Pre-Bid Conference Minutes CULVERT 01AUG23.pdf

PDF 248 KB Posted

Attached to
FY23 Culvert Removal & Replacement Federal contract opportunity
Solicitation number
W91364-23-B-0006
Issued by
Department of the Army Ohio Army National Guard

About this file

The document provides minutes from a pre-bid conference and site visit for solicitation W91364-23-B-0003 for perimeter road restoration and fence replacement work. The conference included a review of the installation map and site area for the project. Attendees then viewed the work site. Questions related to the project were to be directed to the Contracting Officer in writing to ensure a written response. The related federal contract opportunity is solicitation W91364-23-B-0006 for fiscal year 2023 culvert removal and replacement work to be conducted by the Department of the Army Ohio Army National Guard.

View the file

Other files for this federal contract opportunity

Other files attached to FY23 Culvert Removal & Replacement, newest first.
File Type Posted
OF1419 Bid Abstract W91364-23-B-0006.pdf PDF
Sign In Roster Site Visit 01AUG2023.pdf PDF
W91364-23-B-0006-00002 Solicitation Amendment.pdf PDF
W91364-23-B-0006-00001 Solicitation Amendment.pdf PDF
Pre-Bid Conference Minutes CULVERT 25JUL23.pdf PDF
Sign In Roster Site Visit 25JUL23.pdf PDF
Attachment 1 - Statement of Work.pdf PDF
W91364-23-B-0006 Solicitation.pdf PDF
Attachment 2 - RFI Form.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W91364-23-B-0003 - PRE-BID CONFERENCE MINUTES

USPFO - Ohio 09 August 2023

MEMORANDUM FOR RECORD

SUBJECT: Pre-Bid Conference, Site Visit 01 AUG 2023 Solicitation: W91364-23-B-0003, Perimeter Road Restoration & Fence Replacement

1. The site visit was conducted on 01 August 2023 at 9:00 am local time. A sign in roster is attached.

The following project personnel were present:

a. Hugh Holley, Construction Specialist

b. Josh Lenhart, Construction Specialist

c. Brian Persing, Contracting Officer Representative

d. Grant Stoner, Contracting Officer Representative

e. Corey Kuhn, Independent Project Manager, MacDonald-Bedford, LLC

2. The following was discussed:

a. Attendance roster for the 01 AUG 2023 site visit was circulated.

b. Review Map of Installation. Noted the site area for the project.

3. Site visit followed pre-bid conference, where the following was noted.

a. Attendees viewed work site.

Note: If there are any questions related to these minutes or any aspect of this project, please contact the Contracting Officer at 614-336-7430 (questions asked over the phone will be taken out of courtesy; however, the Government will only be responsible for those that are answered in writing). Due to current operations, ensure that you receive a response when submitting RFI, that it has been received. Also note SAM updates, to ensure all RFI’s have been answered.

Brad Wahl Contracting Officer

2023-08-09T16:05:58-0400