TECHNICAL SPECIFICATIONS

DEMO RADOME TOWER #4

PROJECT NO. TVAD022203

FROM:

156th AW/MSG BASE CIVIL ENGINEER

PUERTO RICO AIR NATIONAL GUARD

CAROLINA, PUERTO RICO

FOR:

156th AW/MSG CONTRACTING OFFICER

PUERTO RICO AIR NATIONAL GUARD

CAROLINA, PUERTO RICO

TECHNICAL PROVISIONS

DEMO FUEL RADOME TOWER #4

PROJECT NO. TVAD022203

GENERAL INDEX

SECTION CONTENTS PAGE NO.

A

Work to be done

B

Scope of work

C

Location of the works

D

Special Instructions to Contractor

E

LBP Report

Annex 1

PART 1

DESCRIPTION OF WORK:

a. Work to be done:

· The work consists in demolition of RADOME TOWER #4 to include removal and disposition and/or recycling of all demolition debris and the furnishing of all labor, equipment, appliances, materials and performing all operations in strict accordance with the specifications and the applicable drawings, and subject to the terms and conditions of the contract.

· Contractor will conduct demolition operations assuming that no hazardous materials are present at tower other than lead based paint in the areas identified in annexed report.

· The following is a list of the principal features of the project as described in the specifications, shown, noted or implied upon in the accompanying drawings, showing the general characteristics and extent of the work.

· Parts not specifically detailed shall be constructed in a manner and spirit conforming to the class of work required for the whole project following the best engineering practices.

· Period of Performance for this project is 100 days. This period of performance considers a period up to the initial 30 calendar days for permits and coordination for environmental requirement.

b. Scope of work:

1. Permits and Testing

· Contractor will be responsible for requesting and obtaining all required permits as per Federal and State regulations.

· Contractor is responsible to perform all testing required by Federal and state regulations.

2. Ancillary Equipment

· Contractor will remove and properly dispose according with Federal and state regulations all existing equipment related to the Radome Tower #4.

· Contractor will be required to perform Lead Based Paint (LBP) Abatement actions in accordance with Puerto Rico Environmental Quality Board lead regulations prior to demolishing the structure. The contaminated surfaces or substrates will be removed. The waste generated has to be characterized to determine if the waste generated is hazardous or non hazardous waste.

· The firm providing the abatement services must be certified as an abatement firm by the EQB.

· Workers conducting abatement must be trained and certified as abatement workers by a training provider accredited by the EQB.

· Manifests of all waste containing LBP must be provided by contractor to the PRANG.

· Refer to LBP Inspection Report for PSRS, dated March 2010, Annex 1.

· Contractor shall present documented evidence of recycling from total volume of materials resulting from project execution as per specifications.

· Excavate and install approx. 135 ft of 1 ¼ inch electrical underground conduit to provide electrical power from Building 16 (Admin Building) to Building 29 (Guard House). Excavation will include pavement sawcut and trenching of approximately 20 ft. Compact excavation by layers according to compacting equipment. Asphalt pavement finishing must match existing conditions smoothly. Provide photos of open excavation with final installation of conduits.

· All existing electric, water, data and control conduits running from the Radome tower to any adjacent building will be capped and abandoned in place and documented as per specifications.

· Remove and deliver FOB in Muñiz ANG Base located in Carolina PR, an existing dry type step down transformer according with federal and state regulations

3. Existing Concrete Slab

· Demolish, remove and properly dispose according with Federal and state regulations approximately 2250 SF of concrete floor slab and walls on the Radome Tower and surrounding areas as per construction drawings and specifications.

· Provide and install 4 inches of top soil to cover all excavation and disturbed areas resulting from the project activities.

· Provide and apply seeding treatment to match existing surrounding grass.

· Clean all affected areas and properly dispose of debris.

4. Closeout Documentation

· Contractor will submit to Contracting Officer one binder as per project specifications.

5. Annex 1: LBP Abatement

· Refer to LBP Report and Drawings

c. Location: The Site of the work covered by these specifications is, PRANG 140/ADS Punta Salinas Radar Site in Toa Baja P.R.

d. Special Instructions to Contractor;

· For additional information on drawings and specifications contact the Base Civil Engineer Office at Muñíz ANG Base (787) 253-5172 Telephone, (787) 253-5226/7415 Fax.

· All contracting issues will be directed to the Base Contracting Officer at Muñíz ANG Base (787) 253-5238 Telephone.

· All coordination for entering Punta Salinas Site premises will be made with MSgt Soto or TSgt Gonzalez-Quijano at (787) 795-8370.

· Contractors must be registered (current) in the Central Contractor Registration (CCR) internet program at: http://www.ccr.gov

· All invoices will be submitted using Wide Area Workflow (WAWF) internet program at: https://wawf.eb.mil

· All personnel are required to show a valid not expired ID in the main entrance gate before entering the Base premises.

· Before commencing the project, fill out the official BASE access request form with the information of all employees and vehicles directly involved in the project.

· All personnel are required to show a valid not expired ID in the main entrance gate before entering the Base premises.

· To obtain Base temporary entry authorization badges is required to present a valid police record verification for all employees that will work in this project.

· Only company cars with distinctive logos posted at passenger and driver doors will be authorized inside BASE premises.

· At the end of each working day all areas will be clear from equipment, tools and materials.

· Every day all garbage and remaining materials related to the work will be taken to a garbage can provided by contractor.

· Special precautions will be taken at no cost to government to protect base property during the project execution.

· Use only assigned smoking areas.

· The use of any type of devices for recording images, movies or sounds is strictly prohibited while inside base premises without written authorization.

· The use of any type of military clothing is prohibited while inside base premises.

· The use of Personal Protective Equipment is mandatory at all time while working in the project.

· All removed materials and equipment unless otherwise indicated herein must be disposed at no cost to government in accordance with federal, local government and BASE regulations.

· Submit for approval the following construction materials to BCE office;

1) Disposal procedures and agreements including truck manifests

2) Safety plan to include Personal Protective Equipment monitoring system

3) Credentials for LBP abatement from certified contractor

4) LBP Abatement Plan

5) Landfill proof of disposition papers

6) Recycling manifest

7) Electrical conduits & wiring

8) Certificates of no debts to suppliers or vendors

9) Breakdown for Payment

10) Project Schedule of activities

Other files for this federal contract opportunity

Other files attached to Demolish Radome Tower # 4, newest first.
File Type Posted
ModR0011.pdf PDF
METER-ROOF-CHILLER-TOWER.pdf PDF
NewTDrawings —
LBP Report —
pd215.pdf PDF
pd215.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .