Amendment_Package_W912P421B0003_0001__19_Feb.pdf

PDF 291 KB Posted

Attached to
FY21 Ashtabula 204 (submerged) Breakwater Construction Federal contract opportunity
Solicitation number
W912P421B0003
Issued by
Department of the Army Corps of Engineers Engineering District Buffalo

About this file

This is an amendment to a solicitation for construction of a submerged breakwater in Ashtabula, Ohio. The key details include: the solicitation number is W912P421B0003; the bid opening date has been extended from February 22 to February 24, 2021 at 3:00 PM Eastern Time with call-in instructions provided; specifications and plans have been updated including details on work by other contractors and a contract plan sheet; and the wage determination has been updated. The opportunity is for a submerged breakwater construction project with an estimated value between $5-10 million issued by the U.S. Army Corps of Engineers Buffalo District. No further substantive information is provided in this amendment beyond administrative changes to the solicitation dates and documents.

View the file

Other files for this federal contract opportunity

Other files attached to FY21 Ashtabula 204 (submerged) Breakwater Construction, newest first.
File Type Posted
Specifications_Plans_Ash 204 Amendment 01.pdf PDF
Wage Determination 08 Jan 2021.pdf PDF
Ashtabula 204_pre-bid meeting_9FEB2021.pdf PDF
W912P421B0003.pdf PDF
Plans and Specs.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W81EU603076829

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This Amendment 01:

1. This Amendment 01 has modif ied Clause 52.252-3 w ith additional information added to the solicitation.

2. This Solicitation Bid opening has been moved from 22 February 2021 to 24 February 2021 at 0300 PM Eastern Standard Time.

3. Added Bid Opening audio information by calling 844-800-2712 on the 24nd of February at 0300 PM Eastern Standard Time w ith access number 1991535914.

4. Added a correction to the LRB answ er from the Pre-Bid meeting on 09 February 2021

5. Added update to Specif ications and Plans Section 01 35 13 paragrah 1.2.6.2 Work of Others, the updated paragraph is attached. Updated contract plan Sheet G-002 in Specif ications and Plans, updated contract plan Sheet G-002 is attached.

6. Wage Determination updated

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 19-Feb-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P421B0003

X 9B. DATED (SEE ITEM 11)

19-Jan-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

19-Feb-2021

CODE

U.S. ARMY ENGINEER DISTRICT, BUFFALO

1776 NIAGARA STREET

BUFFALO NY 14207-3199

W912P4 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P421B0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 22-Feb-2021 03:00 PM to 24-Feb-2021 03:00 PM.

SECTION 00 21 13 - INSTRUCTIONS TO BIDDERS

The following have been modified:

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows:

0001 Amendment 01:

1. This Amendment 01 has modified Clause 52.252-3 with additional information added to the solicitation.

2. This Solicitation Bid opening has been moved from 22 February 2021 to 24 February 2021 at0300 PM Eastern Standard Time.

3. Added by providing the call in Bid Opening audio information by calling 844-800-2712 which will be on 24 February 2021 at 3 PM Eastern Standard Time with access code 1991535914.

4. Added a correction to the LRB answer from the Pre-Bid meeting on 09 Feb 2021

5. Added update to Specifications and Plans Section 01 35 13 paragraph 1.2.6.2 Work of Others, the updated paragraph is attached. Updated contract plan Sheet G-002 in Specifications and Plans, updated contract plan Sheet G-002 is attached.

6. Update Wage Determination.

(End of Summary of Changes)

(End of Summary of Changes)

Questions and Answers

From: Ashtabula Harbor 204 Pre-Bid Meeting: New Submerged Stone Breakwater Contract.

Date: 2/9/21 Time: 1010 – 1045

The answer given by the LRB for the question posted by the contractor at 10:29 AM at Pre-Bid meeting has changed too:

Question from Contractor to everyone: 10:29 AM

Mechanically thrown in corner or pumped dredge material, how much equipment may be in our way during BW for the last 2 weeks?

LRB Response: Conditions have changed since the pre-bid meeting at which time little impact from the dredging contractor was anticipated. Amendment 01 changes the length of time the dredging contractor will be working in the area around the east breakwater and adds contract work limits starting August 1, 2021. The dredging contractor will be operating east of the additional contract work limits and is expected to use mechanical placement of dredged material and/or bottom dumping of dredged material from a scow. Pumping dredged material is not anticipated. See attached pages for the changes made to contract specifications and plans.

Original question and response.

Only one question was received from contractor via the Chat box, below:

Question from Contractor to everyone: 10:29 AM

Mechanically thrown in corner or pumped dredge material, how much equipment may be in our way during BW for the last 2 weeks?

LRB Response : mechanical placement for the dredging cycles is planned. We will not be pumping material. Dredging operations will not interfere with breakwater construction during last 2 weeks.

No further questions received.

Front_End_W912P421B0003_P0001__19_Feb
Ashtabula 204_Questions_Update_18Feb

File details come from the government source that posted it. Updated .