Amendment_3_19Mar2015.pdf
PDF 207 KB Posted
- Attached to
- Cleveland Harbor Dredging Federal contract opportunity
- Solicitation number
- W912P4-15-B-0001
About this file
Please see attached amendment 3 correcting admin errors to bid schedules.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_Abstract_Schedule_B_24Mar2015.pdf | ||
| Bid_Abstract_Schedule_A_24Mar2015.pdf | ||
| Bid_Abstract_Schedule_C_24Mar2015.pdf | ||
| Amendment_2_13March2015.pdf | ||
| Amendment_1_05Mar2015.pdf | ||
| Solicitation_Final_24Feb2015(2).pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 00010
SOLICITATION, OFFER, AND AWARD (SF1142) AND BIDDING SCHEDULE
BIDDING SCHEDULE "A"
Bids on Bidding Schedule “A” will be based upon dredging and disposal of dredged material from the Cuyahoga River in the Government-furnished Confined Disposal Facility (CDF) #10B, and Open Lake Placement Site #1, as shown on the contract drawings, in accordance with these specifications.
Item Estimated Unit Estimated No. Description Quantity Unit Price Amount
SPRING/SUMMER 2015 DREDGING PERIOD
1 Mobilization and Demobilization JB $ $
Maintenance Dredging: Upper Cuyahoga River (STA 735+00 to 799+92) w/ placement in Open Lake Site #1)
155,000
CY
Maintenance Dredging: Lower Cuyahoga River (Sta. 499+34 to 735+00) and Old River w/ placement in Government-furnished CDF #10B)
45,000
Total Estimated Amount (Items 1 ~ 3) $
OPTION "A" FALL 2015 DREDGING PERIOD
4 Mobilization and Demobilization JB $ $
5 Maintenance Dredging: Upper Cuyahoga River (Sta. 749+00 to 799+92) w/ placement in Open Lake Site #1)
25,000
CY $ $
Total Estimated Option "A" Amount (Items 4-5) $
Total Estimated Amount (Items 1 through 5) $
(Cont.)
SCHEDULE "A" CONTINUED:
NOTE 1: BIDDERS ARE REQUIRED TO BID ON ALL SCHEDULES. THE GOVERNMENT
RESERVES THE RIGHT TO MAKE AWARD TO THE LOWEST BIDDER (BASE + OPTIONS)
ON "SCHEDULE A", "SCHEDULE B", OR "SCHEDULE C". THE CONTRACTING OFFICER
WILL DETERMINE AN OFFER UNRESPONSIVE FOR FAILURE TO BID ON ALL SCHEDULES.
NOTE 2: FOR BID EVALUATION PURPOSES, THE TOTAL BID WILL BE BASED UPON THE
TOTAL OF THE BASE BID (ITEMS 1 ~ 3) AND OPTIONS (ITEMS 4 THROUGH 5) SHOWN
ABOVE. EACH SCHEDULE WILL BE EVALUATED INDIVIDUALLY AND NO
COMBINATION OF SCHEDULES WILL BE PERMITTED.
NOTE 3: THE GOVERNMENT MAY ELECT TO AWARD ANY OPTION ON AN INDIVIDUAL
SCHEDULE OR NO OPTIONS. IF ANY OF THESE OPTION ITEMS ARE AWARDED, THE
GOVERNMENT RESERVES THE RIGHT TO LIMIT THE QUANTITY OF MATERIAL UP TO
THE ESTIMATED QUANTITY OF EACH OPTION ITEM.
NOTE 4: ANY OPTIONS AWARDED ON SCHEDULE "A" WILL BE AWARDED WITHIN THE
FOLLOWING SCHEDULE:
(1) OPTION A (FALL DREDGING) - BY 01 OCTOBER, 2015
BIDDING SCHEDULE "B"
Bids on Bidding Schedule “B” will be based upon dredging and disposal of dredged material from the Cuyahoga River in the Government-furnished Confined Disposal Facility (CDF) #10B, and a contractor-furnished placement area, as shown on the contract drawings, in accordance with these specifications.
Item Estimated Unit Estimated
2 Maintenance Dredging: Lower
Cuyahoga River (Sta. 499+34 to 735+00) and Old River w/ furnished CDF 10B) 45,000
Total Estimated Amount (Items 1-2) $
OPTION "A"SPRING/SUMMER 2015 DREDGING PERIOD
3 Maintenance Dredging: Upper
799+92) w/ placement in Government-furnished CDF 10B)
70,000
OPTION "B"SPRING/SUMMER 2015 DREDGING PERIOD
4 Maintenance Dredging: Upper
799+92) w/ placement in Contractor-furnished Placement Area) 45,000
SCHEDULE "B" CONTINUED:
OPTION "C" FALL 2015 DREDGING PERIOD
5 Mobilization and Demobilization JB $ $
6 Maintenance Dredging: Upper
Cuyahoga River (Sta. 749+00 to 799+92) w/ placement in Government-furnished CDF #10B) 20,000
Total Estimated Option "C" Amount (Items 5-6) $
Total Estimated Amount (Items 1 ~6) $
RESERVES THE RIGHT TO MAKE AWARD TO THE LOWEST BIDDER (BASE + OPTIONS)
TOTAL OF THE BASE BID (ITEMS 1 ~ 2) AND OPTIONS (ITEMS 3 THROUGH 6) SHOWN
NOTE 4: ANY OPTIONS AWARDED WILL BE AWARDED WITHIN THE FOLLOWING
SCHEDULE:
(1) OPTION A - WITHIN 60 DAYS OF CONTRACT AWARD
(2) OPTION B - WITHIN 75 DAYS OF CONTRACT AWARD
(3) OPTION C (FALL DREDGING) - BY 01 OCTOBER, 2015
BIDDING SCHEDULE "C"
Bids on Bidding Schedule “C” will be based upon dredging and mechanical placement of all dredged material from the Cuyahoga River in the Government-furnished Confined Disposal Facility (CDF) #10B as shown on the contract drawings, in accordance with these specifications.
Item Estimated Unit Estimated
2 Maintenance Dredging: Upper
799+92) w/ w/ mechanical furnished CDF #10B) 115,000
3 Maintenance Dredging: Lower
Cuyahoga River (STA 499-34 to 735+00) and Old River w/ mechanical placement in Government-furnished CDF #10B)
45,000
4 Temporary CDF Improvement JB $ $
Total Estimated Amount (Items 1 ~ 4) $
OPTION "A" FALL 2015 DREDGING PERIOD
5 Mobilization and Demobilization JB $ $
6 Maintenance Dredging: Upper
Cuyahoga River (STA 749+00 to 799+92) w/ mechanical placement in Government-furnished CDF #10B)
20,000
Total Estimated Option "A" Amount (Items 5-6) $
SCHEDULE "C" CONTINUED:
Total Estimated Amount (Items 1 through 6) $
RESERVES THE RIGHT TO MAKE AWARD TO THE LOWEST BIDDER (BASE + OPTIONS)
TOTAL OF THE BASE BID (ITEMS 1 ~ 4) AND OPTIONS (ITEMS 5 THROUGH 6) SHOWN
NOTE 4: ANY OPTIONS AWARDED ON SCHEDULE "C" WILL BE AWARDED WITHIN THE
FOLLOWING SCHEDULE:
(1) OPTION A (FALL DREDGING) - BY 01 OCTOBER, 2015