Q_A.pdf
PDF 318 KB Posted
- Attached to
- Dillard Dry Dock Services Federal contract opportunity
- Solicitation number
- W912P7-18-T-0009
About this file
These are the questions received and responses provided.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Drawings_and_Specs.pdf | ||
| Dillard_Drydock_PWS_2018.pdf | ||
| Line_Item_Breakdown_Pricing_Schedule.xlsx | XLSX spreadsheet | |
| Marin_Wage_Determination.pdf | ||
| Contractor's_Experience_Form.docx | DOCX document | |
| FAR_Provisions.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS AND ANSWERS ABOUT THE DILLARD DRY-DOCK SOLICITATION
Q: -Will there be a walk-through of the vessel before bids are due? We are hoping to see the boat to get a better understanding of the bow chock work and the swim grid bulwark changes.
A: Yes – Information posted as Amendment 3 Site Visit Info
Q: And you provided approximate square footage for the top-side paint work - do you have a square footage for the underwater / Intersleek coverage?
A: Top-side paint square footage is listed in the scope
Q: Are there lifting lugs on the vessel? Or would lifting the boat cradled by slings be acceptable as opposed to flooding our dry dock?
A: No, the lifting lugs are not rated. Unless the contractor gets permission to use them in coordination with the vessel manufacturer, Kvichak.
Q: And if there is even a list of sacrificial anodes that are to be replaced if the Cathodic Protection drawing can’t be produced, that would be a big help.
A: The drawing package is available. See attachments