Amendment_5_17June2015.pdf
PDF 273 KB Posted
- Attached to
- Ashtabula Harbor Dredging Federal contract opportunity
- Solicitation number
- W912P4-15-B-0005
About this file
Please see attached Amendment 5.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_Abstract_Ashtabula_30Jun2015.xls | XLS spreadsheet | |
| Amendment_6.doc | DOC document | |
| W912P4-15-B-0005-0004.pdf | ||
| Amendment_3_08June2015.pdf | ||
| Amendment_2_02Jun2015.pdf | ||
| Amendment_1_01Jun2015.pdf | ||
| Final_Solicitation_04May2015.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
This amendment is making changes to specs package along w ith updated bid form. Please see attached documents for further information.
All other terms remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 17-Jun-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P4-15-B-0005
X 9B. DATED (SEE ITEM 11)
29-Apr-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
17-Jun-2015
CODE
DEPARTMENT OF THE ARMY
USACE, BUFFALO
1776 NIAGARA STREET
BUFFALO NY 14207-3199
W912P4 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
X 1
W912P4-15-B-0005
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
(End of Summary of Changes)
AMENDMENT NO. 5
W912P4-15-B-0005
ASHTABULA HARBOR
MAINTENANCE DREDGING
ASHTABULA, OH
RESPONSE TO BIDDERS
QUESTIONS AND UPDATED
SPECIFICATIONS
17 JUNE 2015
The following pages contains these items:
1. Answers to potential bidder questions.
2. Replacement pages for section 01 35 13 SPECIAL PROJECT PROCEDURES: Changes have been made to the following paragraph:
a. 1.2 (changes highlighted)
3. Replacement pages for section 31 11 00.02 PILOT STUDY: ACTIVATED CARBON FOR DREDGED MATERIAL:. Changes have been made in the following paragraphs:
a. 3.4 (changes highlighted)
FY15 ASHTABULA HARBOR DREDGING PROJECT
ASHTABULA, OHIO
June 17, 2015
Responses to questions from potential bidders:
Question: “Clarification on Amendment 2 Section 32 11 00.02
Paragraph 3.4 states:
Place 15 inches of sediment into the scow Distribute one inch of granular activated carbon across surface of placed sediment
Distribute one inch of powered activated carbon across surface of placed sediment
Add equivalent of six inches of water
What will be the tolerances for placement thickness of sediment?
What will be the tolerances for placement thickness of activated carbon?
How will the thickness be measured to ensure tolerances are met?
Is it the intent to have the contractor place dredge sediment into scow, then grade material in scow for required thickness? Or will contractor be required to place 15 inches of sediment to a uniform grade?
During the stages of material placement the doors of the scows will be under the waterline, this will cause the pockets to be partially flooded with water. Will the material scows have to be water free during the placement of material? Is the intent to use water tight material barges and then re‐ handle material into bottom dump barges for placement?
Material scows do not have uniform cross sectional shape. Please confirm the intent of placing material in specified thicknesses instead of volume?”
This appears to be a very restrictive requirement.
Response: It is the intent of the specification to provide specific proportions of sediment, activated carbon, and water which is to be uniformly distributed in the final treated product.
Treatment must consist of thin-layer (approximately 15 inches) mixing to ensure a thorough, uniform mix is provided. The specification has been modified to emphasize that the specific treatment (mixing) details pertaining to the Contractor’s means and methods for achieving this objective will be provided by the Contractor in the Pilot Study Plan.
FY15 ASH HARBOR DREDGING Amendment No. 5
FY15ASHDREDGE W912P4-15-B-0005
SECTION 01 35 13
SPECIAL PROJECT PROCEDURES
04/06
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only or as otherwise designated. The following must be submitted in accordance with Section 01 33 00, "SUBMITTAL PROCEDURES":
SD-01, Preconstruction Submittals
Candidates
See paragraph 1.2.2 Candidates.
Schedule of Work
Contractor must submit a complete Schedule of Work.
SD-06, Test Reports
Contract Accruals
SD-07, Certificates
Notifications
Submit notification contacts, including date, time and individual contacted.
Notice to Mariners
A copy of the completed "NOTICE TO MARINERS" form must be provided prior to the commencement of work.
1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
Commence work under this contract within ten (10) calendar days after the date of receipt by the Contractor of the Notice to Proceed to prosecute said work diligently, and to complete the entire work ready for use not later than sixty seven (67) calendar days from the date of receipt by the Contractor of the Notice to Proceed provided, that should the total quantity of material to be paid for and actually removed under this contract exceed the limit established in the clause entitled "Variations in Estimated Quantities-Dredging", additional time will be allowed at the rate of one (1) calendar day for each 3,500 cubic yards in excess of the established limit. Of this sixty seven (67) day performance period, fifty
(50) days have been allocated for submittal review and their approval. The time stated for completion must include final clean-up of the premises.
SECTION 01 35 13 Page 1021 06/17/15 h5cosklm Highlight h5cosklm Highlight h5cosklm Highlight
Additionally, the time period between the date of the Notice to Proceed and the opening date of the Environmental Window is reserved for administrative work (submittals, mobilization, etc.) and actual dredging must not commence until the opening date of the Environmental Window. The Contractor must comply with the milestone schedule below. Time extensions will be granted based upon the quantity of material and the dredging rate indicated above, if any of the Option Item are exercised. A time extension of eight (8) days will be provided if Option B (Pilot Study) is exercised.
Milestone Maximum Calendar Days After Receipt of Notice to Proceed
Commence Work (Submittals, Administration, etc.) 10
Commence Actual Sediment Removal Operations 45
Complete Entire Work 67
a. The Notice to Proceed will be issued on or about 07/15/15.
1.2.1 Environmental Window
Based upon Environmental conditions, dredging in the Federal channel may not start before 1 July 2015. Dredging is permitted until 15 October 2015.
1.2.2 Candidates
The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 10 calendar days after the initial contract award."
1.2.3 Schedule of Work
The Contractor must submit a complete schedule of work covering the period of time from the Notice of Award through the specified duration of the contract, including all private and Government work, and the quantity of each type of plant intended for each project, to the Contracting Officer within ten (10) calendar days of receipt of the Notice of Award.
1.2.4 Contract Accruals
In conjunction with the schedule submittal requirements specified in Contract Clause (Section 00700) entitled "Schedules for Construction Contracts", the Contractor must submit a monthly listing of accruals.
Accruals are used to provide projections of the incremental costs not yet paid for, but earned. The accrual submittal must be made one week before the end of each month throughout the contract duration. The accrual information must be provided for each line item of the Bidding Schedule.
SECTION 01 35 13 Page 1022 06/17/15 h5cosklm Highlight h5cosklm Highlight h5cosklm Highlight
e. The Contractor must record and report both the specific coordinates of each scow discharge point and the estimated quantity of sediment in each scow. Discharge locations must be referenced to the scow center point and established using the GPS equipment/accuracy required in this section.
3.4 SEDIMENT TREATMENT
The final 1,500 cubic yards of dredged sediment must be treated (mixed) with activated carbon as indicated below. The Contractor must submit a Pilot Study Plan which details how the sediment will be treated (mixed) to provide a thorough and uniform mixture of sediment, activated carbon, and water. The mixing proportions must be as follows:
PARTS BY
VOLUME
MATERIAL
15 Dredged Sediment
1 Granular Activated Carbon
1 Powder Activated Carbon
6 Water
Using the proportions shown above, mix the materials until free water and all carbon are mixed into the sediment. All mixing must be done in layers to prevent pockets of unmixed materials. The Contractors Pilot Study Plan must propose mixing methods using the general sequence and procedure provided below:
1. Place 15 inches of sediment into the scow.
2. Distribute one inch of granular activated carbon across the surface of the placed sediment.
3. Distribute one inch of powdered activated carbon across the surface of the placed sediment.
4. Add the equivalent of six inches of water.
5. Mix carbon with dredged material and water with dredge bucket in the scow until free water and all carbon are mixed into the sediment.
6. Repeat steps 1 through 5 until the barge is nominally full and all of the powdered activated carbon is used.
7. Disperse the remaining granular activated carbon across the surface of the load and add sufficient buckets of water to thoroughly wet the surface granular activated carbon layer.
3.5 CLOSEOUT SUBMITTAL
After the locations off all scows (where that sediment was placed) has been recorded, submit a final plot showing all locations for all scows, with all locations labeled by scow number (#1 - #{final scow count}). Include a table indicating the estimated quantity of material placed from each scow.
SECTION 32 11 00.02 Page 1081 06/17/15 h5cosklm Highlight
SECTION 00010
SOLICITATION, OFFER, AND AWARD (SF1142) AND BIDDING SCHEDULE
BIDDING SCHEDULE
This Bidding Schedule will be based upon dredging and placement of dredged material from the Ashtabula Outer Harbor in the Government-furnished Open Lake Placement, as shown on the contract drawings, in accordance with these specifications.
Item No. Description
Estimated Quantity
Unit Unit Price
Estimated Amount
1 Mobilization and Demobilization 1 JB $ $
2 Dredge Outer Harbor and Lower
River with placement in Government-furnished Open Lake Placement Site 75,000
CY $ $
Total Estimated Amount (Items 1 ~ 2) $
OPTION "A"
3 Dredge Outer Harbor and Lower River with placement in Government-furnished Open Lake Placement Site
25,000
CY $ $
OPTION "B"
4 Pilot Study 1 JB $ $
Total Estimated Amount (Items 1 through 4) $
NOTE 1: BIDS MUST BE COMPLETE AS TO ALL THE ITEMS ON THE SCHEDULE.
FAILURE TO COMPLETE ALL ITEMS ON A BID SCHEDULE WILL RENDER THE BID NON-
RESPONSIVE.
NOTE 2: FOR BID EVALUATION PURPOSES, THE TOTAL BID WILL BE BASED UPON THE
TOTAL OF THE BASE BID (ITEMS 1 ~ 2) AND THE OPTIONS (ITEMS 3 ~ 4) SHOWN ABOVE.
NOTE 3: REGARDING OPTION ITEM 3, THE GOVERNMENT MAY ELECT TO AWARD OR
NOT TO AWARD THE OPTION. IF THE OPTION ITEM IS AWARDED, THE GOVERNMENT
RESERVES THE RIGHT TO LIMIT THE QUANTITY OF MATERIAL UP TO THE ESTIMATED
QUANTITY OF THE OPTION ITEM. IF THE OPTION IS AWARDED, IT WILL BE AWARDED
WITHIN FORTY-FIVE (45) DAYS OF THE CONTRACT AWARD.
NOTE 4: REGARDING OPTION ITEM 4, THE GOVERNMENT MAY ELECT TO AWARD OR
NOT TO AWARD THE OPTION. IF THE OPTION IS AWARDED, IT WILL BE AWARDED
WITHIN FORTY-FIVE (45) DAYS OF THE CONTRACT AWARD.