SPECS-NORTH_COVE-2017(1).pdf

PDF 17 MB Posted

Attached to
North Cove Maintenance Dredging Federal contract opportunity
Solicitation number
W912WJ17B0015
Issued by
Department of the Army Corps of Engineers Engineering District New England

About this file

Specifications

View the file

Other files for this federal contract opportunity

Other files attached to North Cove Maintenance Dredging, newest first.
File Type Posted
BidAbstract_North_Cove-signed.pdf PDF
Amendment_0004_FINAL.pdf PDF
Amendment_0003_FINAL.pdf PDF
Amendment_0002_FINAL(1).pdf PDF
Amendment_0001_FINAL.pdf PDF
Solicitation_W912WJ17B0015_(FINAL).pdf PDF
PLANS-NORTH_COVE-2017-signed.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912WJ-17-B-0015

MAINTENANCE DREDGING

FEDERAL NAVIGATION

CHANNEL

North Cove Connecticut River Below Hartford Old Saybrook, Connecticut

Construction Solicitation and Specifications

July 2017

Maintenance Dredging, North Cove, CT River, Old Saybrook, CT

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 32 00

GEOTECHNICAL DATA

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 22 00 MEASUREMENT AND PAYMENT

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 QUALITY CONTROL

01 45 01 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 54 50 DREDGING PLANT AND EQUIPMENT

01 57 20 ENVIRONMENTAL PROTECTION

01 58 00 PROJECT IDENTIFICATION

01 71 23 FIELD ENGINEERING FOR DREDGING

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 20 23 DREDGING

35 20 24 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM: SCOW -

MONITORING PROFILE

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 32 00

GEOTECHNICAL DATA

PART 1 GENERAL

1.1 SUMMARY

1.2 REFERENCES

1.3 EXAMINATION OF SAMPLES

1.4 ANALYSIS OF SAMPLES

1.5 INTERPRETATION

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section Table of Contents --

DOCUMENT 00 32 00 Page 1

SECTION 00 32 00

GEOTECHNICAL DATA

PART 1 GENERAL

1.1 SUMMARY

The sediment information indicated in the attachment at the end of the specifications is the result of site surveys, borings, and laboratory tests taken on May 4-5 of 2015. Copies of the grain size analysis, and locations at the site where subsurface investigations were performed, taken from the "Sediment Sampling and Testing in Support of Dredged Material Suitability Determination," are attached at the end of the specifications.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referenced to in the text by basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D2216 (2010) Laboratory Determination of Water (Moisture) Content of Soil and Rock by Mass

ASTM D422 (1963; R 2007) Particle-Size Analysis of Soils

1.3 EXAMINATION OF SAMPLES

Pertinent subsurface information is shown in the attachment at the end of the specifications. Sample materials obtained from the subsurface explorations are not available for examination.

1.4 ANALYSIS OF SAMPLES

Analysis of samples included grain size analysis in accordance with ASTM D422 and water content in accordance with ASTM D2216.

1.5 INTERPRETATION

Subsurface investigation data are provided only for information purposes and for the convenience of the Contractor. The data shown in the attachment at the end of the specifications is for the specific locations indicated only and no assurance is given that these conditions are representative of conditions between sampling locations or areas adjacent thereto. The responsibility lies with the Contractor to interpret subsurface conditions that may affect his work.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section --

DOCUMENT 00 32 00 Page 2

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.2 SUBMITTALS

1.3 PHYSICAL DATA

1.4 SUPERINTENDENCE BY THE CONTRACTOR

1.5 COORDINATION AND DIRECTION DURING CONSTRUCTION

1.6 SEQUENCING AND SCHEDULING

1.6.1 Hours of Operations

1.6.2 Work Sequence

1.6.2.1 General

1.6.2.2 Initial Project Schedule

1.6.2.3 Periodic Schedule Updates

1.6.3 Organization at the Site

1.6.3.1 General

1.6.3.2 Rate of Progress

1.7 CONTRACTOR'S USE OF UPLAND FACILITIES AND HAULING ROUTES

1.8 CONTRACTOR USE OF PREMISES

1.8.1 Access to the Site and Storage/Staging Areas

1.8.2 Temporary Facilities and Utilities, and Storage Areas

1.8.3 Work Limits

1.8.4 Protection and Security

1.8.5 Work By Other Contractors

1.8.6 Emergency Contacts

1.8.7 Damaged Property

1.8.8 Contractor's Receipt of Supplies

1.8.9 Daily Clean Up

1.8.10 Government Sanitary Facilities

1.9 QUALITY ASSURANCE

1.10 MOORINGS

1.11 COORDINATION

1.11.1 Notice to Mariners

1.11.2 Aids to Navigation

1.11.3 Harbormaster

1.11.4 Points of Contact

1.12 GENERAL SAFETY REQUIREMENTS

1.12.1 General

1.12.2 Contractor's Project Superintendent

1.13 ENVIRONMENTAL PROTECTION

1.14 PRECONSTRUCTION CONFERENCE

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 11 00 Page 1

SECTION 01 11 00 Page 2

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

The general description below is given to indicate the approximate scope of this project only. It does not limit the work required under the project drawings and specifications.

The work of this project involves maintenance dredging of the 11-foot entrance channel, 11-foot anchorage, and 6-foot anchorage at North Cove, Lower Connecticut River (below Hartford), Old Saybrook, CT.

North Cove is located on the Connecticut River approximately two miles from the mouth of the river and thirty-five miles northeast of New Haven, CT.

The maintenance dredging work in the Federal Navigation Channel and Anchorages consists of removal of approximately 280,000 cubic yards of material by mechanical dredge with the removed material transported by scow and disposed at the Central Long Island Sound Disposal Site (CLDS) which is located approximately thirty-five miles from the project site.

Due to environmental restrictions and scheduling constraints, dredging and disposal operations at the 11-foot entrance channel and 11-foot anchorage will only be permitted from 01 October 2017 through 31 January 2018.

Dredging and disposal operations at the 6-foot anchorage will only be permitted 01 October 2017 through 31 March 2018. Beginning February 1, 2018, the contractor will be required to use a closed environmental bucket and to deploy a Type II turbidity curtain surrounding the active dredging area.

Therefore the "No Dredging Season" for the 11-foot entrance channel and the 11-foot anchorage are defined as all dates prior to 1 October 2017 and after 31 January 2018. The "No Dredging Season" for the 6-foot anchorage is defined as all dates prior to 1 October and after 31 March 2018. Dredging operations are required to commence within 30 days of NTP.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Initial Project Schedule; G, RO

In accordance with the contract clauses, the Contractor shall, within 5 days after receipt of Notice to Proceed (NTP) or as otherwise determined by the Contracting Officer, submit for approval a practicable project schedule. When changes are authorized that result in contract time extensions, the Contractor shall submit a revised project schedule for approval by the

SECTION 01 11 00 Page 3

Contracting Officer.

Notice to Mariners

Submit a copy of Notice to Mariners to the Contracting Officer.

Aids to Navigation

Submit proof of coordination with the USCG for any necessary relocation or movement of aids to navigation.

Safe Harbor Plan; G, RO

The Contractor shall submit a Safe Harbor Plan to the Contracting Officer for approval prior to the start of on-site work. The Safe Harbor Plan shall include a written description of the Contractor's plan to provide for the safety and security of floating plant, equipment, and personnel in the event of a storm or other site emergency. The location for the docking of floating plant and the off-loading of equipment and crews shall be clearly indicated.

SD-07 Certificates

Periodic Schedule Updates; G, RO

1.3 PHYSICAL DATA

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

a. Site Conditions: The indications of physical conditions on the drawings and in the specifications are the result of site investigations and surveys. The conditions represented prevailed at the time the investigations and surveys were made. A pre-dredge survey will be performed by the Government prior to the start of Contractor dredging operations at the site. Before commencing work at the site, the Contractor shall verify the existing conditions indicated on the drawings and in the specifications. See CONTRACT CLAUSE entitled "SITE

INVESTIGATION AND CONDITIONS AFFECTING THE WORK".

b. Weather Conditions: Weather conditions for the site may be obtained by the Contractor from the National Oceanic and Atmospheric Administration's National Weather Service; www.NOAA.gov.

c. Transportation facilities: The Contractor shall make its own investigations on the use of municipal, State and Federal highways, roads, streets, and bridges.

d. Conditions of Channel: The North Cove Federal Navigation Project was last dredged in 2008 when approximately 175,000 cubic yards of fine sand, silt, and clay material was dredged. The 11-foot channel was dredged to 8-feet below MLLW and the 11-foot and the 6-foot anchorage were dredged to 6-feet below MLLW. The channel and anchorages were last dredged to authorized depth in 1992.

e. Channel Traffic: The channel and the anchorage areas are mainly

SECTION 01 11 00 Page 4 used by small recreation and commercial craft, which may cause interference with contract operations. Consult with the Harbormaster to determine the extent of interference with contract operations. The Government will not undertake to keep the channel free from vessels or other obstructions, except to the extent of applicable regulations.

The Contractor will be required to conduct the work in such a manner as to obstruct navigation as little as possible, and in the event the Contractor's plant so obstructs the channel as to make difficult or endanger the passage of any vessels, the plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage.

f. Tidal Conditions: The average tide range at the mouth of the river is 3.5 feet.

1.4 SUPERINTENDENCE BY THE CONTRACTOR

a. At all times during the performance of the contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent project superintendent who is satisfactory to the Contracting Officer and has the authority to act for the Contractor.

b. The project superintendent shall maintain a physical presence at the site at all times and be responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.

c. Failure to comply with these requirements shall be deemed as cause for a non-compensatory stoppage and suspension of work until the deficiency is remedied.

1.5 COORDINATION AND DIRECTION DURING CONSTRUCTION

a. The Contractor shall not take or accept any direction or instructions issued by any person, employed by the Government or otherwise, other than the Contracting Officer that changes the terms and conditions of contract actions, the scope, or any change that impacts the cost, price, or schedule. Changes authorized by the Contracting Officer will be in the form of a written, official, signed modification to the contract action received by the Contractor before the Contractor will act upon those changes. The Contractor will comply with the changes clause of this contract when the Contractor believes direction has been given from persons other than the Government Contracting Officer that equate to a change by notifying the Contracting Officer as directed by the clause. Any direction given by any Government employee or any other person outside their authority must be reported to the Contracting Officer.

b. The Contracting Officer Representative (COR) is limited to the authorities stated in the COR appointment letter. If a COR is appointed under this contract, they will be appointed by written letter from the Contracting Officer to the Contractor and COR specific to this contract only. COR appointment letters from previous contracts are not valid for this contract. See the Contracting Officer’s Representative clause of this contract.

SECTION 01 11 00 Page 5

1.6 SEQUENCING AND SCHEDULING

1.6.1 Hours of Operations

The Contractor will be allowed to perform all work 24 hours per day, seven days per week, including legal holidays, for the entire performance period. Refer to Subpart 1.1 WORK COVERED BY CONTRACT DOCUMENTS of this section for environmental requirements and restrictions to dredging and disposal activities.

The work hours stated above and work on Saturday, Sunday and legal holidays has been considered in computing the performance time of this contract.

The following legal holidays are observed:

January 1st Third Monday in January Third Monday in February Last Monday of May July 4th 1st Monday of September 2nd Monday of October 11th of November Fourth Thursday of November 25th of December

1.6.2 Work Sequence

1.6.2.1 General

There are certain essential criteria relative to the preparation of a work sequence and time schedule which the Contractor will be required to implement and follow during the prosecution of the work. Minor variations in the sequence of the items of work as approved may be made by the Contractor, provided such variations do not conflict with critical elements of the schedule. Proposed minor variations shall be noted on the progress charts submittal required by CONTRACT CLAUSE, entitled "SCHEDULES FOR CONSTRUCTION CONTRACTS". Variations shall be approved by the Contracting Officer prior to implementation. See Section 35 20 23 DREDGING, Subpart "Order of Work" for additional requirements.

1.6.2.2 Initial Project Schedule

The initial project schedule shall be in the form of a chart graphically indicating the sequence proposed to accomplish each work feature or operation. The chart shall be prepared to show the starting and completion dates of all work features on a linear horizontal time scale beginning with date of Notice to Proceed and indicating calendar days to completion. The Contractor shall indicate on the chart the important work features or operations that are critical to the timely overall completion of the project including start and finish dates of channel and each anchorage area, and environmental permit windows for particular areas. Key dates for such important work features and portions of work features are milestone dates and shall be so indicated on the chart. This schedule will be the medium through which the timeliness of the Contractor's construction effort is appraised. Anticipated adverse weather delay days shall be shown and included in the schedule.

SECTION 01 11 00 Page 6

1.6.2.3 Periodic Schedule Updates

An updated schedule showing actual progress shall be submitted monthly or with each pay request. Changes to the base-line schedule shall be provided graphically in a chart similar to the initial project schedule with a secondary color(s) representing the changes from the baseline and be outlined in a narrative describing the reason for the change.

1.6.3 Organization at the Site

1.6.3.1 General

The Contractor shall employ ample personnel and sufficient equipment to accomplish the work of this contract in the least amount of time, within the prosecution period specified in Section 00 80 00 SPECIAL CONTRACT REQUIREMENTS, Subpart COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (APR

1984) FAR 52.211-10.

1.6.3.2 Rate of Progress

Prosecute the work diligently, and maintain a dredging production rate, based on working 24 hours, 7 days a week, of not less than 75,000 cubic yards for each 30 calendar day period of actual dredging work at the site.

Should the Contractor fail to maintain the required rate of progress, the Contracting Officer may require that additional personnel and equipment be placed on the work and weekend and overtime work be performed, in order that the work be brought back on schedule and maintained. If, after a reasonable amount of time determined by the Contracting Officer, progress has either not been initiated, or has failed to sufficiently bring the work back on schedule to be completed by scheduled contract period, the contract may be terminated.

1.7 CONTRACTOR'S USE OF UPLAND FACILITIES AND HAULING ROUTES

a. Unless obtained by the Government or specified otherwise in the contract documents, the Contractor shall be responsible for the following:

(1) Locating, coordinating, and obtaining permission to use any land-based water access (docks, piers, ramps, etc.) that the Contractor deems necessary to complete the work.

(2) Determining, if necessary, the trucking and hauling routes and associated restrictions to and from the work, to include the coordination for the use of such routes with local, State, and Federal authorities.

(3) Complying with all local, State, and Federal regulations and restrictions when using any upland facilities or hauling routes.

b. The Government and its representatives will be allowed the use of the same land-based water access obtained by the Contractor.

1.8 CONTRACTOR USE OF PREMISES

1.8.1 Access to the Site and Storage/Staging Areas

a. The Contractor is responsible for maintaining access necessary for its equipment, material, and plant to and from the work area.

SECTION 01 11 00 Page 7

b. Access to temporary facilities and storage/staging areas shall be as noted under Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS.

1.8.2 Temporary Facilities and Utilities, and Storage Areas

The Contractor shall conform to Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS regarding temporary facilities, temporary utilities, and storage areas. Confine all operations (including storage of materials) to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

1.8.3 Work Limits

The limits of work consist of all shoaled areas of the North Cove Federal Navigation Channel and Anchorages (including side slopes) to their authorized depths as shown on the contract drawings.

1.8.4 Protection and Security

a. Protection to Contractor personnel or their equipment cannot be provided at the worksite by the Government.

b. The Contractor shall protect all its personnel, Government personnel, and the general public from injury.

c. The Contractor shall conduct all its work so as to prevent injury or unsafe conditions during construction.

1.8.5 Work By Other Contractors

During the performance period of this contract, no other work is anticipated to occur by other contractors.

1.8.6 Emergency Contacts

The Contractor shall provide a list of emergency contacts in the event of an emergency. The list shall include the contact names, addresses, and telephone numbers. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.8.7 Damaged Property

Work shall proceed in a manner which will minimize disturbance or risk of damage to boats, structures, and surrounding lands. The Contractor shall repair such items damaged in the course of carrying out the work at no additional cost to the Government. All repairs shall match similar existing items in all aspects. All replacements shall be in kind.

1.8.8 Contractor's Receipt of Supplies

The Contractor shall be responsible for all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site.

SECTION 01 11 00 Page 8

1.8.9 Daily Clean Up

The Contractor shall at all times keep rubbish from entering surrounding lands and water. Rubbish accumulated at the temporary facilities shall be removed from the premises daily.

1.8.10 Government Sanitary Facilities

Toilet facilities are not available on site for Contractor's use. The Contractor shall provide portable toilets for its personnel, subcontractors, and Government personnel as specified in Section 01 50 00

TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS.

1.9 QUALITY ASSURANCE

a. All items of work not addressed in the contract documents shall be completed in strict accordance with the manufacturers’ specifications.

b. The Government is not obligated to inspect the Contractor’s work, or to protect the Contractor from the consequences of its work. Government inspections are a general examination of the Contractor’s conduct and workmanship and are solely for the purpose of the Government.

Government-designated Quality Assurance Representatives (QARs) do not have the authority to accept work, nor is a Government inspection to be construed as conclusive.

c. Government agents including QARs and project engineers are not authorized to change the contract without the written approval of the Contracting Officer; this lack of authority extends to all situations in which the action of these agents could be construed as constituting a change.

d. The quality of workmanship is subject to audit by Government or Government-designated QARs at any time during the contract. The Contractor shall cooperate fully and provide all information necessary for this audit.

e. The Contractor shall submit all requests for changes in writing to the CONTRACTING OFFICER. Do not proceed with changes without possession of written authorization of the Contracting Officer.

f. The Contractor shall not conceal any work unless the Contracting Officer has approved all items of work which are to be concealed. The Contractor shall notify the Contracting Officer of its intention to conceal work at least 24 hours in advance of concealment.

1.10 MOORINGS

See Section 35 20 23 DREDGING, Subpart "Moorings".

1.11 COORDINATION

1.11.1 Notice to Mariners

Before beginning dredging operations and also prior to starting work, the Contractor shall coordinate with the U.S. Coast Guard (USGG) to issue a "Notice to Mariners" regarding the work to be performed and the Contractor's proposed operations.

The U.S. Army Corps of Engineers and the USCG have agreed to phraseology

SECTION 01 11 00 Page 9 when issuing navigational bulletins and notices. The information furnished shall be consistent with USCG Broadcast Notice to Mariners and Local Notice to Mariners. When requesting local USCG offices to issue navigational information for Corps of Engineers work involving marine construction, the following terminology shall be used, as applicable:

For cautionary areas: "Mariners are urged to use extreme caution in the area."

For dredging and work operations: "Mariners are urged to transit at their slowest safe speed to minimize wake and proceed with caution after passing arrangements have been made."

1.11.2 Aids to Navigation

Aids to navigation (beacons, buoys, markers, etc.) have been placed by the USCG in the vicinity of the project area. The Contractor shall not interfere with these aids to navigation. If the work of this project requires the temporary movement or relocation of any aid to navigation, the Contractor shall notify the USCG and the Contracting Officer of the requirement 30 days in advance. USCG personnel will then move or relocate the aid to navigation as appropriate for the progress of the work. Under no circumstances shall the Contractor move or relocate an aid to navigation under his own authority with his own personnel. The Contractor shall also contact the USCG at the completion of all work and the removal of all marine plant.

1.11.3 Harbormaster

Before beginning dredging operations and scow transport of dredged materials, the Contractor shall coordinate his work operations with the Town of Old Saybrook, CT Harbormaster.

1.11.4 Points of Contact

a. Coast Guard:

Mr. Matt Stuck; 617-223-8365; matthew.b.stuck@uscg.mil.

For Notice to Mariners: Ms. Mary Swanson, 617-223-8356, "mary.f.swanson@USCG.mil".

b. Harbormaster, Town of Old Saybrook, Connecticut Mr. Scott Mitchell Telephone: (H)860-388-0258 (W) 860-662-0385

c. Connecticut Port Authority, Joseph Salvatore Telephone: 860-270-8199 Email: joseph.salvatore@ct.gov

d. Harbor Management Commission, Chairman, Raymond Collins Telephone: 860-395-3123

1.12 GENERAL SAFETY REQUIREMENTS

1.12.1 General

The Contractor shall take all necessary precautions in observing safety regulations in accordance with Section 01 35 26 GOVERNMENTAL SAFETY

SECTION 01 11 00 Page 10

REQUIREMENTS, and shall assume the responsibility to guard against causing of fires and/or explosions and to protect Government property. The Contractor shall perform the work in a manner consistent with security and with fire safety regulations especially with regards to ingress and egress. Temporary closures shall not compromise life safety, security or fire safety.

1.12.2 Contractor's Project Superintendent

The Contractor's project superintendent shall take an active role in enforcing the safety requirements by participation in safety conferences, hazard analysis, tool box meetings, walk-through inspections, correction of violations, etc., and including that of any subcontractor's work.

1.13 ENVIRONMENTAL PROTECTION

To provide for control of all environmental pollution arising from construction activities, the Contractor and its subcontractors, in the performance of this contract, shall comply with Section 01 57 20 ENVIRONMENTAL PROTECTION, and all applicable federal, state, and local laws and regulations concerning environmental protection pollution control and abatement.

1.14 PRECONSTRUCTION CONFERENCE

The Contracting Officer will conduct a preconstruction conference with key Contractor personnel. The purpose of the conference is to review contract requirements and to establish a working relationship between the Contractor's Staff and the Corps Of Engineers personnel who will be closely associated with the project. During the conference, the Contracting Officer will inform the Contractor concerning Job Safety, Quality Control, Labor Relations, and Environmental Protection. The Contractor's Superintendent and Quality Control Representative shall attend this conference.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 11 00 Page 11

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 SUBMITTALS

1.2 JOB PAYMENT ITEMS

1.3 UNIT PRICE PAYMENT ITEMS

1.4 BIDDING SCHEDULE - PAYMENT ITEMS

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 22 00 Page 1

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-05 Design Data

Quantity Surveys

Submit originals of all field notes and all other records relating to quantity surveys.

1.2 JOB PAYMENT ITEMS

Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.3 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items. Submit originals of all field notes and all other records relating to Quantity Surveys.

1.4 BIDDING SCHEDULE - PAYMENT ITEMS

Payment items for the work of this contract on which the contract progress payments will be based are listed in the BIDDING SCHEDULE and are described below. All costs for items of work, which are not specifically mentioned to be included in a particular Bidding Schedule job or unit price payment item, shall be included in the listed job item most closely associated with the work involved.

BASE BID ITEMS:

a. Item Number 0001, "Mobilization and Demobilization for Dredging and

SECTION 01 22 00 Page 2

Disposal".

Payment will be made for costs associated with mobilization and demobilization for dredging and disposal operations, as defined in Special Contract Requirements clause "PAYMENT FOR MOBILIZATION AND

DEMOBILIZATION".

Unit of Measure: Job.

b. Item Number 0002, "Maintenance Dredging of Material From the 11-foot Federal Channel and the 11-foot Federal Anchorage with disposal at the Central Long Island Disposal Site."

The contract price per cubic yard for Item Number 0002 shall include all cost to remove all materials encountered from the 11 Foot Channel and the 11-Foot Anchorage at North Cove to the specified depth, and the costs associated with the transportation of dredged material from the cove to the disposal location as specified in the contract specifications and as indicated on the contract drawings. Include survey effort (pre-survey, interim, final).

The total amount of material removed, transported and disposed, will be measured by the cubic yard in place by computing the volume between the bottom surface shown by soundings of the last pre-dredge survey made before dredging begins and the bottom surface shown by the soundings of a post-dredge survey made as soon as practicable after the removal of the material. Dredged material will be included that is within the limits of the side slopes and specified channel overdepth as described in Section 35 20 23 DREDGING, paragraph OVERDEPTH AND SIDE SLOPES, less any deductions that may be required for misplaced material described in paragraph PLACEMENT OF EXCAVATED

MATERIAL.

The contract drawings listed in Special Contract Requirements, Paragraph "Contract Drawings, Maps and Specifications" are believed to accurately represent conditions existing on the date of the survey shown on the drawings, but the depths and the specific areas to be dredged shown thereon may be verified and corrected by soundings taken by the Government before dredging begins. Determination of quantities removed and the deductions made to determine quantities after having once been made by the Contracting Officer, will not be reopened, except on evidence of collusion, fraud, or obvious error.

Monthly partial payments will be based on approximate quantities dredged and disposed as determined by Contractor quality control surveys. The pre-dredge survey made immediately before dredging, and the post-dredge survey made as soon as practicable after the removal of the material, will be performed by the Government at no cost to the Contractor.

Also refer to Section 35 20 23 DREDGING, Subpart "Overdepth and Side Slopes".

Unit of Measure: Cubic Yard (CD).

c. Item Number 0003, "Derelict Mooring Removal and Recovery."

SECTION 01 22 00 Page 3

The contract price for each Item Number 0003 shall include all costs for removal and recovery of existing derelict moorings within the Federal anchorages. Recovered moorings shall be placed in an onshore location determined by the COR and coordinated with the Harbormaster.

Unit of Measure: Each (EA).

d. Item Number 0004, "(Optional Bid Item), "Turbidity Curtain.".

Payment will be made for costs associated with providing turbidity curtains as specified in Section 01 57 20 ENVIRONMENTAL PROTECTION per linear foot.

Unit of Measure: Linear Foot (LF).

ADDITIVE ITEMS

Item number 0005 Maintenance Dredging of Material from Federal 6-Foot Anchorage with Disposal at Central Long Island Sound Disposal Site

Item number 0006 Maintenance Dredging of Material from Federal 6-Foot

Item number 0007 Maintenance Dredging of Material from Federal 6-Foot

Item number 0008 Maintenance Dredging of Material from Federal 6-Foot

The contract price per cubic yard for Item Numbers 0005 through 0008 shall include all cost to remove all materials encountered from the Federal anchorage to the authorized depth plus one-foot allowable overdepth beginning from the eastern end of the anchorage (station 31+89) and working in towards the western end (station 44+64), and the costs associated with the transportation of dredged material to the Central Long Island Sound Disposal Site (CLDS)as indicated on the contract drawings.

The total amount of material removed, transported and placed in CLDS and paid for under the contract for these Items, will be measured by the cubic yard in place by computing the volume between the bottom surface shown by soundings of the last pre-dredge survey made before dredging begins and the bottom surface shown by the soundings of a post-dredge survey made as soon as practicable after the removal of the material. Dredged material will be included that is within the limits of the side slopes and specified channel overdepth as described in Section 35 20 23 DREDGING, paragraph OVERDEPTH AND SIDE SLOPES, less any deductions that may be required for misplaced material described in paragraph PLACEMENT OF EXCAVATED

MATERIAL.

The contract drawings listed in Special Contract Requirements, Paragraph "Contract Drawings, Maps and Specifications" are believed to accurately represent conditions existing on the date of the survey shown on the drawings, but the depths and the specific areas to be dredged shown thereon may be verified and

SECTION 01 22 00 Page 4 corrected by soundings taken by the Government before dredging begins. Determination of quantities removed and the deductions made to determine quantities after having once been made by the Contracting Officer, will not be reopened, except on evidence of collusion, fraud, or obvious error.

Monthly partial payments will be based on approximate quantities determined by Contractor quality control surveys. The pre-dredge survey made immediately before dredging, and the post-dredge survey made as soon as practicable after the removal of the material, will be performed by the Government at no cost to the Contractor.

Also refer to Section 35 20 23 DREDGING, Subpart "Overdepth and Side Slopes".

Unit of Measure: Cubic Yard (CD).

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 22 00 Page 5

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

1.2.2 Approving Authority

1.2.3 Work

1.3 SUBMITTALS

1.4 SUBMITTAL CLASSIFICATION

1.4.1 Government Approved (G)

1.4.1.1 Approval Codes

1.4.2 Information Only

1.5 PREPARATION

1.5.1 Transmittal Form

1.6 QUANTITY OF SUBMITTALS

1.7 INFORMATION ONLY SUBMITTALS

1.8 VARIATIONS

1.8.1 Considering Variations

1.8.2 Proposing Variations

1.8.3 Warranting That Variations Are Compatible

1.8.4 Review Schedule Is Modified

1.9 SUBMITTAL REGISTER

1.9.1 Use of Submittal Register

1.9.2 Contractor Use of Submittal Register

1.9.3 Approving Authority Use of Submittal Register

1.9.4 Copies Delivered to the Government

1.10 SCHEDULING

1.11 GOVERNMENT APPROVING AUTHORITY

1.11.1 Review Notations

1.12 DISAPPROVED SUBMITTALS

1.13 APPROVED SUBMITTALS

1.14 WITHHOLDING OF PAYMENT

1.15 STAMPS

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 33 00 Page 1

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.

Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.

Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Contractor's Quality Control (CQC) System Manager to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:

Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.

Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

Submittals requirements are specified in the technical sections.

Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Preconstruction Submittals

Submittals which are required prior to start of construction (work) or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.

Safe Practice Manual

Certificates of Insurance

Surety Bonds

SECTION 01 33 00 Page 2

List of Proposed Subcontractors

List of Proposed Products

Construction Progress Schedule

Submittal Register

Schedule of Prices

Health and Safety Plan

Work Plan

Quality Control(QC) Plan

Environmental Protection Plan

Pre-Diving Submittals

Diving Plan

Activity Hazard Analysis

Emergency Management Plan

Dive Personnel Qualifications

SD-05 Design Data

Design calculations, mix designs, analyses or other data pertaining to a part of work.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports.

Daily logs and checklists.

Final acceptance test and operational test procedure.

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material

SECTION 01 33 00 Page 3 attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.

Confined space entry permits.

Text of posted operating instructions.

1.2.2 Approving Authority

Office or designated person authorized to approve submittal.

1.2.3 Work

As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD-01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.

SD-01 Preconstruction Submittals

Submittal Register; G, RO

1.4 SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

1.4.1 Government Approved (G)

Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer.

Within the terms of the Contract Clause entitled, "Specifications and Drawings for Construction," they are considered to be "shop drawings."

1.4.1.1 Approval Codes

a. Construction/Operations Division {"AO" (Area Office), "RO" (Resident Office), or "PO" (Project Office) Reviewer}: An "AO", "RO", or "PO" in column "f" indicates that the submittal review action is by New England District Construction/Operations Division. Send all such submittals to the project Resident or Area Engineer, as applicable.

b. Engineering/Planning Division {"DO" (District Office) Reviewer): A

SECTION 01 33 00 Page 4

"DO" on the attached submittal register, column "f" indicates that the submittal review action is by the New England District, Engineering/Planning Division, or other organization in the District Office. Send all such submittals to the project Resident or Area Engineer for distribution to the appropriate approving authority.

c. Architect-Engineer Firm {"AE" reviewer): An "AE" on the attached submittal register, column "f" indicates that the submittal review action is by the Architect-Engineer firm asscociated with the project.

d. A "G" followed by "SJ" on the attached submittal register, column "f" indicates that the submittal review action is by the South Atlantic Division, Mobile District, 109 Saint Joseph Street, Mobile, Alabama 03668.

e. Government acceptance is required for submittals with a "G, A" designation.

1.4.2 Information Only

Submittals not requiring Government approval will be for information only.

They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.

1.5 PREPARATION

1.5.1 Transmittal Form

Use the attached sample transmittal form (ENG Form 4025) for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor and are included in the QCS software that the Contractor is required to use for this contract. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.

1.6 QUANTITY OF SUBMITTALS

Submit an electronic PDF copy and seven paper copies of each submittal item with an attached ENG FORM 4025 Transmittal Form. The Contractor will be informed at the pre-construction conference to send all submittals to either the project Resident Office or to the project Area Engineer Office, or other office, as applicable.

1.7 INFORMATION ONLY SUBMITTALS

Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals.

The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;

and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

SECTION 01 33 00 Page 5

1.8 VARIATIONS

Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.

1.8.1 Considering Variations

Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).

Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.

1.8.2 Proposing Variations

When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.

Clearly mark the proposed variation in all documentation.

Check the column "variation" of ENG Form 4025 for submittals which include proposed deviations requested by the Contractor. Set forth in writing the reason for any deviations and annotate such deviations on the submittal.

The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.

1.8.3 Warranting That Variations Are Compatible

When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.

1.8.4 Review Schedule Is Modified

In addition to normal submittal review period, a period of 10 working days will be allowed for consideration by the Government of submittals with variations.

1.9 SUBMITTAL REGISTER

Prepare and maintain submittal register, as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and

(i) as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required. Maintain a submittal register for the project in accordance with Section 01 45 01 QUALITY CONTROL SYSTEM (QCS). The Government will provide the initial submittal register in

SECTION 01 33 00 Page 6 electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.

Column (c): Lists specification section in which submittal is required.

Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section.

Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.

Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government.

1.9.1 Use of Submittal Register

Submit submittal register. Submit with QC plan and project schedule.

Verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:

Column (a) Activity Number: Activity number from the project schedule.

Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.

Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.

Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.

1.9.2 Contractor Use of Submittal Register

Update the following fields with each submittal throughout contract.

Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.

Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.

Column (l) List date of submittal transmission.

Column (q) List date approval received.

1.9.3 Approving Authority Use of Submittal Register

Update the following fields.

Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.

Column (l) List date of submittal receipt.

SECTION 01 33 00 Page 7

Column (m) through (p) List Date related to review actions.

Column (q) List date returned to Contractor.

1.9.4 Copies Delivered to the Government

Deliver one copy of submittal register updated by Contractor to Government with each invoice request.

1.10 SCHEDULING

Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Include certifications to be submitted with the pertinent drawings at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.

a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.

b. Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the…