About this file

Amendment 0004

View the file

Other files for this federal contract opportunity

Other files attached to North Cove Maintenance Dredging, newest first.
File Type Posted
BidAbstract_North_Cove-signed.pdf PDF
Amendment_0003_FINAL.pdf PDF
Amendment_0002_FINAL(1).pdf PDF
Amendment_0001_FINAL.pdf PDF
Solicitation_W912WJ17B0015_(FINAL).pdf PDF
SPECS-NORTH_COVE-2017(1).pdf PDF
PLANS-NORTH_COVE-2017-signed.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment is being issued to respond to requests for information (RFIs).

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 21-Aug-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912WJ-17-B-0015

X 9B. DATED (SEE ITEM 11)

20-Jul-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

21-Aug-2017

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912WJ-17-B-0015

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

Q1: The government appears to initially state it will conduct a pre‐dredge survey. However, it then qualifies this general statement by noting it may use its pre‐existing specification survey as a pre‐dredge survey of record, but only for non‐dynamic areas, even if the specification survey is over 180 days old. Is this a correct reading of the relevant terms?

Response: Yes, this is correct. However there are no non‐dynamic areas in this project.

Q2: If so, then please define, using specific coordinates if possible, what areas within the specified dredge prism the government regards as non‐dynamic within the meaning of this language.

Response: There are no non‐dynamic areas in the dredge area.

Q3: We also read the pre‐dredge section of the specifications as indicating it is left to the contractor to do its own pre‐dredge survey at its option and to alert the government of any discrepancy between the contractor's pre‐ dredge survey and the government's survey. Is this correct?

Response: Yes, this is correct.

Q4: If so, then how will the government resolve discrepancies brought to its attention by the contractor? By what standard?

Response: Discrepancies will be handled on a case by case basis after comparing the two surveys.

Q5: Please clarify the apparent ambiguity in the Definitive Responsibility Criterion which states: "Bidders are not required to submit additional documentation related to this criterion at the time of bid, however the apparent awardee shall submit documentation that they meet the above definitive responsibility criterion to the Government by close of business the day of the bid opening to support the responsibility determination." Is the submission of this information a determination of responsiveness? Please clarify the above, as the statement of "… documentation related to the definitive responsibility criterion will be considered a matter of responsibility, not responsiveness…" appears to be a distinction without a difference.

Response: The apparent low bidder shall submit documentation that they meet the above definitive responsibility criterion to the Government by close of business the day of the bid opening to support the responsibility determination. This is a matter of responsibility per FAR 9.104‐2, not responsiveness per

FAR 14..

Q6: Relative to Bid Item Note 3: Please clarify what the Government is referring to when it references "basic requirements" as this term doesn't appear anywhere else in the solicitation or specification.

Response: The term “basic requirement” in Note 3 on page 4 of the solicitation refers to Bid Items 0001 thru 0003

W912WJ-17-B-0015

Q7: Relative to Note 5: How does this notification of descending importance of additive items affect the contractor?

Response: Additive Bid Items are listed in order of priority to comply with DFARS clause 252.236‐7007 and allow for the proper evaluation of additive items to determine the low offeror.

Q8: Relative to Note 10: The specification indicates that the "turbidity curtain shall be suspended no more than 6" from the harbor bottom at high tide & Silt curtain shall be elevated above the harbor bottom before moving as to not drag the curtain across the beds, inducing turbidity." (Sec. 01 57 20 Pg. 8) Given this restriction, dredge movement will be limited to one location per tide cycle due to the prohibition of dragging the turbidity curtain across the bottom. This also creates a different problem when addressing the cut face of the dredge area which varies greatly from the areas yet to be dredged, as the contractor would have to swap in and replace various sections of the curtain in order to maintain this standard. How does the Government expect the contractor to maintain the required production rate while maintaining this extra standard?

Response: The requirement to have the turbidity curtain suspended no more than 6” from the bottom is to facilitate containment of a dredge induced plume at the bottom of the water column. The Turbidity curtain is allowed to come to rest on the bottom between tide cycles during dredging operations, including the area of the cut face. A significant length (2000 feet) of turbidity curtain has been included in CLIN 0004 to allow the contractor the option to set up a substantially large footprint of turbidity curtain in which to make multiple dredge movements. The Contractor will be permitted to enclose the entire dredge area that remains to be dredged after January 31, 2018.

Q9: Request for the Definitive Responsibility Criteria for this project be waived or modified in the final amendment.

Response: The Definitive Responsibility Criteria for this project will not be waived or modified.

Q10: Will the USACE consider adjusting the performance requirements of the project by allowing the construction of the work to occur in the 2018 dredging window?

Response: No, the dredging window will not be adjusted.

(End of Summary of Changes)