Ashtabula 204_pre-bid meeting_9FEB2021.pdf
PDF 95 KB Posted
- Attached to
- FY21 Ashtabula 204 (submerged) Breakwater Construction Federal contract opportunity
- Solicitation number
- W912P421B0003
About this file
This document summarizes a pre-bid meeting for the Ashtabula 204 Submerged Breakwater Construction contract opportunity. The meeting reviewed the contract drawings and specifications for a project to construct a new submerged stone breakwater in Ashtabula Harbor. Attendees included representatives from the U.S. Army Corps of Engineers Buffalo District and three contractor companies. Questions from contractors were submitted via chat and addressed during the meeting. All written questions on the project are due to the contracting office by February 11, 2021. The related federal contract opportunity is solicitation number W912P421B0003 for the Ashtabula 204 Submerged Breakwater Construction project through the Department of the Army Corps of Engineers Buffalo District. The estimated value of the contract is between $5 million and $10 million.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Specifications_Plans_Ash 204 Amendment 01.pdf | ||
| Wage Determination 08 Jan 2021.pdf | ||
| Amendment_Package_W912P421B0003_0001__19_Feb.pdf | ||
| W912P421B0003.pdf | ||
| Plans and Specs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ashtabula Harbor 204 Pre-Bid Meeting: New Submerged Stone Breakwater Contract.
Date: 2/9/21 Time: 1010 – 1045
Attendees LRB:
-Frank Lewandowski -Mike Voorhees -Colleen O’Connell -Russ Brandenburg -Gene Lenhardt
Attendees Contractors:
- Travis Lake (RYBA marine)
- Joe Bailey (Great Lakes Docks)
- Ben Burnham (King Co. Holland, MI)
Meeting Summary:
Opening remarks by Russ B. introducing the project and explained project purpose.
Next, Frank Lewandowski reviewed the contract drawings and the project specifications over the Webex platform.
Only one question was received from contractor via the Chat box, below:
Question from Travis Lake to everyone: 10:29 AM
Mechanically thrown in corner or pumped dredge material, how much equipment may be in our way during BW for the last 2 weeks?
LRB Response by Frank L. : mechanical placement for the dredging cycles is planned. We will not be pumping material. Dredging operations will not interfere with breakwater construction during last 2 weeks.
Frank L. stated that all questions about the project are due in writing to contracting by COB by Thursday 2/11/21.
No further questions received. Meeting adjourned.