shall correct the unacceptable performance and avoid a recurrence. The CDR will also state how long after receipt the contractor has to present this corrective action plan to the COR. The Government shall review the contractor's corrective action plan to determine acceptability. Any CDRs may become a part of the supporting documentation for contract payment deductions, fixed fee deductions, award fee nonpayment, or other actions deemed necessary by the KO. Frequency of Measurement – During contract/order performance, the COR shall take periodic measurements, weekly as specified in the PRS matrix, and shall analyze whether the negotiated frequency of measurement is appropriate for the work behind performed.
Frequency of performance Assessment Meetings – The COR shall meet with the contractor twice weekly to assess performance and shall provide a written assessment.
Documenting Evaluations/Payment Deductions – Due to the critical nature of the support, the Contractor’s performance will be compared to the contract requirements on a monthly basis against the Acceptable Quality Levels using the Quality Assurance Surveillance Plan to guide evaluations and the COR to document findings. If the performance in any required service fails to meet the performance threshold identified in the DOR, payments to the contractor may be reduced by the Contracting Officer.
Performance Requirements Summary Matrix
Desired Outcomes
Required Service Performance Objective and Standard
Acceptable Quality Level
Monitoring Method
Contractor complies in full with all Security requirements
During work, the contractor verifies compliance with security regulations in DOR continuously and enforces them for employees.
The performance objective is to see proactive efforts from the contractor demonstrated on all security requirements.
100% compliance with all security regulations.
COR will communicate weekly with Lead Security Guard to receive information regarding contractor compliance. Contractor will include compliance in weekly report.
Contractor maintains a safe worksite and operations
During work, the contractor meets all safety and environmental regulations referenced in DOR at all times.
The performance objective is to see a safe and environmentally sound job site.
100% compliance with all safety and environmental regulations
COR will visually inspect worksite for safety and environmental hazards on a weekly basis. SEMO may conduct spot inspections.
Any Corps employee may stop a practice immediately dangerous to life and/or health.
Contractor maintains a clean workplace
During work, the machinery room remains uncluttered for access to machinery out of scope and emergency response.
The performance objective is that all operational systems in workspace not be impacted by clutter, dust obscuring markings, etc.
At least 80% of the time during inspections walking areas should be clear and debris and dust removed from working surfaces within 2 – 3 days
During inspections the COR will take photographs of general cleanliness and appearance of key areas and assess them for overall clutter, dust and debris.
Demolition Debris Handling
Contractor demonstrates proper handling of any demolition debris
Performance objective is to avoid abandoned, cluttered or misplaced debris.
At least 80% of the time, debris from any demolition should be promptly moved (2 -3 days) into a C&D dumpster or other dumpster by other arrangement of Contractor
COR will survey work site during demolition phases (if appropriate) on a weekly basis and take photographic evidence of disposition of any demolition debris.
Successful Welding
Contractor conducts all welding activities according to code and of good workmanship
Performance objective is successful welding
98% of all welds should be clear of defects on visual inspection
COR will survey welds with an experienced welder up to twice weekly during welding operations before insulation is added.
Hanging of pipe Hanging of pipe in proper, un-cluttered fashion.
Any installed pipe with pipe-hangers will be un-cluttered and easy to access.
At least 90% of piping run through hangers should be readily accessible and well-labeled.
COR will conduct a 100% inspection of the installed piping.
Electrical Installation work
Electrical installation work done up to code and neatly
All electrical work meets acceptable standards under code specified in DOR and is accessible for maintenance as appropriate.
98% of electrical work should be properly labeled, cleanly accessible and properly configured and insulated.
COR will bring Electrical Engineer along as technical expert on at least one weekly inspection during electrical installation phase.
Insulation Fitting Insulation Fitting will be snug and properly secure against weather/leaks.
All insulation, indoors and outdoors, meets standards specified in DOR.
98% of all new insulation fitting should be snug and smooth to existing insulation and outer seal layer should be complete throughout.
COR will conduct 100% inspection of newly installed insulation with the Contractor reporting as required in QASP on progress.
18. REFERENCES
A. Overview: The following references are given…