Attachment I - Revised Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Extend Fire Protection in Building # 2000, Field Camp Algier, USAG Bavaria, Tower Barracks, newest first.
File Type Posted
01-02_-_Cover_Letter_IFB.pdf PDF
03_-_Solicitation.pdf PDF
05_-_Attachment_II_-_Drawing.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page 1 of 83 Pages Seite 1 von 83 Seiten

- 1 -

ATTACHMENT # I

DEPARTMENT OF THE ARMY

UNITED STATES ARMY GARRISON BAVARIA

DIRECTORATE OF PUBLIC WORKS

UNIT 28130

APO AE 09114-8130

Project No. EZ-00784-9P

8 June 2016 Revision I 12 July 2016 New Work Neuarbeit

S P E C I F I C A T I O N

Extend Fire Protection in Building # 2000, Field Camp Algier, USAG Bavaria, Grafenwoehr Military Community - Tower Barracks

L E I S T U N G S B E S C H R E I B U N G

Erweitern der Feuerschutzmaßnahmen in Gebäude # 2000, Field Camp Algier, USAG Bavaria, Grafenwoehr Military Community -

Tower Barracks

Drawing: 1 sheet

Zeichnung: 1 Blatt

In the event of a disagreement between the English text and the courtesy translation of this specification the English text shall govern.

Im Falle einer Unstimmigkeit zwischen dem englischen Text der Leistungsbeschreibung und der Gefälligkeitsübersetzung ist der englische Text maßgebend.

Internal code: 00784_09S.doc, 12 Jul 2016, Froehler, last saved 12 Jul 2016 13:02:00, Michael Froehler

1106070500.civ Typewritten Text

W912PB-16-B-8111

- 2 -

TABLE OF CONTENTS

INHALTSANGABE

SUBJECT PAGE

TITEL SEITE

Cover Sheet Deckblatt 1

Table of Contents Inhaltsangabe 2

General Description Allgemeine Beschreibung 3

General Preamble Allgemeine Vorbemerkungen 4 - 20

Technical Specification Leistungsbeschreibung 21 - 81

Enclosure # 1 Anlage # 1 82

Enclosure # 2 Anlage # 2 83

This project includes the following work:

Dieses Project enthält folgende Arbeiten:

00. Preparation Work Vorbereitungsarbeiten 21 - 23

01. Sprinkler System Sprinkleranlage 24 - 54

02. Structural Work Bauliche Arbeiten 55 - 58

47. Electrical Work Elektroarbeiten 59 - 81

- 3 -

GENERAL DESCRIPTION

This project specifies the following work:

The existing sprinkler system in building # 2000 will be extended to cover all non-protected areas. This mainly concerns offices in prefabricated container buildings.

Extension of the existing electrical system (fire alarm system, emergency exit lights, door control, exterior lighting).

Provide an additional emergency exit door with adjoining walkway.

ALLGEMEINE BESCHREIBUNG

Dieses Projekt umfasst folgende Arbeiten:

Im Gebäude # 2000 wird das bestehende Sprinklersystem auf alle nicht geschützten Bereiche ausgeweitet. Hierbei handelt es sich in erster Linie um Büroräume in Containerfertigbauweise.

Erweitern der Elektroinstallation (Brandmeldeanlage, Notausgangsleuchten, Türüberwachung, Außenbeleuchtung).

Erstellen einer zusätzlichen Notausgangstür mit anschließendem Gehweg.

- 4 -

General Preamble to Project No. EZ-00784-9P Allgemeine Vorbemerkungen zu Projekt Nr. EZ-00784-9P

1. Regulations

The work to be accomplished and material to be furnished shall be in accordance with the following standards and regulations:

a. DIN standards (German Industry Standards) of German Construction Contract Procedures (VOB), Part C, identified below are governing:

DIN 18 299 General Regulations for all kinds of Construction Work DIN 18 301 Boring Work DIN 18 302 Lining of Boreholes DIN 18 303 Sheathing Work DIN 18 304 Piling, Jiggling and Pressing Work DIN 18 305 Dewatering Work DIN 18 308 Drainage Work DIN 18 309 Injection Work DIN 18 314 Gunite Work DIN 18 319 Pipe Pressing Work DIN 18 330 Masonry Work DIN 18 331 Concrete Work DIN 18 334 Carpentry and Constructional Timber Work DIN 18 335 Steel Construction Work DIN 18 336 Sealing Work DIN 18 339 Plumber's Metalwork DIN 18 340 Dry Wall Construction DIN 18 345 Thermal Insulation Composite Systems DIN 18 350 Plaster and Stucco Work DIN 18 355 Joinery Work DIN 18 357 Metal Fitting Work DIN 18 360 Metal Construction Work DIN 18 363 Painting and Enameling Work, Surface Coatings DIN 18 364 Corrosion Protection on Steel Constructions DIN 18 381 Gas, Water and Sewer Systems within Buildings DIN 18 382 Low and Medium Voltage Systems with Nominal Voltage up to 36 kV DIN 18 386 Building Automation DIN 18 421 Thermal Insulation at Technical Systems DIN 18 451 Scaffolding Work DIN 18 459 Demolition and Deconstruction

b. Other regulations:

VDE Regulation No. 0100 Erection of power installations, with rated voltages up to 1000 V

EN ISO 16484 Building Automation and Control System (BACS)

Pertinent accident prevention regulations of the employer's liability insurance association.

- 5 -

1. Vorschriften

Die auszuführenden Arbeiten und zu liefernden Materialien müssen den folgenden Bestimmungen und Vorschriften entsprechen:

a. DIN Bestimmungen der VOB, Teil C, wie nachfolgend aufgeführt, sind gültig:

DIN 18 299 Allgemeine Regelungen für Bauarbeiten jeder Art DIN 18 301 Bohrarbeiten DIN 18 302 Arbeiten zum Ausbau von Bohrungen DIN 18 303 Verbauarbeiten DIN 18 304 Ramm-, Rüttel- und Pressarbeiten DIN 18 305 Wasserhaltungsarbeiten DIN 18 308 Dränarbeiten DIN 18 309 Einpressarbeiten DIN 18 314 Spritzbetonarbeiten DIN 18 319 Rohrvortriebsarbeiten DIN 18 330 Mauerarbeiten DIN 18 331 Betonarbeiten DIN 18 334 Zimmer- und Holzbauarbeiten DIN 18 335 Stahlbauarbeiten DIN 18 336 Abdichtungsarbeiten DIN 18 339 Klempnerarbeiten DIN 18 340 Trockenbauarbeiten DIN 18 345 Wärmedämm-Verbundsysteme DIN 18 350 Putz- und Stuckarbeiten DIN 18 355 Tischlerarbeiten DIN 18 357 Beschlagarbeiten DIN 18 360 Metallbauarbeiten DIN 18 363 Maler- und Lackierarbeiten - Beschichtungen DIN 18 364 Korrosionsschutz an Stahlbauten DIN 18 381 Gas-, Wasser- und Entwässerungsanlagen innerhalb von Gebäuden DIN 18 382 Nieder- und Mittelspannungsanlagen mit Nennspannungen bis 36 kV DIN 18 386 Gebäudeautomation DIN 18 421 Dämmarbeiten an Technischen Anlagen DIN 18 451 Gerüstarbeiten DIN 18 459 Abbruch- und Rückbauarbeiten

b. Sonstige Bestimmungen:

VDE Bestimmung Nr. 0100 Bestimmungen für das Errichten von Starkstromanlagen mit Nennspannungen bis 1000 V

EN ISO 16484 Systeme der Gebäudeautomation (GA)

Einschlägige Unfallverhütungvorschriften der Berufsgenossenschaft

- 6 -

2. Drawings

The work to be performed will include but is not limited to the items specified in the drawings. The drawing(s) is/are a part of this specification:

Number of sheets: 1

Date of drawing: 8 June 2016

2. Zeichnungen

Die auszuführenden Arbeiten beinhalten unter anderem die in den Zeichnungen angegebenen Objekte. Die Zeichnung(en) ist/sind Bestandteil dieser Leistungsbeschreibung:

Anzahl der Blätter: 1

Zeichnungsdatum: 8. Juni 2016

3. Disposal of Debris

a. The Sanitary Landfill Grafenwöhr will not accept demolition material, such as asphalt, concrete, wood, construction debris, metal, branches, rootstocks, cardboard, special waste (cleaning agents, paints etc), dismantled material (cables, pipes, installation material etc.) or soil excavation. This material becomes property of the contractor and shall be disposed of in accordance with German laws and regulations (Closed Cycle and Waste Management Act, Ordinance of Waste Wood Management, Guideline 3.4/1 of the Bavarian Water Board for tar debris, etc.). If applicable, the contractor must commission a certified laboratory to analyze representative samples for classification. Sampling and chemical analysis of the excavated soil shall be executed according to LAGA PN 98 (German Interstate Working Party on Waste Processing - Ordinance for the procedure for physical, chemical and biological analyses in connection with recycling/removal of waste).

b. Waste wood resulting from demolition work shall be disassembled individually and stored separate from other debris. The disposal shall be in compliance with the German Ordinance on the Management of Waste wood ("Altholzverordnung"). Waste wood shall be categorized and disposed of based on the Ordinance on the Management of Waste wood.

c. The dismantled material shall be stored in water-tight covered containers until removal and shall be disposed of at least once a week.

d. Within USAG Bavaria, Grafenwoehr Military Community there is a separate sewer system for rain water and waste water. Therefore, accumulated waste water shall be disposed of via waste water duct in coordination with the COR.

- 7 -

3. Bauschuttabfuhr

a. Abbruchmaterial, wie Teeraufbruch, Beton, Holz, Bauschutt, Metall, Äste, Wurzelstöcke, Kartonagen, Sondermüll (Reiniger, Farben, etc.), ausgebaute Materialien (Kabel, Rohre, Installationsmaterialien, etc.) oder Erdaushub werden nicht an der Mülldeponie im Lager Grafenwöhr angenommen. Diese Materialien werden Eigentum des Auftragnehmers und sind gemäß deutschen Gesetzen und Vorschriften (Kreislaufwirtschaftsgesetz, Altholzverordnung, Merkblatt 3.4/1 des Bayerischen Landesamt für Wasserwirtschaft für Teeraufbruch, etc.) zu entsorgen. Gegebenenfalls muß der Auftragnehmer ein zertifiziertes Labor beauftragen, repräsentative Proben zu untersuchen und entsprechend einzustufen. Die Probenahme und Analytik des Bodenaushubs muß nach der Richtlinie LAGA PN 98 (Länderarbeitsgemeinschaft Abfall - Richtlinie für das Vorgehen bei physikalischen, chemischen und biologischen Untersuchungen im Zusammenhang mit der Verwertung/Beseitigung von Abfällen) erfolgen.

b. Fallen im Zuge der Abbrucharbeiten Holzabfälle an, sind diese separat zurück zu bauen und von den übrigen Abfällen getrennt zur Entsorgung bereit zu stellen.

Die Entsorgung ist in der Altholzverordnung geregelt. Der anfallende Holzabfall ist gemäß den Kategorien der Altholzverordung einzuteilen und zu entsorgen.

c. Bauabfälle sind bis zur Abfuhr in wasserdicht abgedeckten Containern zu lagern und mindestens einmal pro Woche abzufahren.

d. Im Bereich der USAG Bavaria, Grafenwoehr Military Community besteht ein Trennsystem für Regenwasser und Schmutzwasser. Anfallendes Schmutzwasser muß deshalb nach Angabe des COR über den Schmutzwasserkanal entsorgt werden.

4. Job Site Equipment and Storage

The contractor shall be responsible for the safe storage of materials and equipment. Upon approval from the COR and at their own risk the contractor may be authorized to erect containers for personnel and construction equipment/materials according to current German workplace ordinance. These containers must be a minimum of 25 meters away from any building occupied by 10 or more personnel.

Construction materials and other equipment shall not be stored in U.S. buildings.

Upon completion of work the contractor shall clean up the storage area and return it to its original condition.

4. Baustelleneinrichtung und Materiallagerung

Der Auftragnehmer ist für eine sichere Lagerung der Materialien und Geräte selbst verantwortlich. Er darf mit Genehmigung des COR und auf eigene Gefahr Container für Personal und Baugeräte/Material gemäß der Arbeitstättenverordnung aufstellen.

Diese Container müssen mindestens 25 m von allen Gebäuden entfernt sein, in denen sich 10 oder mehr Personen aufhalten. Baumaterial und sonstige Gegenstände dürfen nicht in U.S. Gebäuden gelagert werden. Nach Beendigung der Arbeiten ist der Lagerplatz zu reinigen und wieder in den ursprünglichen Zustand zu versetzen.

- 8 -

5. Material to be Turned-In

a. Dismantled material becomes contractor’s property and shall be disposed of according to German laws and regulations, unless otherwise indicated in the individual items of the specification.

b. Dismantled material indicated for turn-in by this specification shall be turned-in to the Warehouse Grafenwöhr, Building # 319 (distance from job site 3 km). Operating hours of the Warehouse Grafenwöhr: Monday, Tuesday, Thursday and Friday from 0800 - 1130 hours and from 1300 - 1500 hours, Wednesday from 0800 - 1130 hours. The material to be turned-in must be unloaded and stacked safely.

5. Einzulieferndes Material

a. Ausgebaute Materialien werden Eigentum des Auftragnehmers und sind nach deutschen Gesetzen und Vorschriften zu entsorgen, sofern in den einzelnen Positionen des Leistungsverzeichnisses nichts gegenteiliges gefordert wird.

b. Ausgebaute Materialien, die laut Leistungsbeschreibung abzuliefern sind, müssen in das Warenhaus Grafenwöhr, Gebäude # 319 eingeliefert werden (Entfernung von der Baustelle 3 km). Öffnungszeiten im Warenhaus Grafenwöhr: Montag, Dienstag, Donnerstag und Freitag von 08.00 - 11.30 Uhr und von 13.00 - 15.00 Uhr, Mittwoch von 08.00 - 11.30 Uhr. Das einzuliefernde Material ist abzuladen und sicher aufzustapeln.

6. Connection conditions for Medium Voltage and Low Voltage Network

a. The network provider (US Army Bavaria, Grafenwoehr Military Community - Tower Barracks) takes as a basis the "technical connection conditions" ("Technische Anschlussbedingungen" [TAB] of the Bayernwerk AG, valid as amended. The technical connection conditions (TAB) are valid for work on systems within the low voltage and medium voltage network of the network provider and shall be applied for all systems which are going to be newly connected and for network modifications, respectively. These mainly include modification, extension, deconstruction or dismantling of an electrical system as well as the change of the connected load, the protection concept etc.

b. The system following the network connection up to the disconnecting device for the commissioning of the main or distribution fuses, defined by VDE-AR-N 4101, paragraph 4.5, section 2, shall be commissioned only by the network provider or – with their approval- by an installation company specified in an electrical installation register. The system following this disconnecting device shall be commissioned only by an installation company specified in an electrical installation register.

c. The system shall only be erected, extended, modified and maintained according to the generally approved technical rules. All work shall be performed by an installation company listed in an electrical installation register of a network provider. Only material and devices produced according to §49 of the Energy Industry Act, considering the generally approved technical rules, shall be used.

- 9 -

d. The network provider (US Army Bavaria) does not keep its own installation register. However, it accepts the proof from installation companies that they are listed in the electrical installation register of other network providers, subject to verification. The contractor shall submit to the COR this proof prior to start of work.

e. When working on the medium voltage network, the contractor must submit to the COR proof of switching authorization within voltage networks up to 20 kV (appropriate training certificate). When working on the battery systems, the contractor shall submit to the COR proof for working on live systems (battery system domain)(appropriate training certificate).

f. Required switch-off times shall be kept to a minimum and announced in writing and coordinated with the COR at least five working days in advance.

g. In the event of contradictions between this paragraph and the specification, the specification shall govern.

6. Anschaltbedingungen für das Mittel- und Niederspannungsnetz

a. Der Netzbetreiber (US Army Bavaria, Grafenwoehr Military Community - Tower Barracks) legt die "Technischen Anschlussbedingungen" (TAB) der Bayernwerk AG in ihrer jeweils gültigen Fassung zugrunde. Die TAB gelten für Arbeiten an Anlagen im Niederspannungs- und Mittelspannungsnetz des Netzbetreibers und sind für alle Anlagen anzuwenden, die neu an das Verteilungsnetz angeschlossen werden bzw. für Netzanschlussänderungen. Diese umfassen im wesentlichen Umbau, Erweiterung, Rückbau oder Demontage einer elektrischen Anlage sowie die Änderung der Anschlussleistung, des Schutzkonzeptes usw.

b. Die Anlage hinter dem Netzanschluss bis zu der in der VDE-AR-N 4101 in Abschnitt 4.5, Abs. 2 definierten Trennvorrichtung für die Inbetriebnahme der Haupt- oder Verteilungssicherungen darf nur durch den Netzbetreiber oder mit seiner Zustimmung durch ein in ein Installateurverzeichnis eingetragenes Installationsunternehmen in Betrieb genommen werden. Die Anlage hinter dieser Trennvorrichtung darf nur durch ein in ein Installateurverzeichnis eingetragenes Installationsunternehmen in Betrieb genommen werden.

c. Die Anlage darf nur nach den allgemein anerkannten Regeln der Technik errichtet, erweitert, geändert und instand gehalten werden. Alle Arbeiten müssen durch ein in ein Installateurverzeichnis eines Netzbetreibers eingetragenes Installationsunternehmen durchgeführt werden. Es dürfen nur Materialien und Geräte verwendet werden, die entsprechend §49 des Energiewirtschaftsgesetzes unter Beachtung der allgemein anerkannten Regeln der Technik hergestellt sind.

d. Der Netzbetreiber führt kein eigenes Installateurverzeichnis. Er erkennt jedoch die Ausweise von Installationsunternehmen, dass sie im Installateurverzeichnis anderer Netzbetreiber eingetragen sind, vorbehaltlich einer Nachprüfung, an. Dieser Nachweis ist vor Beginn der Arbeiten dem COR vorzulegen.

e. Für Arbeiten am Mittelspannungsnetz ist zusätzlich der Nachweis der Schaltberechtigung in Spannungsnetzen bis 20 kV vorzulegen (entsprechende Schulungsbescheinigung). Bei Arbeiten an Batterieanlagen ist zusätzlich der Nachweis für Arbeiten unter Spannung (Bereich Batterieanlagen) vorzulegen (entsprechende Schulungsbescheinigung).

- 10 -

f. Notwendige Abschaltungen sind auf ein Minimum zu begrenzen und mindestens fünf Arbeitstage vorher schriftlich beim COR anzumelden und mit diesem zu koordinieren.

g. Bei Widersprüchen zwischen diesem Paragraphen und dem Leistungsverzeichnis, gilt das Leistungsverzeichnis.

7. Water and Electrical Power Supply

a. Water and electrical power required for the execution of this project will be made available to the contractor without charge in accordance with FAR clause 52.236-14 "AVAILABILITY AND USE OF UTILITY SERVICES". Necessary connections to lines shall be made and a meter shall be provided by the contractor without additional cost to the U.S. Government.

b. The connection of worksite distribution boards is authorized only in the presence of personnel from the Electrical Shop, Utilities Branch, DPW.

Arbitrary opening of cable distributions or low-voltage switchgears is not authorized. The necessary coordination shall be made prior to the connection with the COR in writing.

c. Electrical systems at job sites must be checked regularly (specifically after relocation) according to BGV A3 (regulation of the employer's liability insurance association) by a skilled electrical employee. Contractor shall keep measurement reports and test certificates in the construction office and shall present those records upon request by the Government. Electrical connections or temporary installations shall be in accordance with all VDE regulations.

d. Use of electrical heaters on job site is prohibited. If heating is necessary, other heating sources shall be used instead and shall be coordinated with the COR prior to use in writing.

e. Provision of construction water or water required for other temporary purposes shall be coordinated in advance with the COR in writing. DIN EN 1717 defines the requirements concerning the protection of drinking water within drinking water systems as well as the general requirements for safety arrangements to prevent pollution of drinking water caused by backflow. DIN EN 1717 shall be strictly followed.

f. The contractor shall use stand pipe meters or hydrant meters to monitor temporary water usage from hydrants. This equipment must be approved by the "Deutsche Vereinigung des Gas- und Wasserfachs" DVGW.

Ending of the temporary water usage shall be immediately reported to the the COR in writing.

7. Wasser- und Baustromversorgung

a. Wasser und Baustrom, die für die Ausführung dieses Projekts nötig sind, werden dem Auftragnehmer gemäß FAR Klausel 52.236-14 "VERFÜGBARKEIT UND BENUTZUNG VON VERSORGUNGSLEISTUNGEN" kostenlos zur Verfügung gestellt. Der Auftragnehmer muss notwendige Anschlüsse an Leitungen vornehmen und einen Zwischenzähler bereitstellen, ohne dass der U.S. Regierung zusätzliche Kosten entstehen.

- 11 -

b. Das Anschließen von Baustellenverteilern darf nur im Beisein von Mitarbeitern des DPW, Utilities Branch, Elektroshop erfolgen. Eigenmächtiges Öffnen von Kabelverteilern oder Niederspannungsschaltanlagen ist nicht erlaubt. Die notwendige Koordination erfolgt schriftlich über den COR vor dem Anschließen.

c. Baustromanlagen sind einer regelmäßigen Prüfung nach BGV A3 (Berufsgenossenschaftliche Vorschrift) durch eine Elektrofachkraft zu unterziehen (insbesondere nach Umsetzen). Die Mess- und Prüfprotokolle sind im Baubüro zu hinterlegen und auf Verlangen des Auftraggebers vorzuzeigen. Elektrische Anschlüsse oder vorläufige Einrichtungen müssen den VDE Vorschriften entsprechen.

d. Die Verwendung von Elektroheizungen auf Baustellen ist nicht erlaubt. Wenn eine Heizung erforderlich ist, müssen andere Brennstoffe verwendet werden. Dies ist mit dem COR vor der Verwendung schriftlich zu koordinieren.

e. Der Bezug von Bauwasser oder Wasser für sonstige vorübergehende Zwecke ist schriftlich mit dem COR zu koordinieren. Die DIN EN 1717 definiert die Anforderung zum Schutz des Trinkwassers vor Verunreinigungen in Trinkwasserinstallationen und die allgemeinen Anforderungen an Sicherheitseinrichtungen zur Verhütung von Trinkwasserverunreinigungen durch Rückfließen. Die DIN EN 1717 ist dringendst einzuhalten.

f. Für die vorübergehende Wasserentnahme aus Hydranten sind Standrohrzähler oder Hydrantenzähler vom Auftragnehmer zu verwenden. Diese Einrichtungen müssen von der Deutschen Vereinigung des Gas- und Wasserfachs DVGW geprüft sein.

Die Beendigung der vorübergehenden Wasserentnahme ist dem COR umgehend schriftlich zu melden.

8. Welding and Cutting Work

Contractors who are responsible for welding and cutting work shall coordinate with the COR in writing in order to attend the mandatory safety briefing at the local Fire Station prior to start of work. After the briefing, a Hot Work Permit (DA Form 5383) will be issued to the welders.

8. Schweiss- und Schneidarbeiten

Auftragnehmer, die für Schweiss- und Schneidarbeiten zuständig sind, werden vom COR angewiesen, einer Sicherheitsbesprechung bei der örtlichen U. S. Feuerwehr beizuwohnen. Nach der Besprechung wird ein Erlaubnisschein für Schweissarbeiten (Hot Work Permit, DA Form 5383) an die Schweisser ausgegeben.

9. As-built Drawings

a. For the scope of work described in the specification, as-built drawings shall be delivered in the format of CAD Software Microstation, version 8 (DGN-file).

- 12 -

b. The COR will provide the contractor with existing U.S. Government drawing documents on compact disk in the above referenced format. The contractor shall provide the data media required for this purpose. The assignment of the individual drawing levels shall be coordinated with the COR. The as-built drawings shall be provided on compact disk in both the German and English languages.

9. Bestandspläne

a. Für den im Leistungsverzeichnis beschriebenen Leistungsumfang sind Bestandspläne im Format der CAD-Software Microstation, Version 8 (DGN-Datei), zu liefern.

b. Der COR stellt dem Auftragnehmer die vorhandenen Planunterlagen der U.S.

Regierung auf CD’s im oben aufgeführten Format zur Verfügung. Die hierfür erforderlichen Datenträger sind vom Auftragnehmer zu stellen. Die Belegung der einzelnen Zeichnungsebenen ist mit dem COR abzustimmen. Die Bestandspläne sind in deutscher und englischer Sprache auf CD’s zu liefern.

10. Preliminary Remarks for Fire Alarm System

a. The firm responsible for installation and commissioning of the fire alarm system shall be certified for installation and commissioning of Esser fire alarm systems according to DIN 14675 and for a quality management system according to ISO 9001. Furthermore, it must have VDS authorization for Esser fire alarm systems.

These certifications shall be submitted to the COR prior to start of installation work.

b. The firm shall review the project specifications. If any changes are necessary for the installation of the fire alarm system according to regulations, the COR shall be informed in writing before start of installation work.

10. Vorbemerkungen für Brandmeldeanlage

a. Die für die Montage und Inbetriebnahme der Brandmeldeanlage verantwortliche Firma muss gemäß DIN 14675 für die Montage und Inbetriebnahme von Esser Brandmeldeanlagen und nach ISO 9001 für ein Qualitäts-Managementsystem zertifiziert sein. Ausserdem muss sie eine VDS-Zulassung für Esser Brandmeldeanlagen besitzen.

Die entsprechenden Dokumente sind dem COR vor Beginn der Installationsarbeiten vorzulegen.

b. Die Firma hat die Projektunterlagen zu überprüfen. Sollten für eine vorschriftsmäßige Installation der Brandmeldeanlage irgendwelche Änderungen erforderlich sein, so ist dies dem COR vor Beginn der Installationsarbeiten schriftlich mitzuteilen.

- 13 -

11. Additional work required for the connection of the central fire alarm system to the electronic intelligent display terminal Gebanis located at the local Fire Department

a. Prior to start of work the contractor shall submit to the COR proof of the manufacturer certification for Gebanis multi-user systems, version 4 or 5 (manufacturer B&M Informatik AG) for the responsible expert firm executing this action.

b. Prior to start of work and immediately after completion of the work the data file of the Gebanis system will be saved on a DVD by the U.S. Government in cooperation with the contractor. The contractor shall provide the required blank DVDs. Visualization (entering of data) must be performed continuously without interruption, because always only one contractor can perform work on the system, which is to be considered when scheduling. In case system errors should occur after the connection (instable ring etc.), the contractor has one week for debugging. If it is not possible to fix the error, the original condition will be restored by the U.S. Government. In that case, the contractor will have another week for a proper execution of the work. If the problem cannot be solved within this time frame, the work will be awarded to another firm by the U.S. Government.

Arising costs shall be paid by the contractor.

c. All work on the Gebanis system as well as interventions into the existing Essernet-system, such as the opening of an Essernet-ring, shall only be performed upon coordination with the Electric Shop at DPW. The contractor shall coordinate this through the COR at least three working days in advance in writing. As a general rule, work on the Gebanis System shall only be performed during normal workdays from 0800 to 1145 hours and from 1300 to 1530 hours.

d. Special attention shall be paid to the fact that only virus-free data files, software and computers shall be used. Prior to the start of work the contractor shall provide the COR with a certificate in order to prove that all computers used at the job site are protected by up-to-date virus scanning software with automatic data test function. Spot checks may be performed at any time in order to assure a proper protection.

11. Zusatzarbeiten für die Aufschaltung der Brandmeldezentrale auf die elektronische Einsatzdatei Gebanis bei der Feuerwehr

a. Vor Beginn der Arbeiten muß der Auftragnehmer dem COR nachweisen, daß die verantwortliche Fachfirma, welche die Aufschaltung ausführt, von der Herstellerfirma (B&M Informatik AG) für Gebanis Mehrplatzsysteme, Version 4 oder 5, zertifiziert ist.

b. Vor Beginn und unmittelbar nach der Arbeit wird von der U.S. Regierung der Datenbestand des Gebanis-Systems auf einer DVD in Zusammenarbeit mit dem Auftragnehmer gesichert. Die erforderlichen Rohlinge sind vom Auftragnehmer zu stellen. Die Visualisierung (Eingabe von Daten) ist in einem Stück durchzuführen, denn es kann immer nur eine Firma am System arbeiten, was bei der Zeitplanung berücksichtigt werden muss.

- 14 -

Sollten nach dem Aufschalten Systemfehler (instabiler Ring etc.) auftreten, so erhält der Auftragnehmer eine Woche Zeit, um diese zu beheben. Kann er dies nicht, so wird von der U.S. Regierung der Ursprungszustand des Systems wieder hergestellt.

In diesem Fall erhält der Auftragnehmer eine weitere Woche Zeit, die Arbeiten korrekt auszuführen. Sollte ihm dies wieder nicht möglich sein, so wird die U.S.

Regierung die Arbeiten durch eine andere Firma ausführen lassen. Hierfür anfallende Kosten sind vom Auftragnehmer zu tragen.

c. Sämtliche Arbeiten an der Gebanis Zentrale, sowie Eingriffe in das bestehende Essernet-System, wie z. B. das Auftrennen eines Essernet-Ringes, dürfen nur in Absprache mit dem DPW Elektro-Shop erfolgen. Der Auftragnehmer muß dies schriftlich mit dem COR mindestens drei Arbeitstage vorher koordinieren. Arbeiten am Gebanis System dürfen in der Regel nur an den normalen Arbeitstagen in der Zeit von 08.00 bis 11.45 Uhr und 13.00 bis 15.30 Uhr durchgeführt werden.

d. Es ist strengstens darauf zu achten, nur virenfreie Dateien, Software und Rechner zu verwenden. Vor Beginn der Arbeiten ist dem COR zu bescheinigen, dass alle vom Auftragnehmer auf der Baustelle eingesetzten Rechner durch einen aktuellen Virenscanner mit automatischer Dateiprüffunktion geschützt sind. Stichproben zur Überprüfung dieser Anforderung können jederzeit durchgeführt werden.

d. Es ist strengstens darauf zu achten, nur virenfreie Dateien, Software und Rechner zu verwenden. Vor Beginn der Arbeiten ist dem COR zu bescheinigen, dass alle vom Auftragnehmer auf der Baustelle eingesetzten Rechner durch einen aktuellen Virenscanner mit automatischer Dateiprüffunktion geschützt sind. Stichproben zur Überprüfung dieser Anforderung können jederzeit durchgeführt werden.

12. Spill reporting procedures for contractors working within the Training Area/Tower Barracks and Rose Barracks

a. Applicability: In accordance with USAG Bavaria’s Environmental Management System (EMS) the following procedures shall be followed in the event of a spill of hazardous substances caused by vehicles or equipment of contractors working within the Training Area/Tower Barracks or Rose Barracks

b. Hazards for humans and environment:

- Release of hazardous substances during accidents (mainly Petroleum, Oil and

Lubricant (POL)products);

- Release of hazardous substances caused by equipment failure (mainly POL products)

- Release of hazardous substances during transportation of hazardous materials/waste (excluding Class 1, explosives).

c. Protective Measures and Procedures: The following requirements must be met when operating a vehicle within the Training Area/Tower Barracks or Rose Barracks.

- Valid driving license appropriate for the vehicle;

- Valid hazardous cargo driver’s license for the transportation of hazardous material/hazardous waste;

- Follow the Road Traffic Regulation:

- Road Traffic Law (Straßenverkehrsgesetz - StVG);

- Road Traffic Regulation (Straßenverkehrsordnung - StVO)Federal Motor Vehicle

Safety Standards (Straßenverkehrs-Zulassungs-Ordnung - StVZO);

- 15 -

- European Agreement concerning the international carriage of dangerous goods by road (Accord europeen relatif au transport international des marchandises Dangereuses par Route - ADR);

- Load safety according to VDI 2700 and ADR

- Spill equipment shall be kept on hand (e.g. absorbent, absorbent pads etc.).

d. The following procedures shall be followed should hazardous situations arise:

- Immediately notify the COR and the local US Fire Department under the following number: 09641 – 83 8303 if hazardous substances (diesel, hydraulic fluid etc.), including hazardous waste, are released due to failure of vehicles or construction equipment;

- The contractor shall take immediate protective measures to prevent spilled material from spreading;

- The necessary spill clean-up will be performed by the contractor or their subcontractors.

e. Emergency Procedures – First Aid:

- Secure scene of the accident;

- Inform the COR and the local U.S. Fire Department at 09641-83-8303 (emergency number: 09641-83-112);

- Provide first aid to injured individuals

f. Refueling, Maintenance, Disposal:

- To avoid impacting the environment, appropriate precautionary measures shall be taken during refueling of construction vehicles / equipment;

- Maintenance of vehicles and equipment shall only be conducted on paved surfaces connected to an oil/water separator (such as maintenance hardstands/refueling pads);

- The contractor is responsible for the disposal of hazardous substances and contaminated soil caused by accidents or failure of vehicles/equipment. Proof of proper disposal shall be provided to the COR (Entsorgungsnachweis).

12. Verhaltensregeln für Auftragnehmer bei Freisetzung von Gefahrstoffen auf dem Truppenübungsplatz/Tower Barracks (Grafenwöhr) bzw. Rose Barracks (Vilseck)

a. Geltungsbereich: Gemäß dem Umweltmanagementsystem (Environmental Management System – EMS) von USAG Bavaria, wird im Folgenden das Verhalten bei Freisetzung von Gefahrstoffen während des Betriebs von Baufahrzeugen von auf dem Truppenübungsplatz/Tower Barracks bzw. in der Rose Barracks tätigen Auftragnehmern beschrieben.

b. Gefahren für Mensch und Umwelt:

- Freisetzen von Gefahrstoffen bei Unfällen(in der Regel Mineralöle).

- Freisetzen von Gefahrstoffen durch defekte Maschinen (in der Regel Mineralöle).

- Freisetzen von Gefahrstoffen bei Gefahrstofftransporten/Sondermülltransporten

(ausgenommen Klasse 1, Sprengstoffe)

- 16 -

c. Schutzmaßnahmen und Verhaltensregeln: Voraussetzung für das Führen eines Fahrzeuges auf dem Truppenübungsplatz/Tower Barracks bzw. in der Rose Barracks:

- Gültige Fahrerlaubnis für das entsprechende Fahrzeug.

- Gültiger Gefahrgutführerschein beim Transport von Gefahrgut/Sondermüll.

- Einhalten der Vorschriften des Straßenverkehrsrechts:

- Straßenverkehrsgesetz (StVG)

- Straßenverkehrsverordnung (StVO)

- Straßenverkehrs-Zulassungs-Ordnung (StVZO)

- Europäisches Abkommen zum internationalen Transport von Gefahrgütern auf

Straßen (Accord europeen relatif au transport international des marchandises Dangereuses par Route - ADR).

- Ladungssicherung entsprechend VDI 2700 und ADR

- Ausrüstung zur Bekämpfung von Ölunfällen ist für den Notfall bereitzuhalten

(z.B. Bindemittel, Ölbindematten etc.).

d. Verhalten bei Störungen und im Gefahrfall:

- Bei Freisetzen von Gefahrstoffen (auch Sondermüll) oder Betriebsmitteln

(Hydrauliköl, Diesel usw.) durch Defekte an Fahrzeugen bzw. Baumaschinen sind sofort der COR und die Standortfeuerwehr unter der Telefonnummer 09641-83-8303 zu verständigen.

- Der Auftragnehmer hat dafür zu sorgen, dass geeignete Sofortmaßnahmen getroffen werden um ein Ausbreiten zu verhindern.

- Die anfallenden Reinigungsarbeiten sind vom Auftragnehmer bzw. Subunternehmer durchzuführen.

e. Verhalten bei Unfällen - Erste Hilfe:

- Unfallstelle sichern.

- COR und Standortfeuerwehr unter 09641-83-8303 (Notruf: 09641-83-112) verständigen.

- Verletzte versorgen.

f. Betanken, Instandhaltung, Entsorgung:

- Beim Betanken von Baustellenfahrzeugen / Baumaschinen sind geeignete

Vorsichtsmaßnahmen zu treffen, um Umweltschäden zu vermeiden.

- Instandhaltungsarbeiten an Fahrzeugen und Baumaschinen sind grundsätzlich nur auf befestigtem Untergrund mit Anschluss an einen Ölabscheider durchzuführen (z.B. Wartungs- und Betankungsflächen).

Die Entsorgung von ausgelaufenen Substanzen oder von verunreinigtem Boden als Folge von Unfällen oder durch defekte Fahrzeuge/Baumaschinen ist vom Auftragnehmer selbst durchzuführen. Dem COR ist ein Entsorgungsnachweis vorzulegen.

13. Time extensions for unusually severe weather

a. The following specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the contract clause FAR 52.249-10, DEFAULT (FIXED PRICE CONSTRUCTION). In order for the Contracting Officer to award a time extension under this clause, the following conditions must be met:

- 17 -

(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the contractor.

b. The following schedule of monthly anticipated adverse weather delays for the project location will constitute the base line for monthly weather time evaluations. The contractor’s performance schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

Monthly Anticipated Adverse Weather Calendar Days

| JAN | FEB | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV | DEC |

| 4 | 3 | 2 | 1 | 1 | 1 | 1 | 1 | 1 | 2 | 2 | 3 |

c. Upon acknowledgement of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor shall record on its inspection records, the occurrence of adverse weather and resultant impact to normally scheduled work.

Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the contractor’s scheduled work day.

d. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph b above, the contracting officer will approve the exceeding calendar days and issue a modification for time in accordance with contract clause FAR 52.249-10.

13. Zeitverlängerungen im Falle extrem schlechten Wetters

a. Im Folgenden wird der Verfahrensablauf zur Gewährung von Zeitverlängerungen bei extrem schlechtem Wetter gemäß der Vertragsklausel FAR 52.249-10, NICHTEINHALTUNG (FESTPREISBAUVERTRAG) beschrieben. Damit der Vertragsoffizier eine Zeitverlängerung im Rahmen dieser Klausel gewähren kann, müssen folgende Bedingungen erfüllt sein:

(1) Die Wetterbedingungen auf der Baustelle müssen sich während der Vertragslaufzeit als extrem schlecht erweisen, das heißt, schlechter als man für den jeweiligen Monat am Ausführungsort erwarten würde.

(2) Das extrem schlechte Wetter muß tatsächlich der Grund für eine

Verzögerung der Fertigstellung der Baumaßnahme sein. Grund für eine Verzögerung ist höhere Gewalt ohne Verschulden oder Fahrlaessigkeit seitens des Auftragnehmers.

b. Die nachfolgende Aufstellung der monatlich zu erwartenden Verzoegerungen bedingt durch schlechtes Wetter gilt als Basis fuer die monatliche Zeitauswertung.

Die zu erwartenden Verzoegerungen aufgrund schlechten Wetters muessen im Bauzeitenplan des Auftragnehmers ersichtlich sein.

- 18 -

Monatlich zu erwartende Schlechtwettertage

| JAN | FEB | MÄR | APR | MAI | JUN | JUL | AUG | SEP | OKT | NOV | DEZ |

| 4 | 3 | 2 | 1 | 1 | 1 | 1 | 1 | 1 | 2 | 2 | 3 |

c. Nach Zurkenntnisnahme der "Notice to Proceed" (Anweisung zum Beginn der Arbeiten) und waehrend der gesamten Vertragslaufzeit muss der Auftragnehmer die Schlechtwettertage und die daraus resultierenden Auswirkungen auf die geplanten Arbeiten dokumentieren. Tatsaechliche Schlechtwettertage sind vom Auftragnehmer geplante Arbeitstage, an denen entscheidende Taetigkeiten fuer mindestens einen halben Arbeitstag (50%) oder laenger behindert werden.

d. Die Anzahl der tatsaechlichen Verzoegerungstage bedingt durch Schlechtwetter beinhaltet auch die Tage, die durch wirklich schlechtes Wetter verursacht wurden, (selbst wenn das schlechte Wetter im vorangegangenen Monat aufgetreten ist). Diese sollen in zeitlicher Abfolge, vom ersten bis zum letzten Tag eines jeden Monats, als volle Tage abgerechnet werden. Sollte die Anzahl der tatsaechlichen Verzoegerungen bedingt durch Schlechtwetter die Anzahl der zu erwartenden Tage (siehe Paragraph b, oben ) ueberschreiten, wird der Vertragsoffizier die zusaetzlichen Kalendertage genehmigen und eine Vertragsverlaengerung in Übereinstimmung mit der Vertragsklausel FAR 52.249-10 ausstellen.

14. Security Checks

The contractor must consider delays caused by checks when entering and leaving the construction sites on US installations, as this will not be separately reimbursed.

14. Sicherheitskontrollen

Verzögerungen bedingt durch Zugangskontrollen beim Betreten und Verlassen der Baustellen innerhalb von Liegenschaften der US-Armee sind vom Auftragnehmer zu berücksichtigen, da diese nicht extra bezahlt werden..

15. Anti-Terrorism/Operations Security (AT/OPSEC) Requirements

Contractors and sub-contractors shall comply with the following AT/OPSEC requirements:

a. Access and General Protection/Security Policy and Procedures. The contractor and all associated subcontractor employees will comply with applicable installation, facility, and area commander installation/facility access and local security policy and procedures (provided by Government representative). The contractor will also provide all information required for background checks to meet installation-access requirements to be accomplished by the installation provost marshal office, director of emergency services, or security office. The contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA, and local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the force protection condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

- 19 -

b. iWATCH/iSALUTE Training. The contractor and all associated subcontractors will brief all employees on the local iWATCH/iSALUTE program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training will be completed within 30 calendar days after the contract is awarded and within 5 calendar days after new employees commence contract performance, with the results reported to the COR within 30 calendar days after the contract is awarded.

15. Vorschriften zur Sicherheit und Anti-Terrormassnahmen (AT/OPSEC)

Auftragnehmer und Sub-Unternehmer sollen die folgenden AT/OPSEC Vorschriften erfüllen:

a. Vorschriften und Regelungen für den Zutritt zum Gelände und allgemeine Schutzmassnahmen. Der Auftragnehmer und alle Subunternehmer müssen die gültigen Vorschriften und Anweisungen für den Zutritt zum Gelände und allgemeine Sicherheitsregeln befolgen (werden von einem Vertreter der US Armee ausgehändigt).

Der Auftragnehmer muß alle Unterlagen zur Durchführung einer Sicherheitsüberprüfung vorlegen, damit die Zutrittsvoraussetzungen der örtlichen Militärpolizei, der Abteilung für Katastrophenschutz sowie des Büros für Sicherheit erfüllt werden.

Die Mitarbeiter der Vertragsfirma sind ausweispflichtig gemäß den Bestimmungen des U.S. Verteidigungsministeriums, des Hauptquartiers der U.S. Armee, und den Bestimmungen vor Ort. Zusätzlich zu Änderungen aufgrund der Änderungsklausel zu diesem Vertrag, kann die Regierung die Sicherheitsmassnahmen oder -vorschriften ändern, wenn sich die Sicherheitseinstufung (FPCON) eines Gebäudes oder Standorts ändert.

b. iWatch/iSalute Training. Der Auftragnehmer und alle Subunternehmer müssen ihre Mitarbeiter über das örtliche iWATCH/iSALUTE Programm in Kenntnis setzen. Die erforderlichen Schulungsunterlagen werden vom Anti-Terrorismus-Bevollmächtigten der auftraggebenden Dienststelle zur Verfügung gestellt. Inhalt der Schulung ist es, die Mitarbeiter aufzuklären, gegenüber welchen ungewöhnlichen Umständen sie wachsam sein sollen, und welche sie an den COR melden sollen. Diese Schulung soll innerhalb eines Zeitraums von 30 Kalendertagen, nachdem der Vertrag vergeben und innerhalb 5 Kalendertagen nachdem neue Mitarbeiter die Arbeit gemäß Vertrag aufnehmen, stattfinden. Die Dokumentation darüber ist innerhalb von 30 Kalendertagen nach der Vertragsvergabe dem COR zu übergeben.

16. Measurements in the specification

All dimensions (sizes, technical data, etc.) in the specification are only approximate values with a tolerance of about +/- 2 %. If exact measurements are necessary, this will be specifically indicated.

16. Maßangaben in der Leistungsbeschreibung

Alle Maßangaben (Abmessungen, technische Daten, usw.) in der Leistungsbeschreibung sind Circa-Angaben mit einer Toleranz von etwa +/- 2 %. Sollten genaue Maße erforderlich sein, so wird dies gesondert angegeben.

- 20 -

17. Abbreviations

LS = lump sum ea = each linm = linear meter sqm = square meter cbm = cubic meter m = meter kg = kilogram approx. = approximately COR = Contracting Officer's Representative DC = direct current DN = nominal diameter etc. = etcetera IAW = in accordance with LED = light emitting diode PN = nominal pressure (l/w/h) = (length/width/height) (h/w/d) = (height/width/depth)

17. Abkürzungen

PS = pauschal Stck = Stück lfdm = laufende Meter qm = Quadratmeter cbm = Kubikmeter m = Meter kg = Kilogramm bzw. = beziehungsweise

ca. = circa COR = Vertreter des Vertragsoffiziers DC = Gleichstrom DN = Nenndurchmesser PN = Nenndruck usw. = und so weiter (L/B/H) = (Länge/Breite/Höhe) (H/B/T) = (Höhe/Breite/Tiefe)

Item No. Quantities Description Pos. Nr. Mengen Beschreibung

- 21 -

TECHNICAL SPECIFICATION

LEISTUNGSBESCHREIBUNG

00. Preparation Work

Vorbereitungsarbeiten

00.001

LS Transport site equipment to the job site and erect. Job site mobilization shall include all equipment, scaffolding, fences, dayrooms, storage rooms and facilities for power supply and water including connection devices which are required for a proper and timely execution of the services listed in this specification. Included is the provision of lockable storage, toilet and dayrooms for all subcontractors, unless these are a part of the incidental services according to VOB, part C, para 4.1. of the respective DIN. Job site mobilization also includes all measures for safeguarding of traffic in the area of the construction site, as well as the erection and provision of a temporary fence of wooden posts and reinforcing wire mats, around the job site and around the day and storage rooms, approx. 2.00 m high.

Provision of site equipment during the entire construction period, in accordance with the obliging construction schedule, including binding time schedules for subcontractors and temporary supply lines. Provision of the job site mobilization includes the safeguarding of all meter marks and reference points, securing of all devices, tools, machines and materials against unauthorized use, drainage of rain or surface water, the maintenance of a clean job site, cleaning of the access roads, in case the contamination was caused by the contractor or by one of his subcontractors.

Dismount and remove site equipment. This item covers the removal of all temporary fences, storage rooms and dayrooms of the job site mobilization, including backfilling and compacting of all temporary excavations, clearing and cleaning of the entire site and access roads and the restoration of these areas into their original condition.

PS Baustelleneinrichtung anfahren und aufstellen. Zur Baustelleneinrichtung gehören alle zur fach- und fristgerechten Durchführung der in diesem Projekt erfassten Bauleistungen notwendigen Geräte, Gerüste, Absperrungen, Aufenthalts- und Lagerräume, Versorgungseinrichtungen für Baustrom und Wasser einschließlich der Anschlussvorrichtungen.

Enthalten ist die Aufstellung verschließbarer Lager-, Toiletten- und Aufenthaltsräume für die Nachunternehmer (Subunternehmer), soweit dies gemäß VOB, Teil C, Ziffer

4.1. der jeweiligen DIN keine Nebenleistungen sind. Zur Baustelleneinrichtung gehören alle Maßnahmen zur Verkehrssicherung im Bereich der Baustelle, sowie das Errichten und Vorhalten eines provisorischen Bauzaunes aus Holzpfosten und Baustahlmatten, um die Baustelle und um die

- 22 -

Aufenthalts- und Lagerräume, ca. 2.00 m hoch.

Vorhalten der Baustelleneinrichtung für die Dauer der gesamten Bauzeit, entsprechend dem verbindlich aufgestellten Bauterminplan, einschließlich der verbindlich anzugebenden Terminpläne der Nachunternehmer (Subunternehmer) und provisorischer Versorgungsleitungen.

Zum Vorhalten der Baustelleneinrichtung gehören ferner die Sicherung aller Meterrisse und Messpunkte, die Sicherung aller Geräte, Werkzeuge, Maschinen und Materialien gegen unbefugte Benutzung, die Ableitung von Tag- oder Oberflächenwasser, das Sauberhalten der Baustelle, das Reinigen der Zufahrtswege, sofern diese durch den Auftragnehmer oder dessen Nachunternehmer verschmutzt wurden.

Baustelleneinrichtung abbauen und abfahren. Hierzu gehören die Beseitigung aller provisorischen Zäune, Lagerräume und Aufenthaltsräume der Baustelleneinrichtung, einschließlich verfüllen und verdichten aller zeitweiliger Ausschachtungen, das Räumen und Säubern der gesamten Baustelle und Zufahrtsstraßen sowie das Wiederversetzen dieser Flächen in ihren ursprünglichen Zustand.

00.002

LS Addition for difficult working condition. Work has to be done within a security area. Therefore coordinate the daily working time with the COR. It is possible that the contractor is not allowed to enter he job site on some days.

PS Zuschlag für erschwerte Arbeitsbedingungen. Die Arbeiten werden in einer Sicherheitszone durchgeführt. Deshalb müssen die täglichen Arbeitszeiten mit dem COR koordiniert werden. Weiterhin ist möglich, dass der Auftragnehmer die Baustelle an einzelnen Tagen nicht betreten darf.

00.003 ea Assembly and disassembly of sufficient mobile erecting scaffoldings, if required, as well as provision and transportation within the construction site.

Installation height 2.50 to 4.00 m above floor and/or terrain, in compliance with the Accident Prevention Regulations and the requirements of the Employer’s Liability Insurance Associations. Provide scaffoldings for the performance of all services described within this specification.

Stck Auf- und Abbau sowie Vorhaltung und Transport innerhalb der Baustelle von gegebenenfalls mobilen Montagegerüsten, in ausreichender Anzahl.

Montagehöhen 2,50 bis 4,00 m über Fußboden beziehungsweise Gelände, unter Einhaltung der UVV und der Forderungen der Berufsgenossenschaften, für die Dauer der Ausführung sämtlicher in der Leistungsbeschreibung dieses Titels aufgeführten Leistungen.

00.004

LS Prepare and provide the following as-built drawings as described in the General Preamble.

Coordinate the assignment of the individual levels with the

- 23 -

COR.

- Layout civil work scale 1 : 500

-…