Sol-SF30-W912P4-16-B-0002-Amend-1-final.pdf
PDF 4 MB Posted
- Attached to
- Seneca Bluffs Federal contract opportunity
- Solicitation number
- W912P4-16-B-0002
About this file
Attachment Amendment 0001 to Solicitation W912P4-16-B-0002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912P4-16-B-0002-0004.pdf | ||
| w912p4-16-B-0002-0003-final.pdf | ||
| signin-senbluff-II.pdf | ||
| W912P416B0002-amendment2.pdf | ||
| Site_Visit_Signin_Sheet_-_Seneca_Bluffs.pdf | ||
| W912P4-16-B-0002-final-27JUN16.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
This amendment provides changes to the previously provided 14 JUNE 2016 PLANS AND SPECIFICATIONS. Please see the attached 12 JULY 2016 PLANS AND SPECIFICATIONS for the specific changes and updates. There are no other changes to the previously provided solicitation.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 14-Jul-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P4-16-B-0002
X 9B. DATED (SEE ITEM 11)
27-Jun-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
14-Jul-2016
CODE
U.S. ARMY ENGINEER DISTRICT, BUFFALO
1776 NIAGARA STREET
BUFFALO NY 14207-3199
W912P4 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P4-16-B-0002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
(End of Summary of Changes)
AMENDMENT NO. 1
W912P4-16-B-0002
SENECA BLUFF HABITAT RESTORATION (GLRI)
BUFFALO, NY
PLANS AND SPECIFICATIONS
12 JULY 2016
h5cosklm Highlight
Drawings
Spec Section
Number Paragraph What was changed/added/removed
00 01 15 1.2 The name of sheet C 106 has been changed
01 35 26 Intro
Added paragraph concerning accessing EM 385‐1‐1 and the two
(2) references stated in the new paragraph are added to the
"Reference" paragraph.
01 50 00 2.4 Corrected spelling of "Contractors"
01 50 00 3.1 (new)
Inserted new paragraph indicated that the large stone at the parking lot may be moved, but must be put back to their original locations.
01 50 00 3.8 Paragraph "DISPOSAL OF MATERIALS" deleted, It is in section 31
11 00
00 73 00 1.1 (d) In first sentence changed "shall" to "will"
35 31 19 2.1 & 2.1.3 In second sentence, in each, changed "shall" to "will"
00 73 00 / 01
33 00 / 01 45
00.10 10 / 01
78 00 / 31 11
00 / 32 92 19 /
32 92 20 / 35
31 19
Changed "shall" to "must" in entire section, except as noted above.
31 11 00 3.3 Added sentence "As directed by the COR, remove any fallen trees and their stumps (within the work limits) in accordance with paragraph "DISPOSAL OF MATERIALS "."
31 32 11 New section added COIR MATTING, submittal register for this section only is included.
32 92 19 All parts
(1) Added paragraph 1.11 Herbivore Repellant to inlcude additional submittals and reference (2) inserted sentence at start of paragraphs 2.2 TYPE D ‐ LIVE STAKES, 2.3 TYPE E ‐ RIPARIAN
SHRUBS, & 2.4 TYPE F ‐ RIPARIAN TREES;(3) Added paragraphs
2.9 GUYING AND STAKING MATERIAL, 2.10 HERBIVORE
REPELLANT, 2.11 ANTIDESICCANT, (4) added new paragraph 3.3
ANTIDESICCANT (all paragraph after this are renumbered and any stated, are the new numbers) (5) added sentences to 3.3
SHRUBS AND TREES b.,(6) Added new paragraph TREE/SHRUB
GENERAL PLANTING REQUIREMENTS (7) Inserted 3 sentences in paragraph 3.9 PEST CONTROL, b. Updated submittal register for this section only is included.
32 92 20 1.4.1 The 2nd sentence is changed to read "The company must be the
Contractor, and subcontractor, if used."
35 20 23 3.3.1 Corrected the spelling of "stockpile"
35 20 23 3.3.2 Added the word "refuse" into the first sentence
General
Forms for the AHA (Activity Hazard Analysis), ENG 3394 (Accident
Reporting Form) , and Transmittal Form can be found in the
Attachments panel of this PDF and will be in the same location in the As‐Awarded documents
G‐002 / C‐101 / C‐
102 / C‐106 / C‐
107 / C‐305 / C‐
Changes denoted by numbered symbol, typical shown here. For
C‐107, data for borings B‐2 through B‐7 were moved so labels are not in the border.
SENECA BLUFFS ‐ W912P4‐16‐B‐0002 ‐ CHANGES TO PLANS AND SPECIFICATIONS
All of the sections listed above, in their entirety, are inlcuded in this amendment. Page numbers will be different from original solicitation h5cosklm Highlight
Seneca Bluff Habitat Restoration (GLRI) AMENDMENT NO. 1
FY16SENBLUFF W912P4-16-B-0002
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 01 15
LIST OF DRAWINGS
02/11
PART 1 GENERAL
1.1 SUMMARY
1.2 CONTRACT DRAWINGS
-- End of Section Table of Contents --
DOCUMENT 00 01 15 Page 1032 07/07/16
SECTION 00 01 15
LIST OF DRAWINGS
02/11
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project.
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
REFERENCE NO. TITLE
G-001 COVER SHEET
G-002 GENERAL INFORMATION
G-003 PLAN OF EXISTING CONDITIONS
C-101 PLAN OF NEW WORK
C-102 PLAN OF NEW WORK - REACH 1
C-103 PLAN OF NEW WORK - REACH 2
C-104 PLAN OF NEW WORK - REACH 3-3A
C-105 PLAN OF NEW WORK - REACH 4
C-106 EROSION AND SEDIMENT CONTROL PLAN
C-107 PLAN OF SOIL BORINGS
C-301 CROSS SECTION - REACH 1
C-302 TYPICAL SECTIONS - REACH 2
C-303 CROSS SECTIONS - REACH 3-3A
C-304 CROSS SECTIONS - REACH 4
C-305 TYPICAL SECTIONS
C-501 MISC. DETAILS
E-101 INVASIVE SPECIES TREATMENT - REACH 1-2
E-102 INVASIVE SPECIES TREATMENT - REACH 3-4
E-103 SEEDING PLAN - REACH 1-2
E-104 PLANTING PLAN - REACH 1-2
E-105 SEEDING PLAN - REACH 3-4
E-106 PLANTING PLAN - REACH 3-4
-- End of Document --
DOCUMENT 00 01 15 Page 1033
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 73 00
EQUIPMENT OWNERSHIP/OPERATING EXPENSE SCHEDULE
06/16
PART 1 GENERAL
1.1 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE (MAR 1995)
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section Table of Contents --
DOCUMENT 00 73 00 Page 1034
SECTION 00 73 00
EQUIPMENT OWNERSHIP/OPERATING EXPENSE SCHEDULE
06/16
PART 1 GENERAL
1.1 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE (MAR 1995)
(a) This special contract requirement does not apply to terminations.
See 52.249-5000, Basis for Settlement of Proposals, and FAR Part 49.
(b) Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier must be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment must be based upon the applicable provisions of EP 1110 1 8, Construction Equipment Ownership and Operating Expense Schedule, Region I.
Working conditions must be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations must apply. For retroactive pricing, the schedule in effect at the time the work was performed must apply.
(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205 36, Rental Costs. Rates for equipment rented from an organization under common control, lease purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.
(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the SAT, the contracting officer will request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data must be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section --
DOCUMENT 00 73 00 Page 1035
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
05/11
PART 1 GENERAL
1.1 SUMMARY
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
1.2.2 Approving Authority
1.2.3 Work
1.3 SUBMITTALS
1.4 SUBMITTAL CLASSIFICATION
1.4.1 1.3.2 Government Approved
1.4.1.1 1.3.1.1 Designated Reviewers
1.5 PREPARATION
1.5.1 Transmittal Form
1.5.2 Identifying Submittals
1.5.3 Electronic File Format
1.6 INFORMATION ONLY SUBMITTALS
1.7 VARIATIONS
1.7.1 Considering Variations
1.7.2 Proposing Variations
1.7.3 Warranting that Variations are Compatible
1.7.4 Review Schedule is Modified
1.8 SUBMITTAL REGISTER AND DATABASE
1.8.1 Use of Submittal Register
1.8.2 Contractor Use of Submittal Register
1.8.3 Approving Authority Use of Submittal Register
1.8.4 Action Codes
1.8.4.1 Government Review Action Codes
1.8.5 Copies Delivered to the Government
1.9 SCHEDULING
1.10 GOVERNMENT APPROVING AUTHORITY
1.11 DISAPPROVED OR REJECTED SUBMITTALS
1.12 APPROVED/ACCEPTED SUBMITTALS
1.13 WITHHOLDING OF PAYMENT
1.14 STAMPS
PART 2 PRODUCTS
PART 3 EXECUTION
ATTACHMENTS:
Appendix A - Submittal Register
-- End of Section Table of Contents --
SECTION 01 33 00 Page 1036
SECTION 01 33 00 Page 1037
SECTION 01 33 00
SUBMITTAL PROCEDURES
05/11
PART 1 GENERAL
1.1 SUMMARY
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Contractor's Quality Control (CQC) System Manager and the Designer of Record, if applicable, to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited
to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications;
warranties; and other such required submittals.
Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
A submittal register showing items of equipment and materials for when submittals are required by the specifications is provided as "Appendix A - Submittal Register".
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Submittals which are required prior to start of construction (work).
issuance of contract notice to proceed.or commencing work on site.or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.
Certificates of insurance
SECTION 01 33 00 Page 1038
Surety bonds
List of proposed SubContractors
List of proposed products
Construction progress schedule
Network Analysis Schedule (NAS)
Submittal register
Schedule of prices or Earned Value Report
Health and safety plan
Work plan
Quality Control(QC) plan
Environmental protection plan
Accident Prevention Plan (APP)
Contractor Accident Prevention Checklist
Contractor Activity Hazard Analysis
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or
SECTION 01 33 00 Page 1039 system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or SubContractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and (MSDS)concerning impedances, hazards and safety precautions.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.2.2 Approving Authority
Office or designated person authorized to approve submittal.
SECTION 01 33 00 Page 1040
1.2.3 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD-01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Submittal Register; G, AOF
1.4 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
1.4.1 1.3.2 Government Approved
1.4.1.1 1.3.1.1 Designated Reviewers
The organization designated to perform the review for approval for items requiring Government approval (G) is identified by acronym in the (f) (CLASSIFICATION/GOVT OR A/E REVWR) column on the SUBMITTAL REGISTER.
Following is a list of the acronyms used and their full description:
AOF = The Resident U.S. Army Corps of Engineers Area Office, Buffalo District, U.S. Army Corps of Engineers
DC = Buffalo District, U.S. Army Corps of Engineers, ATTN:
Coastal/Geotech Team
DS = Buffalo District, U.S. Army Corps of Engineers, ATTN:
Civil/Structural Design Team
SUR = Buffalo District, U.S. Army Corps of Engineers, ATTN: Survey Team
PMP = Buffalo District, U.S. Army Corps of Engineers, ATTN: Planning Management Team
1.5 PREPARATION
1.5.1 Transmittal Form
Use the attached sample transmittal form (ENG Form 4025, found in the Attachments panel of this pdf file) for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of
SECTION 01 33 00 Page 1041 the contract drawings pertinent to the data submitted for each item.
1.5.2 Identifying Submittals
When submittals are provided by a SubContractor, the Prime Contractor is to prepare, review and stamp with Contractor's approval all specified submittals prior to submitting for Government approval.
Identify submittals, except sample installations and sample panels, with the following information permanently adhered to or noted on each separate component of each submittal and noted on transmittal form. Mark each copy of each submittal identically, with the following:
a. Project title and location.
b. Construction contract number.
c. Date of the drawings and revisions.
d. Name, address, and telephone number of subContractor, supplier, manufacturer and any other subContractor associated with the submittal.
e. Section number of the specification section by which submittal is required.
f. Submittal description (SD) number of each component of submittal.
g. When a resubmission, add alphabetic suffix on submittal description, for example, submittal 18 would become 18A, to indicate resubmission.
h. Product identification and location in project.
1.5.3 Electronic File Format
Provide submittals other than material samples in both hard copy (paper) and electronic formats. The electronic submittal file must be compiled as a single, complete document, to include the Transmittal Form described in Paragraph 1.6.1. The electronic submittal file must be named specifically according to its contents (e.g. 01 45 00.00-1.2_Quality Control Plan.pdf).
Electronic files must be of sufficient quality that all information is legible. Electronic format must be in Adobe.PDF format, unless otherwise specified or directed by the Contracting Officer's Representative (COR).
Whenever possible, PDF files must be generated from original documents so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required. Files exceeding 30 pages must be indexed and bookmarked to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature, or scan of a signature.
Email electronic submittal documents fewer than 10MB to an email address as directed by the COR. Electronic documents over 10MB must be provided on a CD/DVD, or through an electronic file sharing system such as the AMRDEC SAFE Web Application located at the following website:
https://safe.amrdec.army.mil/safe/
Provide hard copies of submittals as specified in this or other
SECTION 01 33 00 Page 1042 specification sections. Up to 2 additional hard copies of any submittal may be requested from the Contractor at the discretion of the COR, at no additional cost to the Government.
1.6 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals.
The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;
and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.7 VARIATIONS
Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.
1.7.1 Considering Variations
Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.
1.7.2 Proposing Variations
When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.
Clearly mark the proposed variation in all documentation.
Check the column "variation" of ENG Form 4025 for submittals which include proposed deviations requested by the Contractor. Set forth in writing the reason for any deviations and annotate such deviations on the submittal.
The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.
1.7.3 Warranting that Variations are Compatible
When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
SECTION 01 33 00 Page 1043
1.7.4 Review Schedule is Modified
In addition to normal submittal review period, a period of 10 working days will be allowed for consideration by the Government of submittals with variations.
1.8 SUBMITTAL REGISTER AND DATABASE
Prepare and maintain submittal register, as the work progresses. Use electronic submittal register program furnished by the Government or any other format. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and (i) as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required. Maintain a submittal register for the project in accordance with Section 01 45 00.10 10 QUALITY CONTROL SYSTEM (QCS). The Government will provide the initial submittal register
Column (c): Lists specification section in which submittal is required.
Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.
Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government.
1.8.1 Use of Submittal Register
Submit submittal register as an electronic database, using submittals management program furnished to Contractor. Submit with QC plan and project schedule. Verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register database submitted with the QC plan and the project schedule:
Column (a) Activity Number: Activity number from the project schedule.
Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.
Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.
Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.
1.8.2 Contractor Use of Submittal Register
Update the following fields in the Government-furnished submittal register
SECTION 01 33 00 Page 1044 program with each submittal throughout contract.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) List date of submittal transmission.
Column (q) List date approval received.
1.8.3 Approving Authority Use of Submittal Register
Update the following fields in the Government-furnished submittal register program.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (l) List date of submittal receipt.
Column (m) through (p) List Date related to review actions.
Column (q) List date returned to Contractor.
1.8.4 Action Codes
Entries for columns (j) and (o), are to be used are as follows (others may be prescribed by Transmittal Form):
1.8.4.1 Government Review Action Codes
"A" - "Approved as submitted"; "Completed"
"B" - "Approved, except as noted on drawings"; "Completed"
"C" - "Approved, except as noted on drawings; resubmission required"; "Resubmit"
"D" - "Returned by separate correspondence"; "Completed"
"E" - "Disapproved (See attached)"; "Resubmit"
"F" - "Receipt acknowledged"; "Completed"
"G" - "Other (Specify)"; "Resubmit"
"K" - "Government concurs with Interim Design"; "Completed"
"R" - "Acceptable for Release for Construction"; "Completed"
"X" - "Receipt acknowledged, does not comply with contract requirements"; "Resubmit"
1.8.5 Copies Delivered to the Government
Deliver one copy of submittal register updated by Contractor to Government with each invoice request.
SECTION 01 33 00 Page 1045
1.9 SCHEDULING
Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Include certifications to be submitted with the pertinent drawings at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.
b. Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A."
c. Re-submit register and annotate monthly by the Contractor with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.
d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."
1.10 GOVERNMENT APPROVING AUTHORITY
When approving authority is Contracting Officer, the Government will:
a. Note date on which submittal was received from QC Manager.
b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with markings appropriate for action indicated.
Upon completion of review of submittals requiring Government approval, stamp and date submittals. Two copies of the submittal will be retained by the Contracting Officer and one copy of the submittal will be returned to the Contractor.
1.11 DISAPPROVED OR REJECTED SUBMITTALS
Contractor must make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the Contract clause CHANGES, is to be given to the Contracting Officer. Contractor is responsible for the dimensions and design of connection details and construction of work.
Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.
SECTION 01 33 00 Page 1046
If changes are necessary to submittals, make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.12 APPROVED/ACCEPTED SUBMITTALS
The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing and other information are satisfactory.
Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible forall work.
After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.13 WITHHOLDING OF PAYMENT
Payment for materials incorporated in the work will not be made if required approvals have not been obtained. No payment for materials incorporated in the work will be made if all required Designer of Record or required Government approvals have not been obtained. No payment will be made for any materials incorporated into the work for any conformance review submittals or information only submittals found to contain errors or deviations from the Solicitation or Accepted Proposal.
1.14 STAMPS
Stamps used by the Contractor on the submittal data to certify that the submittal meets contract requirements is to be similar to the following:
SECTION 01 33 00 Page 1047
| CONTRACTOR |
| (Firm Name) | | _____ Approved | | _____ Approved with corrections as noted on submittal data and/or | | attached sheets(s) |
| SIGNATURE: __________________________________________________________ |
| TITLE: ______________________________________________________________ |
| DATE: _______________________________________________________________ |
For design-build construction, both the Contractor Quality Control System Manager and the Designer of Record are to stamp and sign to certify that the submittal meets contract requirements.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 33 00 Page 1048
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 35 26
GOVERNMENTAL SAFETY REQUIREMENTS
11/15
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.2.1 Competent Person (CP)
1.2.2 Competent Person, Confined Space
1.2.3 Competent Person, Cranes and Rigging
1.2.4 Competent Person, Excavation/Trenching
1.2.5 High Risk Activities
1.2.6 High Visibility Accident
1.2.7 Load Handling Equipment (LHE)
1.2.8 Medical Treatment
1.2.9 Near Miss
1.2.10 Operating Envelope
1.2.11 Qualified Person (QP)
1.2.12 Recordable Injuries or Illnesses
1.2.13 USACE Property and Equipment
1.2.14 Load Handling Equipment (LHE) Accident or Load Handling
Equipment Mishap
1.3 SUBMITTALS
1.4 MONTHLY MAN-HOUR EXPOSURE REPORTS
1.5 REGULATORY REQUIREMENTS
1.6 SubContractor Safety Requirements
1.6.1 Experience Modification Rate (EMR)
1.6.2 OSHA Days Away from Work, Restricted Duty, or Job Transfer
(DART) Rate
1.7 SITE QUALIFICATIONS, DUTIES, AND MEETINGS
1.7.1 Personnel Qualifications
1.7.1.1 Site Safety and Health Officer (SSHO)
1.7.1.2 Contractor Quality Control (QC) Manager:
1.7.1.3 Competent Person Qualifications
1.7.1.3.1 Competent Person for Confined Space Entry
1.7.1.4 Crane Operators/Riggers
1.7.2 Personnel Duties
1.7.2.1 Duties of the Site Safety and Health Officer (SSHO)
1.7.3 Meetings
1.7.3.1 Preconstruction Conference
1.7.3.2 Safety Meetings
1.8 ACCIDENT PREVENTION PLAN (APP)
1.8.1 Names and Qualifications
1.8.2 Plans
1.8.2.1 Confined Space Entry Plan (if applicable)
1.8.2.2 Standard Lift Plan (SLP)
1.8.2.3 Critical Lift Plan - Crane or Load Handling Equipment (if applicable)
1.8.2.4 Hazardous Energy Control Program (HECP)
1.8.2.5 Excavation Plan
1.9 ACTIVITY HAZARD ANALYSIS (AHA)
SECTION 01 35 26 Page 1049
1.9.1 AHA Management
1.9.2 AHA Signature Log
1.10 DISPLAY OF SAFETY INFORMATION
1.10.1 Safety Bulletin Board
1.10.2 Safety and Occupational Health (SOH) Deficiency Tracking System
1.11 SITE SAFETY REFERENCE MATERIALS
1.12 EMERGENCY MEDICAL TREATMENT
1.13 NOTIFICATIONS and REPORTS
1.13.1 Mishap Notification
1.13.2 Accident Reports
1.13.3 LHE Inspection Reports
1.13.4 Certificate of Compliance and Pre-lift Plan/Checklist for LHE and Rigging
1.14 CONFINED SPACE ENTRY REQUIREMENTS.
1.14.1 Entry Procedures
1.15 SEVERE STORM PLAN
PART 2 PRODUCTS
2.1 CONFINED SPACE SIGNAGE
PART 3 EXECUTION
3.1 CONSTRUCTION AND OTHER WORK
3.1.1 Worksite Communication
3.1.2 Hazardous Material Use
3.1.3 Hazardous Material Exclusions
3.1.4 Unforeseen Hazardous Material
3.2 CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT)
3.3 EQUIPMENT
3.3.1 Material Handling Equipment (MHE)
3.3.2 Load Handling Equipment (LHE)
3.3.3 Machinery and Mechanized Equipment
3.3.4 USE OF EXPLOSIVES
3.4 EXCAVATIONS
3.4.1 Utility Locations
3.4.2 Utility Location Verification
3.4.3 Utilities Within and Under Concrete, Bituminous Asphalt, and
Other Impervious Surfaces
3.5 ELECTRICAL
3.5.1 Conduct of Electrical Work
3.5.2 Qualifications
3.5.3 Arc Flash
3.5.4 Grounding
3.5.5 Testing
-- End of Section Table of Contents --
SECTION 01 35 26 Page 1050
SECTION 01 35 26
GOVERNMENTAL SAFETY REQUIREMENTS
11/15
PART 1 GENERAL
The Engineer Manual EM 385-1-1 can be accessed at http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf
NOTE: The requirements of this Guide Specification supplement U.S. Army Corps of Engineers (USACE) Safety and Health Requirements Manual, EM 385-1-1, and clarify safety concerns for all activities. All contracts that include FAR Clause 52.236-13 require the Contractor to prepare and execute a written APP - Accident Prevention Plan and AHA's - Activity Hazard Analyses in accordance with EM 385-1-1, Safety and Health Requirements Manual based upon the work to be performed. (POLICY MEMORANDUM and
OPERATIONS ORDER)
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)
ASSE/SAFE A10.34 (2001; R 2012) Protection of the Public on or Adjacent to Construction Sites
ASSE/SAFE A10.44 (2014) Control of Energy Sources (Lockout/Tagout) for Construction and Demolition Operations
ASSE/SAFE Z244.1 (2003; R 2014) Control of Hazardous Energy Lockout/Tagout and Alternative Methods
ASME INTERNATIONAL (ASME)
ASME B30.20 (2013; INT Oct 2010 - May 2012) Below-the-Hook Lifting Devices
ASME B30.22 (2010) Articulating Boom Cranes
ASME B30.26 (2015; INT Jun 2010 - Jun 2014) Rigging Hardware
ASME B30.3 (2009) Tower Cranes
ASME B30.8 (2010) Floating Cranes and Floating Derricks
ASME B30.5 (2014) Mobile and Locomotive Cranes
ASME B30.9 (2014; INT Feb 2011 - Nov 2013) Slings
SECTION 01 35 26 Page 1051
ASTM INTERNATIONAL (ASTM)
ASTM F855 (2015) Standard Specifications for Temporary Protective Grounds to Be Used on De-energized Electric Power Lines and Equipment
Institute of Electrical and Electronics Engineers (IEEE)
IEEE 1048 (2003) IEEE Guide to Protective Grounding of Power Lines
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 10 (2013) Standard for Portable Fire Extinguishers
NFPA 241 (2013; Errata 2015) Standard for Safeguarding Construction,Alteration, and Demolition Operations
NFPA 70 (2014; AMD 1 2013; Errata 1 2013; AMD 2 2013; Errata 2 2013; AMD 3 2014; Errata 3-4 2014; AMD 4-6 2014) National Electrical Code
NFPA 70E (2015; ERTA 1 2015) Standard for Electrical Safety in the Workplace
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
POLICY MEMORANDUM USACE "Policy Memorandum For USACE District Chiefs of Operations and Cheifs of Construction", 2 November 2011
OPERATIONS ORDER USACE "Operations Order 2014-020 (Crane Safety Program Review)—LRD (U)"; Issue Date: 15OCT2014
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910 Occupational Safety and Health Standards
29 CFR 1910.146 Permit-required Confined Spaces
29 CFR 1910.147 Control of Hazardous Energy (Lock Out/Tag Out)
29 CFR 1910.333 Selection and Use of Work Practices
29 CFR 1915 Confined and Enclosed Spaces and Other Dangerous Atmospheres in Shipyard Employment
29 CFR 1915.89 Control of Hazardous Energy (Lockout/Tags-Plus)
SECTION 01 35 26 Page 1052
29 CFR 1926 Safety and Health Regulations for Construction
29 CFR 1926.1400 Cranes and Derricks in Construction
29 CFR 1926.16 Rules of Construction
CPL 2.100 (1995) Application of the Permit-Required Confined Spaces (PRCS) Standards, 29 CFR 1910.146
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE C2 (2012) National Electrical Safety Code
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA Z535.2 (2011) Environmental and Facility Safety Signs
1.2 DEFINITIONS
1.2.1 Competent Person (CP)
The CP is a person designated in writing, who, through training, knowledge and experience, is capable of identifying, evaluating, and addressing existing and predictable hazards in the working environment or working conditions that are dangerous to personnel, and who has authorization to take prompt corrective measures with regards to such hazards.
1.2.2 Competent Person, Confined Space
The CP, Confined Space, is a person meeting the competent person requirements as defined EM 385-1-1 Appendix Q, with thorough knowledge of OSHA’s Confined Space Standard, 29 CFR 1910.146, and designated in writing to be responsible for the immediate supervision, implementation and monitoring of the confined space program, who through training, knowledge and experience in confined space entry is capable of identifying, evaluating and addressing existing and potential confined space hazards and, who has the authority to take prompt corrective measures with regard to such hazards.
1.2.3 Competent Person, Cranes and Rigging
The CP, Cranes and Rigging, as defined in EM 385-1-1 Appendix Q, is a person meeting the competent person, who has been designated in writing to be responsible for the immediate supervision, implementation and monitoring of the Crane and Rigging Program, who through training, knowledge and experience in crane and rigging is capable of identifying, evaluating and addressing existing and potential hazards and, who has the authority to take prompt corrective measures with regard to such hazards.
1.2.4 Competent Person, Excavation/Trenching
A CP, Excavation/Trenching, is a person meeting the competent person requirements as defined in EM 385-1-1 Appendix Q and 29 CFR 1926, who has been designated in writing to be responsible for the immediate supervision, implementation and monitoring of the excavation/trenching program, who
SECTION 01 35 26 Page 1053 through training, knowledge and experience in excavation/trenching is capable of identifying, evaluating and addressing existing and potential hazards and, who has the authority to take prompt corrective measures with regard to such hazards.
1.2.5 High Risk Activities
High Risk Activities are activities that involve work at heights, crane and rigging, excavations and trenching, scaffolding, electrical work, and confined space entry.
1.2.9 1.2.6 High Visibility Accident
A High Visibility Accident is any mishap which may generate publicity or high visibility.
1.2.7 Load Handling Equipment (LHE)
LHE is a term used to describe cranes, hoists and all other hoisting equipment (hoisting equipment means equipment, including crane, derricks, hoists and power operated equipment used with rigging to raise, lower or horizontally move a load).
1.2.8 Medical Treatment
Medical Treatment is treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by a physician or registered personnel.
1.2.9 Near Miss
A Near Miss is a mishap resulting in no personal injury and zero property damage, but given a shift in time or position, damage or injury may have occurred (e.g., a worker falls off a scaffold and is not injured; a crane swings around to move the load and narrowly misses a parked vehicle).
1.2.10 Operating Envelope
The Operating Envelope is the area surrounding any crane or load handling equipment. Inside this "envelope" is the crane, the operator, riggers and crane walkers, other personnel involved in the operation, rigging gear between the hook, the load, the crane's supporting structure (i.e. ground or rail), the load's rigging path, the lift and rigging procedure.
1.2.11 Qualified Person (QP)
The QP is a person designated in writing, who, by possession of a recognized degree, certificate, or professional standing, or extensive knowledge, training, and experience, has successfully demonstrated their ability to solve or resolve problems related to the subject matter, the work, or the project.
1.2.12 Recordable Injuries or Illnesses
Recordable Injuries or Illnesses are any work-related injury or illness that results in:
a. Death, regardless of the time between the injury and death, or the
SECTION 01 35 26 Page 1054 length of the illness;
b. Days away from work (any time lost after day of injury/illness onset);
c. Restricted work;
d. Transfer to another job;
e. Medical treatment beyond first aid;
f. Loss of consciousness; or
g. A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in (a) through (f) above.
1.2.13 USACE Property and Equipment
Interpret "USACE" property and equipment specified in USACE EM 385-1-1 as Government property and equipment.
1.2.14 Load Handling Equipment (LHE) Accident or Load Handling Equipment Mishap
A LHE accident occurs when any one or more of the eight elements in the operating envelope fails to perform correctly during operation, including operation during maintenance or testing resulting in personnel injury or death; material or equipment damage; dropped load; derailment;
two-blocking; overload; or collision, including unplanned contact between the load, crane, or other objects. A dropped load, derailment, two-blocking, overload and collision are considered accidents, even though no material damage or injury occurs. A component failure (e.g., motor burnout, gear tooth failure, bearing failure) is not considered an accident solely due to material or equipment damage unless the component failure results in damage to other components (e.g., dropped boom, dropped load, or roll over). Document any mishap that meets the criteria described in the Contractor Significant Incident Report (CSIR) using the Crane High Hazard working group mishap reporting form.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Accident Prevention Plan (APP); G, AOF
Contractor Accident Prevention Plan (APP) Checklist; G, AOF
Activity Hazard Analysis (AHA); G, AOF
SD-06 Test Reports
SECTION 01 35 26 Page 1055
Monthly Man-Hour Exposure Reports
Notifications and Reports
Accident Reports; G, AOF
LHE Inspection Reports
SD-07 Certificates
Crane Operators/Riggers
Standard Lift Plan; G, AOF
Critical Lift Plan ; G, AOF
Confined Space Entry Permit
Naval Architecture Analysis; G, AOF
Certificate of Compliance
1.4 MONTHLY MAN-HOUR EXPOSURE REPORTS
Provide a Monthly Exposure Report and attach to the monthly billing request. This report is a compilation of employee-hours worked each month for all site workers, both Prime and subContractor. Failure to submit the report may result in retention of up to 10 percent of the voucher.
1.5 REGULATORY REQUIREMENTS
In addition to the detailed requirements included in the provisions of this contract, comply with the most recent edition of USACE EM 385-1-1, and all federal, state, and local laws, ordinances, criteria, rules and regulations. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work.
Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern.
1.6 SubContractor Safety Requirements
For this contract, neither Contractor nor any subContractor may enter into contract with any subContractor that fails to meet the following requirements. The term subContractor in this and the following paragraphs means any entity holding a contract with the Contractor or with a subContractor at any tier.
1.6.1 Experience Modification Rate (EMR)
SubContractors on this contract must have an effective EMR less than or equal to 1.10, as computed by the National Council on Compensation Insurance (NCCI) or if not available, as computed by the state agency's rating bureau in the state where the subContractor is registered, when entering into a subcontract agreement with the Prime Contractor or a subContractor at any tier. The Prime Contractor may submit a written request for additional consideration to the Contracting Officer where the
SECTION 01 35 26 Page 1056 specified acceptable EMR range cannot be achieved. Relaxation of the EMR range will only be considered for approval on a case-by-case basis for special conditions and must not be anticipated as tacit approval.
Contractor's Site Safety and Health Officer (SSHO) must collect and maintain the certified EMR ratings for all subContractors on the project and make them available to the Government at the Government's request.
1.6.2 OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART) Rate
SubContractors on this contract must have a DART rate, calculated from the most recent, complete calendar year, less than or equal to 3.4 when entering into a subcontract agreement with the Prime Contractor or a subContractor at any tier. The OSHA Dart Rate is calculated using the following formula:
(N/EH) x 200,000 where:
N = number of injuries and illnesses with days away, restricted work, or job transfer
EH = total hours worked by all employees during most recent, complete calendar…