This project is a total small business set aside. A site visit for this project will be held on Wednesday 7 September 2011 at 10 00AM. Please follow the instructions for attending the site visit. Site visit instructions will be found on pages 30 - 31 of the solicitation. Proposals for this project will be due no later than 11 00AM on 16 September 2011. Proposals may be submitted by fax or email and all proposals shall be submitted on the standard form 1442 or your companies letterhead.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
F9S3S11202A001
Remove and replace the cabinets in the fuels lab of building 28.
MICHAEL KENNETH SPATUZZI 518 344-2487
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
26-Aug-2011
(RFP)
(IFB)
X
CALL:
POL CABINETS
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______14 calendar days and complete it w ithin ________15 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
YES X NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________16 Sep 2011 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______ calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
W912PQ - 109 MSG/MSC
1 AIR NATIONAL GUARD ROAD
SCOTIA NY 12302-9752
W912PQ
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
11:00 AM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
VBDZ112033
8. ADDRESS OFFER TO (If Other Than Item 7)
518-344-2687FAX:TEL: 518-344-2477 TEL: FAX:
W912PQ-11-R-0056 35
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued)
(Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W912PQ-11-R-0056
Section 00010 - Solicitation Contract Form
DAVIS BACON WAGE RATES
General Decision Number: NY100002 08/12/2011 NY2
Superseded General Decision Number: NY20080002
State: New York
Construction Types: Building, Heavy and Highway
Counties: Albany, Columbia, Fulton, Greene, Montgomery, Rensselaer, Saratoga, Schenectady, Schoharie and Washington
Counties in New York.
BUILDING CONSTRUCTION PROJECTS (For all counties except
COLUMBIA, FULTON & GREENE) (does not include single family homes and apartments up to a including 4 stories), HEAVY AND
HIGHWAY CONSTRUCTION PROJECTS
Modification Number Publication Date
0 03/12/2010
1 04/16/2010
2 04/30/2010
3 07/23/2010
4 09/24/2010
5 10/08/2010
6 10/15/2010
7 11/12/2010
8 11/19/2010
9 12/03/2010
10 01/28/2011
11 02/04/2011
12 02/25/2011
13 04/22/2011
14 05/06/2011
15 05/20/2011
16 06/03/2011
17 06/10/2011
18 06/17/2011
19 07/01/2011
20 07/08/2011
21 08/05/2011
22 08/12/2011
ASBE0040-002 05/01/2009
Rates Fringes
Asbestos/Insulator Worker
SCOPE OF WORK: includes application of all insulating materials, protective, coverings, coating and finishing to all types of mechanical systems.....................$ 27.14 16.88
HAZARDOUS MATERIAL HANDLER
Duties limited to preparation wetting;
stripping; removal;
scrapping; vacuuming;
bagging; and disposing of all insulation materials, whether they contain asbestos or not from mechancial systems..........$ 17.37 9.95
BOIL0197-002 10/20/2010
BOILERMAKER......................$ 30.00 17.23
BRNY0002-019 06/01/2010
BRICKLAYER
BRICKLAYERS, STONE MASONS,
CEMENT MASONS, PLASTERERS,
POINTERS, CAULKERS &
CLEANERS....................$ 26.91 15.78
HEAVY & HIGHWAY
CONSTRUCTION
CEMENT MASONS..............$ 27.87 15.04
MARBLE, TILE & TERRAZZO
FINISHERS...................$ 22.84 13.28
MARBLE, TILE & TERRAZZO
WORKERS.....................$ 28.78 15.78
CARP0019-002 07/01/2009
Carpenters:
HEAVY AND HIGHWAY
CONSTRUCTION (COLUMBIA AND
GREENE COUNTIES)
Carpenters, Millwrights, Pile Drivers...............$ 24.40 15.59
CARP0229-003 07/01/2009
SARATOGA COUNTY
HEAVY & HIGHWAY
CONSTRUCTION:
Carpenters.................$ 27.54 13.80
WASHINGTON COUNTY
CONSTRUCTION:
Carpenters.................$ 27.04 13.80
PAID HOLIDAYS: Labor Day, provided the employee has been on the payroll the calender week or any of the holiday week preceding the holiday and works the day after the holiday.
CARP0370-001 06/01/2010
ALBANY, FULTON, MONTGOMERY, RENSSELAER, SCHENECTADY AND
SCHOHARIE COUNTIES
BUILDING CONSTRUCTION
Carpenters & Soft Floor
Layers.....................$ 27.20 15.81
Piledriver.................$ 27.70 15.81
HEAVY & HIGHWAY
CONSTRUCTION
Carpenters.................$ 26.39 14.95
CARP0370-003 07/01/2009
CARPENTERS..................$ 26.39 14.95
DIVER TENDERS...............$ 25.49 14.95
DIVERS (Dry Day)............$ 25.49 14.95
DIVERS......................$ 60.00 14.95
PILEDRIVERS.................$ 24.49 14.95
* ELEC0236-001 06/01/2011
ALBANY; COLUMBIA; FULTON; GREENE (that portion North of a line following the south limits of the city of Catskill);
MONTGOMERY; RENSSELAER, SARATOGA; SCHENECTADY; SCHOHARIE;
WASHINGTON
ELECTRICIAN......................$ 32.50 3%+18.07
ELEC0363-004 04/01/2011
GREENE COUNTY (Portion of)
ELECTRICIAN......................$ 37.00 23.12
ELEC1249-003 01/01/2011
LINE CONSTRUCTION: Lineman
(LIGHTING AND TRAFFIC SIGNAL
Including any and all Fiber
Optic Cable necessary for
Traffic Signal Systems, Traffic Monitoring systems and Road Weather information systems)
Flagman.....................$ 23.28 15.00 + 6.5% +a
Groundman Truck Driver
(tractor trailer unit)......$ 32.98 15.00 + 6.5% +a
Groundman Truck Driver......$ 31.04 15.00 + 6.5% +a
Lineman & Technician........$ 38.80 15.00 + 6.5% +a
Mechanic....................$ 31.04 15.00 + 6.5% +a
FOOTNOTE:
a. New Year's Day, Memorial Day, Independence Day, Labor
Day, Thanksgiving Day, Christmas Day, plus President's Day, Good Friday, Decoration Day, Election Day for the President of the United States and Election Day for the Governor of the State of New York, provided the employee works the day before or the day after the holiday.
* ELEC1249-004 01/01/2011
Line Construction:
Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities (where no other trades are or have been involved):
Flagman....................$ 24.79 15.00+6.5%+a
Groundman digging machine operator...................$ 37.19 15.00+6.5%+a
Groundman truck driver
(tractor trailer unit).....$ 35.12 15.00+6.5%+a
Groundman Truck driver.....$ 33.06 15.00+6.5%+a
Lineman and Technician.....$ 41.32 15.00+6.5%+a
Mechanic...................$ 33.06 15.00+6.5%+a
Overhead transmission line work (where other trades are or have been involved):
Flagman....................$ 26.29 15.00+6.5%+a
Groundman digging machine operator...................$ 39.44 15.00+6.5%+a
Groundman truck driver
(tractor trailer unit).....$ 37.25 15.00+6.5%+a
Groundman truck driver.....$ 35.06 15.00+6.5%+a
Lineman and Technician.....$ 43.82 15.00+6.5%+a
Mechanic...................$ 35.06 15.00+6.5%+a
Substation:
Cable Splicer..............$ 45.45 15.00+6.5%+a
Flagman....................$ 24.79 15.00+6.5%+a
Ground man truck driver....$ 33.06 15.00+6.5%+a
Groundman digging machine operator...................$ 37.19 15.00+6.5%+a
Groundman truck driver
(tractor trailer unit).....$ 35.12 15.00+6.5%+a
Lineman & Technician.......$ 41.32 15.00+6.5%+a
Mechanic...................$ 33.06 15.00+6.5%+a
Switching structures;
railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation
Cable Splicer..............$ 46.87 15.00+6.5%+a
Flagman....................$ 25.57 15.00+6.5%+a
Groundman Digging Machine
Operator...................$ 38.35 15.00+6.5%+a
Groundman Truck Driver
(tractor-trailer unit).....$ 36.22 15.00+6.5%+a
Groundman Truck Driver.....$ 34.09 15.00+6.5%+a
Lineman & Technician.......$ 42.61 15.00+6.5%+a
Mechanic...................$ 34.09 15.00+6.5%+a
TELEPHONE, CATV
FIBEROPTICS CABLE AND
EQUIPMENT
Cable splicer/Central
Office Person..............$ 23.07 3.05+3%
Cable splicer..............$ 27.44 4.43 + 3%
Groundman..................$ 13.81 4.43 + 3%
Installer Repairman-
Teledata
Lineman/Tecnician-
Equipment Operator.........$ 26.05 4.43 + 3%
TREE TRIMMER................$ 21.64 7.36+3%
a. PAID HOLIDAYS: New Year's Day, Presidents' Day, Memorial
Day, Good Friday, Independence Day, Labor Day, Thanksgiving
Day, Christmas Day, and Election Day for the President of the United States and Election Day for the Governor of New
York State, provided the employee works two days before or two days after the holiday.
b. New Years Day, Washington's Birthday, Good Friday, Decoration Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, Day after Thanksgiving Day and Christmas
Day.
ELEC1249-007 05/04/2009
LINE CONSTRUCTION (LINEMAN) LIGHTING AND TRAFFIC SIGNAL
INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR THE
TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD
WEATHER INFORMATION SYSTEMS
COLUMBIA COUNTY
LINE CONSTRUCTION: Lineman
Flagman.....................$ 23.00 13.50+6.5%+a
Groundman Digging Machine
Operator....................$ 34.51 13.50+6.5%+a
Groundman Truck Driver
(Tractor-trailer unit)......$ 32.59 13.50+6.5%+a
Groundman Truck Driver......$ 30.67 13.50+6.5%+a
Lineman and Technician......$ 38.34 13.50+6.5%+a
Mechanic....................$ 30.67 13.50+6.5%+a
PAID HOLIDAYS:
a. Memorial Day, New Year's Day, President's Day, Good
Friday, Decoration Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, and Election Day for the
President of the United States and Election Day for the
Governor of New York State, provided the employee works two days before or two days after the holiday.
ELEV0035-001 01/01/2011
ALBANY; COLUMBIA (Towns of Claverack, Hillsdale, Ghent, Stockport, Austerlitz, Canaan, New Lebanon, Chatham, Kinderhook, Styvesant and Greenport); FULTON; GREENE (Towns of
Durham, Greenville, New Baltimore, Coxcsackie and Athens);
MONTGOMERY, RENSSELAER, SARATOGA, SCHENECTADY, SCHOHARIE AND
WASHINGTON COUNTIES
Elevator Constructor.............$ 38.94 21.785
FOOTNOTES:
a. 8 PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving
Day, and the day after Thanksgiving Day, Christmas Day.
b. Employer contributes 8% of basic hourly rate for 5 years or more of service or 6% of basic hourly rate for 6 months to 5 years of service as vacation pay credit.
ELEV0138-004 01/01/2011
COLUMBIA COUNTY (THE TOWNS OF ANCRAM, CLERMONT, COPAKE,
GALLATIN, GERMANTOWN, LIVINGSTON, AND TAGHKANIC); GREEN COUNTY
(THE TOWNS OF HUNTER AND CATSKILL)
ELEVATOR MECHANIC................$ 48.96 21.785+a+b
a. 8 PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving
Day, the Friday after Thanksgiving Day and Christmas Day.
b. Employer contributes 8% of basic hourly rate for 5 years or more of service or 6% of basic hourly rate for 6 months to 5 years of service as vacation pay credit.
ENGI0106-001 07/01/2010
Power equipment operators:
GROUP 1.....................$ 33.87 19.65+a
GROUP 2.....................$ 33.44 19.65+a
GROUP 3.....................$ 32.53 19.65+a
GROUP 4.....................$ 29.96 19.65+a
GROUP 5.....................$ 35.05 19.65+a
GROUP 6.....................$ 34.37 19.65+a
GROUP 7.....................$ 34.87 19.65+a
POWER EQUIPMENT OPERATOR CLASSIFICATIONS (HEAVY & HIGHWAY)
GROUP 1: Boom Truck (over 5 tons), Crane, Cherry Picker (over
5 ton capacity), Derricks (steel erection), Dragline, Overhead Crane (Gantry or Straddle type), Pile Driver, Truck Crane
GROUP 2: Automated Concrete Spreader (CMI), Automatic Fine
Grader, Backhoe (Except Tractor Mounted, Rubber Tired), Backhoe Excavator Full Swing (CAT 212 or similar type), Belt Placer (CMI type), Black Top Plant (Automated), Boom
Truck (5 tons and under), Cableway, Caisson Auger, Central
Mix Concrete Plant (Automated), Concrete Pump (8" or over), Dredge, Dual Drum Paver, Excavator (All Purpose-Hydraulicly
Operated) (Gradall or similar), Fork Lift (Factory Rated 15
ft. and over), Front End Loader (4 c.y. and over), Head
Tower (Sauerman or equal), Hoist (2 or 3 Drum), Holland
Loader, Mine Hoist, Mucking Machine or Mole, Pavement
Breaker (SP) Wertgen; PB-4 and similar type, Power Grader, Profiler (over 105 H.P), Quad 9, Quarry Master (or equivalent), Scraper, Shovel, Side Boom, Slip Form Paver, Tractor Drawn Belt-Type Truck Crane, Truck or Trailer
Mounted Log Chipper (Self-Feeder), Tug Operator (Except
Manned Rented Equipment), Tunnel Shovel
GROUP 3: Asphalt Paver, Backhoe (Tractor Mounted, Rubber
Tired), Bituminous Spreader and Mixer, Blacktop Plant
(Non-Automated), Blast or Rotary Drill (Truck or Tractor
Mounted), Boring Machine, Cage-Hoist, Central Mix Plant
(Non-Automated) and All Concrete Batching Plants, Cherry
Picker (5 Tons Capacity and Under), Compressors (4 or less)
Exceeding 2000 C.F.M. Combined Capacity, Concrete Paver
(over 16S), Concrete Pump (Under 8"), Crusher, Diesel Power
Unit, Drill Rigs (Tractor Mounted), Front End Loader (under
4 c.y.), Hi-Pressure - Boiler (15 lbs. and over), Hoist
(One Drum), Kolman Plant Loader and Similar Type Loaders, L.C.M. Work Boat Operator, Locomotive, Maintenance
Engineer/Greaseman/ Welder, Mixer (For Stabilized Base
Self-Propelled), Monorail Machine, Plant Engineer, Profiler
(105 H.P. and under), Pug Mill, Pump Crete, Ready Mix
Concrete Plant, Refrigeration Equipment (For Soil
Stabilization), Road Widener, Roller (All Above Subgrade), Sea Mule, Self-contained Ride-on-Rock Drill, excluding
Air-Track Type Drill, Skidder, Tractor with Dozer and/or pusher, Trencher, Tugger Hoist, Vermeer saw (ride on, any size or type), Winch, Winch Cat
GROUP 4: A-Frame Winch Hoist on Truck, Ballast Regulator
(Ride- On), Compressors (4 not to exceed 2000 C.F.M.
Combined Capacity, or 3 or less with more than 1200 C.F.M.
but not to exceed 2000 C.F.M.), Directional Drill Machine
Locator Dust Collectors, Generators, Pumps, Welding
Machines, Light Plants (4 of Any Type Of Combination), Concrete Pavement Spreaders and Finishers, Conveyor, Drill
Core, Drill Well, Electric Pump Used In Conjunction with
Well Point System, Farm Tractor with Accessories, Fine
Grade Machine, Fork Lift (under 15 ft.), Grout Pump, Gunite
Machine, Hammers (Hydraulic-Self-Propelled), Hydra- Spiker
(Ride-On), Hydro-Blaster Water, Post Hole Digger and Post
Driver, Power Sweeper, Roller (Grade and Fill), Scarifier
(Ride-On Spansaw (Ride-On), Skid Steer loader (Bobcat or similar), Submersible Electric Pump (When Used In Lieu Of
Well Point System), Tamper (Ride-On), Tie Extractor
(Ride-On), Tie Handler, Tie Inserter (Ride-On), Tie Spacer
(Ride-On), Tire Repair, Track Liner, Tractor With Towed
Accessories, Vibrator Compactor, Vibro Tamp, Well Point, Aggregate Plant, Boiler (Used In Conjunction With
Production), Cement and Bin Operator, Compressors (3 or less not to Exceed 1200 C.F.M. Combined Capacity), Dust
Collectors, Generators, Pumps, Welding Machines, Light
Plants (3 or less of Any Type or Combination), Concrete or
Mixer (16S and under), Concrete Saw (Self-Propelled), Fireman, Form Tamper, Hydraulic Pump (Jacking System), Light Plants, Mulching Machine, Oiler, Parapet-Concrete or
Pavement Grinder, Power Broom (Towed), Power Heaterman, Revinius Widener, Shell Winder, Steam cleaner, Tractor
GROUP 5: Master Mechanic
GROUP 6: Crane Premium with Boom Length and Jib 150 Ft.- 199
Ft.
GROUP 7: Crane Premium with Boom Length and Jib 200 Ft. and over
Tower Crane Premium .50
Hazmat Work Premium 2.50
Hydrographic .50
a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence
Day, Labor Day, Thanksgiving Day, Christmas Day, Lincoln's
Birthday, Washington's Birthday, Good Friday, Columbus Day, November Election Day and Veteran's Day
ENGI0106-002 07/01/2010
BUILDING
Power equipment operators:
GROUP 1.....................$ 33.88 19.79+a
GROUP 2.....................$ 33.44 19.79+a
GROUP 3.....................$ 32.53 19.79+a
GROUP 4.....................$ 29.96 19.79+a
GROUP 5
1..........................$ 34.38 19.79+a
2..........................$ 34.88 19.79+a
GROUP 6.....................$ 34.38 19.79+a
GROUP 7.....................$ 35.43 19.79+a
GROUP 8.....................$ 37.93 19.79+a
Hazardous work - Anytime Operating Engineers are involved with level C or above, $2.50 per hour over regular rate.
a. Paid Holidays: New Years Day, Memorial Day, Independence
Day, Labor Day, Thanksgiving Day, Christmas Day.
POWER EQUIPMENT OPERATOR CLASSIFICATIONS (BUILDING)
GROUP 1: Crane, hydraulic cranes, tower crane, locomotive crane, piledriver, cableway, derricks, whirlies, dragline, boom truck (over 5 tons)
GROUP 2: Shovel, All backhoe (except tractor mounted rubber tired John Deere 510 or smaller), gradalls, power road grader, all CMI equipment, front-end rubber tire loader, tractor-mounted drill (quarry master), mucking machine, concrete central mix plant, concrete pump, Belcrete system, automated asphalt concrete plant and tractor road paver, boom truck (5 tons and under)
GROUP 3: Backhoe, (tractor mounted rubber tired equivalent to John Deere 510 or less), bulldozer, pushcat, tractor, traxcavator, scraper, LeTourneau grader, form fine grader, road roller, blacktop roller, blacktop spreader, power brooms, sweepers, trenching machine, Barber Green loader, side booms, hydrohammer, concrete spreader, concrete finishing machine, one drum hoist, power hoisting (single drum), hoist - two drum or more, three drum engine, power hoisting (two drum and over), two drum and swinging engine, three drum swinging engine, hod hoist, A-L frame winches, cord and well drillers (one drum), post hole digger, model
CHB Vibro-Tamp or similar machine, batch bin and plant operator, dinkey locomotive, skid steer loader, track excavator 5/8 cu. yd. or smaller
GROUP 4: Fork lift, high lift, lull, oiler, fireman and heavy- duty greaser, boilers, and steam generators, pump, vibrator, motor mixer, air compressor, dust collector, welding machine, well point, mechanical heater, generators, temporary light plants, concrete pumps, electric submersible pump 4" and over, murphy type diesel generator, conveyor, elevators, concrete mixer and belcrete power pack
(belcrete system), seeding, and mulching machines, pumps
GROUP 5: Crane Premiums:
1 over 150'
2 over 200'
GROUP 6: Tower Crane
GROUP 7: Master mechanic (other than nuclear work)
GROUP 8: Master mechanic on nuclear work
IRON0012-011 05/01/2011
ALBANY; COLUMBIA; FULTON (Albin, Bleecker, Broad, Johnstown, Mayfield, Northampton and Perth); GREENE, MONTGOMERY
(Amsterdam, Charleston, Florida, Glen, Mohawk and Root);
RENSSELAER, SARATOGA; SCHENECTADY; SCHOHARIE; and WASHINGTON
COUNTIES:
Ironworkers:
Sheeter, Bucker-up..........$ 25.78 17.96
Sheeter.....................$ 27.90 19.24
Structural, Ornamental, Rodman, Machinery Mover, Rigger, Fence Erector, Reinforcing, Stone
Derrickmen..................$ 27.65 19.24
IRON0440-007 05/01/2011
FULTON (Twps. of Caroga, Ephratah, Oppenheim, Stratford);
MONTGOMERY (Twps of Canajoharie, Minden, Palatine, St.
Johnsville):
Ironworkers:
Structural, Ornamental, Rodman, Machinery Mover, Rigger, Fence Erector, Reinforcement, and Stone
Derrickman..................$ 23.63 22.01
LABO0017-001 06/01/2010
COLUMBIA COUNTY (Twps of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont and the City of Hudson)
Laborers:
COLUMBIA COUNTY (Townships of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont, and the City of Hudson)
(Asbestos, lead, toxic and hazardous waste abatement and any other environmental related work) HEAVY & HIGHWAY
GROUP 1:...................$ 32.75 17.95+a
GROUP 2:...................$ 36.65 17.95+a
GREENE COUNTY (Township of
Catskill) HEAVY & HIGHWAY:
GROUP 1:...................$ 28.40 17.95+a
GROUP 2:...................$ 32.75 17.95+a
GROUP 3:...................$ 36.65 17.95+a
GROUP 4:...................$ 39.15 17.95+a
TUNNEL, SHAFT & CAISSON
WORK
GROUP 1....................$ 39.15 17.95+a
For HEAVY & HIGHWAY CLASSIFICATIONS in COLUMBIA COUNTY
(Townships of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont and the City of Hudson)
HEAVY & HIGHWAY CLASSIFICATIONS
GROUP 1: Asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous material abatement when protective equipment and clothing are not required
GROUP 2: Asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous material abatement when protective clothing and equipment is required
For HEAVY & HIGHWAY CLASSIFICATIONS in GREENE COUNTY
(Township of Catskill)
a. PAID HOLIDAYS: New Years Day, President's Day, Memorial
Day, Independence Day, Lincoln's Birthday, Labor Day, Election Day, Veterans Day, Thanksgiving Day, Christmas
Day, provided the employee is an employee of the company prior to the scheduled holiday and reports to work the first day following the holiday unless prevented from doing so for legitimate reasons.
GROUP 1: Flagperson, gateperson
GROUP 2: General laborers, chuck tender, handling and distributing drinking water, distributing all tools and supplies of laborers, nipper, powder carrier, magazine tender, warehouse laborers, concrete man, vibrator man, mason tender, mortar man, spraying, brushing and covering of concrete for curing and preservative purposes, traffic striper, scaffold builder, concrete curb and sidewalk form setter; permanent traffic striping and reflective devices, placing and maintenance of all flares, cones, lights, signs, barricades, traffic patterns, and all temporary reflective type materials for traffic control, custodial work, traffic directors, temporary heat or light tenders, tool room, dewatering pump men, pitman, dumpmen, snow removal and firewatch, asphalt man, joint setter, signal person, pipelayer, pipe lining and relining, wellpoints, conduit and duct layer, wire puller, rip rap and dry stone layer, steel rod carrier, core drill, rock splitter, Hilti gun air or electric, jackhammer, bush hammer, pavement breaker, chipping hammer, wagon drill, air track, jib rig, joy drill, gunite and sand blasting, coal passer and other machine operators, power tool operator, sprayer and nozzle man on mulching and seeding machine, all guard rail and fence, all seeding and sod laying, all landscape work, grade checker, all bridge work, walk behind self-propelled power saw, grinder, groover or similar type machine, walk behind tamper and roller of all types, salvage, stripping, wrecking and dismantling laborer (including barman, cutting torch and burner man), sheeting and shoring coming under laborers jurisdiction, bit grinder, operator of form pin puller and drivers, sandblasting, joint and jet sealer, filling and wiring baskets for gabion walls, permanent sign man, median barrier, sta-wall or similar type product, chain saw operator, railroad track laborer, waterproofer, pre-stressed and pre-cast concrete brick, block and stone pavers, power tools used to perform work usually done by laborers, power buggy and pumpcrete operator, fireproof, plaster and caustic pump, asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous materials abatement when protective clothing and equipment is not required, power brush cutter, retention liners, artificial turf, retaining walls, walk behind surface planer, welding related to laborers work, remote controlled equipment normally operated by laborers, all technician work including but not limited to stitching, seaming, heat welding, fireproof sprayer, mortar mixer, concrete finisher, form setter for concrete curbs and flatwork.
Gunite nozzle man, stone cutters, granite stone layer, manhole, catch basin or inlet installing, laser men.
Ground man on milling machine
GROUP 3 Ingersoll Rand heavy duty crawler-master HCMZ, any drill using a 4" or larger bit, asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous material abatement when protective clothing and equipment is required, all working foremen including grade, pipe concrete, clearing, blacktop, drill, paving and blaster etc., Hydraulic drill or similar, forklift for masonry only, Blaster and asphalt screedman
GROUP 4: Asbestos, toxic, lead or hazardous material abatement foreman
For TUNNEL, SHAFT & CAISSON WORK CLASSIFICATIONS
a. PAID HOLIDAYS: New Years Day, President's Day, Memorial
Day, Independence Day, Labor Day, Election Day, Veterans
Day, Thanksgiving Day, Christmas Day
GROUP 1: Laborer, Pit and Dumpman, Chuck Tender, Brakeman and
Powderman;
Miner and all machine men, Safety Miner, all shaft work, caisson work, drilling, blow pipe, all air tools, tugger, scaling, nipper gunniting from pot to nozzle, bit grinder, signal man (top and bottom), shield driven tunnel, mixed face and soft ground liner plate tunnel in free air
LABO0035-001 06/01/2010
FULTON (TWPS OF CAROGA, EPHRATA, OPPENHEIM, AND STRAFORD);
MONTGOMERY (TWPS OF CANAJOHARIE, MINDEN AND PALATINE, ROOT AND
ST. JOHNSVILLE)
Laborers Building Construction
Asbestos Removal............$ 21.50 13.44
Blasters, Form Setters, MotorBuggy Operator (Rider
Type)......................$ 20.50 13.44
Hazardous Waste Removal
Hazardous waste removal includes wetting, stripping, removal, scrapping, vaccuuming, bagging and disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems.........$ 21.50 13.44
HEAVY & HIGHWAY:
GROUP 1:...................$ 24.30 16.54
GROUP 2:...................$ 24.50 16.54
GROUP 3:...................$ 24.70 16.54
GROUP 4:...................$ 24.90 16.54
Laborers....................$ 20.00 13.44
Pipelayers, Motor Mixers, Motor Buggy Operator
(Walk Behind) Power Lift
(Walk Behind)...............$ 20.15 13.44
Wagon Drill Operator........$ 20.40 13.44
Day, Labor Day, Thanksgiving Day and Christmas Day.
GROUP 1: Common Laborers, Flagman, Outboard and Hand boats
GROUP 2: Bull Float, Chain Saw, Concrete aggregate bin, Concrete Bootman, Gin Buggy, Hand or Machine Vibrator, Jackhammer, Mason Tender, Mortar Mixer, Pavement Breaker, Handlers of all steel mesh, Small generators for laborer's tools, Installation of bridge drainage, Pipelayers, Vibrator type rollers, Tamper, Drill doctor, Tail or Screw
Operator on asphalt paver, Water pump operator (1 1/2" and single diaphragm), Nozzle (asphalt, gunnite, seeding and sand blasting), Laborers on chain link fence erection, Rock splitter and power unit, Pusher type concrete saw and all other gas, electric, oil, and air tool operators, Wrecking laborers
GROUP 3: All rock or drilling machine operators (except quarry master and similar type), Acetylene torch operators, and Asphalt paver, Powderman
GROUP 4: Blasterers, Form setters, Stone or Granite Curb setters
LABO0157-001 07/01/2009
FULTON (Twps. of Bleeker, Mayfield, Northhampton, Johnstown, Broadalbin and Perth); MONTGOMERY (Twps. of Mohawk, Glen, Charleston, Amsterdam, and Florida); SARATOGA (Twps. of Day, Hadley, Edinburg, Corinth, Moreau, South Glens Falls, Providence, Greenfield, Wilton, Northcumberland, Galway, Milton, Saratoga Springs, Charlton, Ballston, Malta and Clifton
Park); SCHENECTADY and SCHOHARIE COUNTIES.
LABORER
BUILDING:
GROUP 1....................$ 22.88 13.65
GROUP 2....................$ 24.23 13.65
HEAVY & HIGHWAY:
GROUP 1:...................$ 24.34 14.40+a
GROUP 2:...................$ 24.54 14.40+a
GROUP 3:...................$ 24.74 14.40+a
GROUP 4:...................$ 24.94 14.40+a
GROUP 5:...................$ 26.34 14.40+a
LABORER CLASSIFICATIONS
Group 1: Common Laborers
Group 2: Asbestos and Toxic Materials
Commercial projects valued at $800,000 or less and/or industrial projects valued at $100,000 or less, excluding demolition work (the complete razing of structures) 75% of the basic wage scale with full benefits will apply
a. PAID HOLIDAYS: New Years Day, Memorial Day, Independence
Day, Labor Day, Thanksgiving Day, and Christmas Day
LABORER CLASSIFICATIONS
GROUP 1: Common laborers, flagman, outboard & hand boats
GROUP 2: Bull float, chain saw, concrete aggregate bin, concrete bootman, gin buggy, hand or machine vibrator, jackhammer, mason tender, mortar mixer, pavement breaker, handlers of all steel mesh, small generators for laborers' tools, installation of bridge drainage, pipelayers, vibrator type rollers, tamper, drill doctor, tail or screw operator on asphalt paver, water pump operator (1 1/2") and single diaphragm), nozzle (asphalt, gunnite, seeding, and sand blasting), laborers on chain fence erection, rock splitter and power unit, pusher type concrete saw and all other gas, electric, oil, and air tool operators, wrecking
GROUP 3: All rock drilling machine operators (except quarry master and similar type), acetylene torch operator, and asphalt paver, powderman
GROUP 4: Blasterers, form setters, stone or granite curb
GROUP 5: Hazardous waste removal
LABO0190-001 07/01/2011
ALBANY; RENSSELAER COUNTY, WASHINGTON COUNTY, SARATOGA COUNTY
(Townships of Stillwater, Halfmoon, Saratoga)
BUILDING:
GROUP 1....................$ 22.66 16.42
GROUP 2....................$ 24.01 16.42
LABORERS CLASSIFICATIONS
GROUP 1: Common Laborers
GROUP 2: Hazardous waste removal Commercial projects valued at $800,000 or less and/or industrial projects valued at
$100,000 or less excluding demolition work, (complete razing of structures) will receive 75% of basic wage scale with full fringes will apply
LABO0190-002 07/01/2011
ALBANY; RENSSELAER; COLUMBIA (Twps. of Stuyvesant, Stockport, Kinderhook, New Lebanon, Cannan, Ghent, Chatham, Austerlitz).
GREENE (except Catskill Township). WASHINGTON COUNTY. SARATAGO
COUNTY (Townships of Stillwater, Halfmoon Saratoga)
HEAVY & HIGHWAY:
GROUP 1:...................$ 25.39 16.95
GROUP 2:...................$ 25.39 16.95
GROUP 3:...................$ 25.59 16.95
GROUP 4:...................$ 25.79 16.95
GROUP 5:...................$ 25.99 16.95
PAID HOLIDAYS: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.
LABORERS CLASSIFICATIONS
GROUP 1: Common laborers, flagmen, outboard and hand boats
GROUP 2: Bull float, chain saw, concrete aggregated bin, concrete bootman, gin buggy, hand or machine vibrator, jackhammer, mason tender, mortar mixer, pavement breaker, handlers of all steel mesh, small generators for laborers' tools, installation of bridge drainage, pipelayers, vibrator type rollers, tampers, drill doctor, Tail or screw operator on asphalt paver, Water pump operator (1 1/2" and single diaphragm), Nozzle (asphalt, gunnite, seeding, and sand blasting) Laborers on chain link fence erection, rock splitter and power unit, pusher type concrete saw and all other gas, electric, oil, air tool operators, and wrecking
GROUP 3: All rock air drilling machine operators (except quarry master and similar type), acetylene torch operators, and asphalt paver, powderman
GROUP 4: Blasterers, form setters, stone or granite curb
GROUP 5: Hazardous waste removal
LABO1000-005 05/01/2009
COLUMBIA (Twps. of Greenport, Claverack, Hillsdale, Livingston, Germantown, Taghkanic, Copake, Clermont, Gallatin, Ancram):
GROUP 1....................$ 24.20 18.75+a
GROUP 2....................$ 27.96 18.75+a
GROUP 3....................$ 28.96 18.75+a
LABORERS CLASSIFICATIONS (HEAVY & HIGHWAY)
GROUP 1: Flagperson; Placing and maintenance of all flares, cones, lights, signs, barricades; traffic control custodial work; traffic directors; temporary heat or light tenders;
tool rooms
GROUP 2: General Laborers, Dumpman, Pitman, Concrete man;
Signal man; Pipelayers; Rip rap; Dry stone layer; Jack hammer; Powderman; Highscalers power buggy operator; Steel rod carrier; Vibratory operator; other machine operator;
wrecking; Vibrator operator-compactor; Gunite and sandblasting; Water pump 2" or under; Nipper; Chucker;
Asphalt Workers
GROUP 3: Asphalt raker; Asphalt Screedman; Drillers (all);
Laser Beam Operator; Form Setter/Aligners; Blasters
a. PAID HOLIDAYS: New Years Day, Presidents Day, Good Friday, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, November Election Day, Thanksgiving Day, and
Christmas Day
PAIN0009-005 05/01/2010
Painters:
Lead Abatement Workers, Structural Steel
Zone 1.....................$ 26.04 8.58
Zone 2.....................$ 24.79 9.83
Painters, Drywall
Finishers, Spray
Zone 1.....................$ 25.04 8.58
Zone 2.....................$ 23.79 9.83
Zone #1 Entire counties of ALBANY, FULTON, MONTGOMERY, RENNSELAER, SCHOHARIE, SCHENECTADY AND SARATOGA
ZONE #2 All of WASHINGTON County
PAIN0009-013 07/01/2010
GLAZIER..........................$ 23.10 14.59
PAIN0155-002 05/01/2010
COLUMBIA AND GREENE COUNTIES
Drywall Finisher............$ 27.39 16.31
Lead Abatement Work.........$ 27.39 16.31
Painter/Paperhanger.........$ 27.39 16.31
Spray Rate..................$ 28.39 16.31
PAIN0806-002 10/01/2010
ALBANY, COLUMBIA, FULTON, GREENE, MONTGOMERY, RENNSELAER,
SCHOHARIE, SCHENECTADY, SARATOGA AND WASHINGTON
Structural Steel and Bridge.$ 46.25 31.03
PLUM0007-001 05/01/2011
ALBANY; COLUMBIA; FULTON; GREENE; MONTGOMERY; RENSSELAER;
SCHENECTADY; SARATOGA (Towns of Charlton, Clifton Park, Galway, Halfmoon, Milton, Stillwater and Waterford)
PLUMBER/PIPEFITTER...............$ 33.46 20.95
PLUM0112-019 05/01/2011
Townships of Canajoharie and Minden
Plumber and Steamfitter
Northern Zone...............$ 29.90 19.49
PLUM0773-002 05/01/2011
SARATOGA (Remainder of County); WASHINGTON COUNTY:
PLUMBER/PIPEFITTER...............$ 30.25 20.53
ROOF0203-003 06/01/2007
SCHOHARIE COUNTY:
ROOFER, Including Built Up, Composition and Single Ply
Roofs............................$ 21.20 10.34
ROOF0241-001 06/01/2010
ROOFER, Including Built Up, Composition and Single Ply
Roofs............................$ 25.65 10.97
SFNY0669-001 04/01/2011
SPRINKLER FITTER.................$ 30.15 18.90
SHEE0083-001 06/01/2011
Sheet metal worker...............$ 29.78 20.21+a
Day, Labor Day, Thanksgiving Day, Christmas Day. If any of these holidays fall on a Saturday or Sunday, either the preceding Friday or following Monday will be observed as the holiday.
TEAM0294-002 05/01/2006
BUILDING CONSTRUCTION
Truck drivers:
GROUP 1.....................$ 22.27 9.84+a
GROUP 2.....................$ 22.57 9.84+a
a. One week vacation after 1 year; 2 weeks vacation after 5 years.
TRUCK DRIVERS BUILDING CLASSIFICATIONS
GROUP 1: Straight, winch, transit mix on job site, road oilers, dump, panel, pick-up, water and fuel trucks on site
(including nozzle)
GROUP 2: Euclid or similar equipment, lowboy or lowboy trailers
TEAM0294-003 07/01/2011
Truck drivers:
GROUP 1....................$ 26.67 15.65+a
GROUP 2....................$ 26.72 15.65+a
GROUP 3....................$ 26.77 15.65+a
GROUP 4....................$ 26.92 15.65+a
GROUP 5....................$ 27.07 15.65+a
TRUCK DRIVERS CLASSIFICATIONS (HEAVY & HIGHWAY)
GROUP 1: Pick-ups, panel trucks, flatboy material trucks
(straight jobs), single axle dump trucks, dumpsters, receivers, greasers, truck tireman
GROUP 2: Tandems, batch trucks, mechanics
GROUP 3: Semi-trailers, low-boy trucks, asphalt distributor trucks, agitator, mixer trucks and dumpcrete type vehicles, truck mechanic, fuel truck
GROUP 4: Specialized earth moving equipment - euclid type or similar off-highway equipment, where not self-loaded, straddle (ross) carrier, self-contained concrete unit
GROUP 5: Off-highway tandem back dump, twin engine equipment and double hitched equipment where not self-loaded
Day, Labor Day, Thanksgiving Day, Christmas Day, provided the employee works the day before and the day after the holiday.
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses
(29CFR 5.5 (a) (1) (ii)).
In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour
Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the
Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the
Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator
(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator
U.S. Department of Labor
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
STATEMENT OF WORK
Scope of Work
POL Cabinets
Project Number VBDZ112033
PROJECT DESCRIPTION
The Contractor shall provide all material, labor, equipment, and supervision required to remove and replace the cabinets in the fuels lab of bldg 28. The new cabinets will be sized according to the attached sketch and comparable to the attached specs. The cabinets will be modified to accommodate the existing ductwork. This project will also include new epoxy resin countertops, new 4” cove base, and a new sink fixture. The Contractor will coordinate work schedule with 109 th Civil Engineering. All measurements are approximate; it is the Contractor’s responsibility to verify accuracy of measurements. The Contractor will be responsible for the repair or replacement of any damages to Air Force property that they inflict.
Due to the scope of the project it is highly recommended that the Contractor attend a pre-arranged site visit prior to submitting a bid.
CONTRACTOR REQUIREMENTS
1. The Contractor is responsible for the proper disposal of all rubbish off-base.
2. The Contractor is required to follow all environmental regulations including providing 109 th
Civil Engineering with all applicable MSDS sheets.
3. The Contractor will submit all warrantee information against defects in material and workmanship upon completion of installation.
4. The Contractor is responsible for accuracy of all measurements and the implementation of appropriate building codes. The Contractor must get approval from Civil Engineering
Production Control (344-2441) and/or Engineering (344-2568) before starting work and before any utility shutdowns.
5. The Contractor is responsible for site cleanliness.
6. The Contractor shall provide product submittals for equipment and materials. The 109
Civil Engineering Squadron will review product submittals and return them to the
Contractor. The Government will select colors from product submittal data. Only materials approved by the 109
Civil Engineering Squadron will be used for this project.
PROPOSED PROJECT SCHEDULE
The project will begin 14 days following the Notice to Proceed. The project shall be completed within
15 calendar days following the start date.
LIQUIDATED DAMAGES
STATEMENT OF LIQUIDATED DAMAGES
(Project: POL Cabinets VBDZ112033)
In accordance with FAR 36.206, liquidated damages will be assessed for each calendar day required to complete the construction work on this project past the scheduled completion date. The contractor has complete control of the pace of work. Liquidated damages shall be in the amount as follows:
$420.00 Each day past scheduled completion date.
$300.00 One-time fixed cost.
Itemized Costs
CIVIL ENGINEER
Engineer 4.00 hrs/day @ $55.00/hr = $220.00 per day
Project Engineer 0.0 hrs/day @ $25.00/hr =
Inspector 4.0 hrs/day @ $20.00/hr = $80.00 per day
Transportation $0.00 per day
Total Civil Engineering Cost per day $300.00 per day
PROCUREMENT
Contracting Officer 2.0 hrs/day @ $30.00/hr = $60.00 per day
Contract Administrator 2.0 hrs/day @ $30.00/hr = $60.00 per day
Total Procurement Cost per day $120.00 per day
TOTAL COST PER DAY BEYOND COMPLETION DATE = $ 420.00 per day
PROBABLE ADDITIONAL LOSSES
Loss of living quarters by non-completion
Loss of use of runways/taxiways
$ N/A
$ N/A
Loss of use of building
Loss of revenue from facilities providing services, $ N/A
$ N/A
FIXED COSTS
One time transportation cost – Engineer
One time transportation cost -- Procurement
$ N/A
$ N/A
Preparation of Modification
Staff Judge Advocate Review
$125.00
$175.00
TOTAL FIXED COST $300.00
CHRISTOPHER E. TYMULA, SMSgt, NYANG
Base Contracting Officer
MAGNITUDE OF THE PROJECT
In accordance with Far Part 36.204(a) the magnitude of this project is Less than $25,000.
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Lump Sum POL Cabinets
FFP
POL Cabinets
CE Work Order Number: VBDZ112033
FOB: Destination
NSN: Y173-00-000-0000
PURCHASE REQUEST NUMBER: F9S3S11202A001
SIGNAL CODE: A
NET AMT
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
0001 POP 12-OCT-2011 TO
27-OCT-2011
N/A F9S3S4 - 109 CES RPM-SRM
2LT JAMES VAN WORMER
1 AIR NATIONAL GUARD ROAD
SCOTIA NY 12302-9752
518-344-2480
FOB: Destination
F9S3S4
CLAUSES INCORPORATED BY REFERENCE
52.204-7 Central Contractor Registration APR 2008
52.222-3 Convict Labor JUN 2003
52.222-6 Davis Bacon Act JUL 2005
52.222-7 Withholding of Funds FEB 1988
52.222-8 Payrolls and Basic Records JUN 2010
52.222-9 Apprentices and Trainees JUL 2005
52.222-10 Compliance with Copeland Act Requirements FEB 1988
52.222-11 Subcontracts (Labor Standards) JUL 2005
52.222-12 Contract Termination-Debarment FEB 1988
52.222-13 Compliance with Davis-Bacon and Related Act Regulations. FEB 1988
52.222-14 Disputes Concerning Labor Standards FEB 1988
52.222-15 Certification of Eligibility FEB 1988
52.222-21 Prohibition Of Segregated Facilities FEB 1999
52.222-26 Equal Opportunity MAR 2007
52.222-36 Affirmative Action For Workers With Disabilities OCT 2010
52.232-5 Payments under Fixed-Price Construction Contracts SEP 2002
52.236-13 Accident Prevention NOV 1991
52.236-15 Schedules for Construction Contracts APR 1984
52.236-17 Layout of Work APR 1984
CLAUSES INCORPORATED BY FULL TEXT
52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (JUN 2003)
(a) Definition.
"Small business concern," as used in this clause, means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the size standards in this solicitation.
(b) General. (1) Offers are solicited only from small business concerns. Offers received from concerns that are not small business concerns shall be considered nonresponsive and will be rejected.
(2) Any award resulting from this solicitation will be made to a small business concern.
(c) Agreement. A small business concern submitting an offer in its own name shall furnish, in performing the contract, only end items manufactured or produced by small business concerns in the United States or its outlying areas. If this procurement is processed under simplified acquisition procedures and the total amount of this contract does not exceed $25,000, a small business concern may furnish the product of any domestic firm. This paragraph does not apply to construction or service contracts.
(End of clause)
52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)
At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor.
52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991)
The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor's fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract.
52.236-12 CLEANING UP (APR 1984)
The Contractor shall at all times keep the work area, including storage areas, free from accumulations of waste materials. Before completing the work, the Contractor shall remove from the work and premises any rubbish, tools, scaffolding, equipment, and materials that are not the property of the Government. Upon completing the work, the
Contractor shall leave the work area in a clean, neat, and orderly condition satisfactory to the Contracting Officer.
52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)
If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer's notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for Wednesday 7 September 2011 at 10:00AM. All site visit participants will meet in the Building 25 (Civil Engineering) training room…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .