Attached is the Amendment to answer questions posted on this solicitation.

View the file

Other files for this federal contract opportunity

Other files attached to Lorain Breakwater, newest first.
File Type Posted
Abstract_IGE_adjusted_Lorain_19.xls XLS spreadsheet
W912P419B0026-0003.pdf PDF
Magnitude_Amendment.pdf PDF
amendment1.pdf PDF
SolicitationFull.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04 EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The Purpose of this amendment is to post questions and answers.

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA 15C. DATE SIGNED 15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer) (Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P419B0026

X 9B. DATED (SEE ITEM 11)

22-Jul-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

U0002

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

16-Aug-2019

CODE

U.S. ARMY ENGINEER DISTRICT, BUFFALO

1776 NIAGARA STREET

BUFFALO NY 14207-3199

W912P4 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODE CODE

EMAIL: TEL:

W912P419B0026

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

(End of Summary of Changes)

Lorain Detached Breakwater Prebid Questions and Answers:

1) What are the water depths at the crack repair locations? Plans only show contours near the new sheet pile cell construction.

Answer: Survey data will be made available in xyz format that covers the complete perimeter of the lake bottom near the breakwall.

2) Is the special pile shown within the eastern side of the new cell required or could an alternate layout be utilized that doesn't require a special pile?

Answer: Alternative layouts would be considered by the Government, the special pile within the eastern sheet pile wall is not a requirement if an acceptable alternate layout is shown to not require that special pile.

3) When is award of the project anticipated?

Answer: Bids are to be opened on August 21st at 3:00PM as per the solicitation, award is anticipated for mid-September to late September.

4) What is the width of the gap between the existing piles and new piles?

Answer: The width of the gap will vary but the narrowest area is on the order of 12-24 inches.

5) A visual inspection is required. What is required in this visual inspection? Is the inspection above water only?

Answer: The visual inspection is intended to verify the crack locations shown in the contract and to capture the location of any other cracks not identified in the contract documents. Diving is not required for the visual inspection. The intent is for the inspection to be performed from a small craft when the lake conditions are flat, meaning there is minimal wave action.

6) Historical & forecasted lake levels show that the proposed C12x30 Double Channel waler will be installed below the waterline. Is the bidder to assume that the proposed waler is to be installed below the waterline?

Answer: Waler elevation may be below water at time of installation depending on actual Lake Erie water levels.

7) What are the requirements of bid item #3 Visual Survey? Is this an underwater survey of the cracks? I do not see a measurement and payment or specification section on this.

Answer: The visual inspection is intended to verify the crack locations shown in the contract and to capture the location of any other cracks not identified in the contract documents. Diving is not required for the visual inspection. The intent is for the inspection to be performed from a small craft when the lake conditions are flat, meaning there is minimal wave action.

8) Bid item 9 Solar lanterns has a quantity of 36, the plan sheet C-501 lists 19 locations with 2 lights each, this totals 38.

Answer: Please bid the quantity shown in the contract line item.

9) Does the steel debris need to be removed from site?

Answer: Steel debris, if generated or found, would need to be removed and disposed/recycled.

10) The new double channel wale is at an elevation +4.0 from LWD, water levels are currently at nearly +5.0. Is the intent that the new wale and cross bracing be installed underwater?

Answer: Waler elevation may be below water at time of installation depending on actual Lake Erie water levels.

11) Have there been other questions asked by contractors? Will there be an addendum forthcoming?

Answer: All bidder questions received on or before 13 August 2019 are answered in an amendment.