w912p4-16-B-0002-0003-final.pdf

PDF 149 KB Posted

Attached to
Seneca Bluffs Federal contract opportunity
Solicitation number
W912P4-16-B-0002
Issued by
Department of the Army Corps of Engineers Engineering District Buffalo

About this file

Answers to questions and specification page change

View the file

Other files for this federal contract opportunity

Other files attached to Seneca Bluffs, newest first.
File Type Posted
W912P4-16-B-0002-0004.pdf PDF
signin-senbluff-II.pdf PDF
W912P416B0002-amendment2.pdf PDF
Site_Visit_Signin_Sheet_-_Seneca_Bluffs.pdf PDF
Sol-SF30-W912P4-16-B-0002-Amend-1-final.pdf PDF
W912P4-16-B-0002-final-27JUN16.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment answ ers questions that w ere received and provides a notification of a change to the originally published specification. A page change is provided as an attachment. All other conditions remain the same.

1. CONTRACT ID CODE PAGE OF PAGES

1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 29-Jul-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P4-16-B-0002

X 9B. DATED (SEE ITEM 11)

27-Jun-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

29-Jul-2016

CODE

U.S. ARMY ENGINEER DISTRICT, BUFFALO

1776 NIAGARA STREET

BUFFALO NY 14207-3199

W912P4 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P4-16-B-0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

QUESTIONS AND ANSWERS

SENECA BLUFFS ‐ W912P4‐16‐B‐0002

SOLICITATION AMENDMENT

RESPONSES TO QUESTIONS RECEIVED AND NOTIFICATION OF CHANGE TO SPECIFICATION.

Question 1. "Section 01 32 16, Page 1046, 3.1.1 – Time Lapse Photography – Can you provide additional information on the requirements for this section. It states that photographs need to be collected every

30 seconds. Can the number of locations be provided? At the site walk it was stated that photographs would be submitted monthly, the spec says by the next day at 9 am, can this be clarified? Will separate cameras be needed at the various reaches outlined in 3.1.1.1 as well as the invasive species treatment areas?"

Answer:

‐ Provide Time Lapse Photography at three locations that captures an overview of the shoreline/bank work for Reach 1, 2 and 3. Three cameras will be needed and will be set in areas as specified in 3.1.1.1.

USACE will determine exact location of camera placement as part of the preconstruction documentation. Photographs should be taken every 30 seconds as is standard for readily available time lapse cameras. Photographs should be submitted monthly or whenever the memory card is full. This time lapse photography is intended to capture the progress of habitat recovery and will be used in the creation of project videos; not to show a "real time" snapshot of current work. If the photographs are not showing a good representation of the work the contractor may be required to move the camera location.

‐ Time Lapse Photography is NOT necessary for invasive species treatment areas. This is better documented with other means (i.e. photographs taken every few weeks). "Section 01 32 16 ‐ 3.1.1.2

Invasive Treatment Areas" will be removed from the specifications. (NOTE: a page change to the specification is provided as part of this amendment.)

Question 2. " Section 01 32 16 – Photographs – There are a lot of requirements for photographs and the documentation of the work, is this level of effort accurate as described in specifications?"

Answer:

‐ Yes, photographs and documentation of the work is accurate as described with the exception of video documentation. The goal for photograph documentation of the work is to get a good representation in the daily QC reports for work that was done that day. Contractor should take as many pictures necessary to give an understanding of the work that was done that day to someone who was not on site. If in the COR's opinion the photographs aren't representative the COR may request more photographs be taken to provide appropriate documentation of work.

‐ Video documentation will be at the discretion of the COR on site. If there is some installation process that is unique or the COR feels is imperative to document the COR will direct the contractor to video record it. Otherwise video documentation is not necessary day to day.

Question 3. "Section 01 35 26 – Are full time HSO and CQC required for the entire project, including invasive species treatments for each season?"

Answer:

‐ Yes

Question 4. "Spec 01 45 00 state that the CQC Manager cannot serve as the Superintendent and

Spec 01 35 26 states the CQC Manager cannot serve as the SSHO unless formally approved by the

Contracting Officer. What are the requirements to have an individual approved to serve as both the CQC

Manager and SSHO?"

Answer:

‐ As long as the individual meets the personnel qualifications for both CQC manager (Sec. 01 45 00.00 10

‐ 3.4.2) and SSHO (Sec. 01 35 26 ‐ 1.6.1.1) then documentation of the background/experience would be submitted to COR for approval of the individual.

Question 5. "Seeing this contract has a multiyear duration what are the contractors responsibilities for maintenance and repair after initial completion of earthwork, rock, and anchor logs? Specifically who is responsible for rework if flood or ice damage occurs after the civil construction component is completed?"

Answer:

‐ After "Final Acceptance Inspection" (as per Sec. 01 45 00.00 10 ‐ 3.7) for each respective reach is complete the warranty period starts for that component or reach. Until then the contractor is responsible for maintaining the completed work. The "Warranty of Construction Clause 52.246‐21" was mistakenly omitted from the contract and an amendment will be sent out with this clause reinserted that states the contractor will warranty their work for 365 days past final acceptance of work.

Question 6. "Please clarify the requirements for time lapse photographs. Specifically Spec 01 32 16 states “During the calendar 2016, time lapse photographs are required for the following areas and must be obtained until 5 minutes are completion of all work for the area, including seed and/or planting, all clean‐up has been completed, and all Contractor equipment has been moved far enough away to not be seen in any photograph."

Answer:

‐ This sentence should read "…. Are required for the following areas and must be obtained until 5 minutes OF completion of all work…". The intent is that the time lapse video in 2016 captures all work completed and remain in place to capture the growing seasons of 2017 and 2018 as specified in "Sec. 01

32 16 ‐ 3.1.1.1".

Question 7.

"Please confirm the following requirement for time lapse photographs “These photographs must be obtained at 30‐second intervals”."

Answer:

‐ See response to question #1.

Question 8. "We are trying to quantify the number of locations/cameras and durations required to achieve the requirement for Spec 01 32 16. Are time lapse photographs only required in one location in all 3 areas (Reach1, Reach 2, Reach 3) for the following periods:

August 30, 2016 to November 15, 2016 & May 15, 2017 to October 15, 2017 & May 15, 2018 to October

15, 2018"

Answer:

‐ See response to question #1 for locations. Yes. 3 time lapse cameras will be needed. One will be placed in representative areas of each of the 3 reaches. Time frame should be anytime any shoreline construction activities are taking place on Reach 1, 2 or 3. However, the cameras should be left in place in 2016 until all construction work is completed.

Question 9.

"Also how many location need to be photographed for the invasive species treatment areas? Is it just one location per reach? Are these the only periods time lapse photographs are required for invasive species treatment?

August 30, 2016 to November 15 ,2016 & June 1 ,2017 to October 1, 2017"

Answer:

‐ Time Lapse Photography is NOT necessary for invasive species treatment areas. This is better documented with other means (i.e. photographs taken every few weeks of representative areas)

(End of Summary of Changes)

Seneca Bluff Habitat Restoration (GLRI) CERTIFIED FINAL - RTA

FY16SENBLUFF W912P4-16-B-0002

3.1.1.1 Construction-Type Work

During the calendar 2016, time lapse photographs are required for the following areas and must be obtained until 5 minutes are completion of all work for the area, including seed and/or planting, all clean-up has been completed, and all Contractor equipment has been moved far enough away to not be seen in any photograph:

1. Reach 1 - Cutback area/shoreline to included tiebacks, single stone bendway weirs, locked logs, and any other type of work associated with this area, except invasive species treatment.

2. Reach 2 - Restored Wetland, and any other type of work associated with this area, except invasive species treatment.

3. Reach 3 - Cutback area/shoreline to included tiebacks, single stone bendway weirs, locked logs, and any other type of work associated with area, except invasive species treatment.

From 15 May 2017 to 15 October 2017 and 15 May 2018 to 15 October 2018, obtain the time lapse photographs of the same areas, in the same manner.

3.1.1.2 Invasive Species Treatment Areas

3.1.1.2.1 Calendar Year 2016

Begin obtaining time lapse photographs on 30 August 2016 at 12:00 PM and end on 15 November 2016, at sunset.

3.1.1.2.2 Calendar Years 2017

Begin obtaining time lapse photographs on 01 June 2017 at 12:00 PM and end 01 October 2017.

3.1.2 Surveys

Daily photographs of personnel performing all surveys. If the same survey is being performed with 2 different methods, then a photograph of each method must be taken. If more than one type of survey is being perform in a day, (before, check, after) photographs of each type must be obtained.

The quantity of photographs to be taken will be determined on site by the

COR.

3.1.3 Delivered Materials

The intent of the photographs in this paragraph is to document the materials as they are delivered and stored/stockpiled.

a. Geotextile Reinforcement:

See section 31 32 11 COIR MATTING.

1. As delivered to the project site, before unloading. There must be a photograph of each delivery.

2. After unloading of each roll.

3. As the first increment is placed, prior to stone placement.

SECTION 01 32 16 Page 1047 06/23/16

Amendment Page Change 29 July 2016