LEAD BASED PAINT INSPECTION REPORT

FOR

PUERTO RICO AIR NATIONAL GUARD

SAMPLING CONDUCTED AT

PUNTA SALINAS RADAR SITE,

TOWER IV

TOA BAJA, PR

MARCH, 2010

PREPARED BY:

ZIMMETRY ENVIRONMENTAL MANAGEMENT CORP.

PO BOX 3545 BAYAMÓN, PR 00958

PHONE: 787.376.9010 FAX: 787.995.0005 �

ZIMMETRY ENVIRONMENTAL MANAGEMENT CORP.

Lead Based Paint Inspection Punta Salinas Radar Site, Tower IV Toa Baja, PR

TABLE OF CONTENT

SECTION 1: Executive Summary

1.1 Introduction

1.2 Summary of Property Evaluation

1.3 Summary of Lead Based Paint

1.4 Property Locations of Building Components with Lead Based Paint Table 1-1 Summary of Building Components with Lead Based Paint SECTION 2: LEAD-BASED PAINT INSPECTION REPORT Summary

2.1 Overview of the Evaluation Summary

2.2 Sampling Procedure and Results Presentation

2.3 Lead Regulatory Levels

2.4 Conditions and Limitations

2.5 Abatement Conditions

2.6 Recommendations

2.7 Environmental Assessment Report Certification

SECTION 3: APPENDICES

Appendix A: XRF Sampling Data Appendix B: Location of Positive Materials Appendix C: Project Photographs Appendix D: Certifications, Licenses, and Accreditations

ZIMMETRY ENVIRONMENTAL MANAGEMENT CORP.

Lead Based Paint Inspection Punta Salinas Radar Site, Tower IV Toa Baja, PR

SECTION 1: EXECUTIVE SUMMARY

1.1 INTRODUCTION

A Lead-Based Paint inspection was conducted on March 5, 2010 at the Tower IV located at Punta Salinas Radar Site in Toa Baja, PR. The lead-based paint inspection was performed to identify paint that contains lead above allowable levels that could result in harm to construction personnel, workers and especially to young children. This evaluation report can help Owners develop a plan for eliminating any lead-based paint hazards that were found, and may aid in establishing an ongoing lead-based paint maintenance and re-evaluation program, if needed.

1.2 SUMMARY OF PROPERTY EVALUATION

The project consisted of the evaluation on the interior and exterior areas of the Tower IV.

The evaluation found that lead-based paint was present in concrete surfaces, ceramic and metal component through the evaluated areas on the date of the inspection Table 1-1 identifies the components positive for lead.

1.3 SUMMARY OF LEAD-BASED PAINT

Table 2-1 identifies lead-based paint as defined by the U.S. Environmental Protection Agency (EPA) and the Environmental Quality Board (EQB). For specific locations and additional detail on the location of lead-based paint reference Sections 2 and 3.

1.4 PROPERTY LOCATIONS OF BUILDING COMPONENTS WITH LEADBASED

PAINT

Table 1-1 summarizes the side components coated with lead-based paint. Details that identify positive lead-based paint findings within specific areas and on surfaces were provided in the Lead-based paint inspection report. The “substrate” is the building component material directly beneath the painted surface.

ZIMMETRY ENVIRONMENTAL MANAGEMENT CORP.

Lead Based Paint Inspection Punta Salinas Radar Site, Tower IV Toa Baja, PR Note: The quantification of positives materials presented in this table is only an estimate. If an abatement of the materials will be conducted the Contractors shall calculate their own quantification of the materials to be abated.

Table 1-1: Summary of Components with Lead Based Paint Area Component Color Substrate Area / Amount (Approx.)

BETWEEN 1ST &

2ND AND 2ND & 3RD

STAIRCASES

(RISERS) Yellow Metal 2 Staircases Units AREA 1-1 SINK White Metal 1 Unit AREAS 1-2 & 1-3 WALL TILES Cream Ceramic 408 Ft2 AREA 1-3 LAVATORY White Ceramic 1 Unit

EXTERIOR

STAIRCASE

(STRINGERS, RISERS

& STAIRCASE BASE)

Yellow Concrete 60 Ft2 �

ZIMMETRY ENVIRONMENTAL MANAGEMENT CORP.

Lead Based Paint Inspection Punta Salinas Radar Site, Tower IV Toa Baja, PR

SECTION 2: LEAD-BASED PAINT INSPECTION REPORT

2.1 OVERVIEW OF THE EVALUATION

This lead-based paint inspection is an interior and exterior investigation to identify all leadbased paint on a surface-by-surface basis. A lead-based paint inspection conforming to HUD guidelines was performed at the structures.

Averages of 141 samples were taken at all identified surfaces on the inside and outside of the evaluated structure using X-ray fluorescence (XRF) analyzer. The evaluation found that leadbased paint was present in concrete surfaces ceramic & metal components through the evaluated structures on the date of the assessment (See Table 1-1) Some of the remaining XRF test locations exhibited lead-in-paint levels below the level that EPA identifies as lead-based paint, namely 1.0 mg/cm2. Such surfaces could create dust-lead or soil-lead hazards if the paint is turned into dust by abrasion, scraping, or sanding. Should these or any lead containing components or surfaces be disturbed in any manner that generates dust, care should be taken to limit its spread.

Testing was performed by Alfredo J. Pérez, state-certified inspector 8293-0409-LI-004, and Harry Peña, state-certified risk assessor 3357-1209-RA-0034, using the Niton XLp-300A XRF, SN-18574. The credentials are provided in Section 3, Appendix D: Certifications, Licenses, and Accreditations. The XRF analyzer is designed to measure the lead content of surface coatings on a variety of building surfaces, substrates, and components. The measurement is rapid and nondestructive and, according to the manufacturer, is capable of detecting lead concentrations that occur within numerous layers of various surface coatings.

Please refer to the XRF Testing Results Section 3, Appendix A: XRF Sampling Data for the detailed analytical testing results for each distinct area inspected. The reports provide a complete testing data.

2.2 SAMPLING PROCEDURE AND RESULTS PRESENTATION

The Lead Based Paint Sampling Procedure was design to evaluate and document all the data obtained form the inspection in a sequential method that provided confidence at the moment of the results presentation.

The survey was performed following the methodology established in the HUD Guidelines for the Evaluation and Control of Lead Based Paint in Housing (1997 revision) and the PREQB Lead Based Paint Abatement Control Regulation. The surfaces evaluation was performed as follows:

• If the lead concentration measured by the XRF Spectrum Analyzer is less than 1.0 mg/cm2 it is considered negative

• If the lead concentration measured by the XRF Spectrum Analyzer is equal or greater than 1.0 mg/cm2 it is considered positive. �

ZIMMETRY ENVIRONMENTAL MANAGEMENT CORP.

Lead Based Paint Inspection Punta Salinas Radar Site, Tower IV Toa Baja, PR To each functional space of the property a name was assigned according to the use of that space. If no name could be assigned then a code letter or number was assigned. The room numbers will be assigned clockwise as you enter the structure and go towards the left always.

Each wall surface was named with letters beginning with wall A the wall facing the main street or building main entrance. The wall at your left will be wall B, the wall at front wall C and the wall at you right will be wall D.

2.3 LEAD REGULATORY LEVELS

The lead regulatory levels provided below are those used when preparing this lead-based paint evaluation or when evaluating data collected. The EPA regulatory levels are the same as the state regulatory levels provided in the following table.

TABLE 2-1: LEAD REGULATORY LEVELS

EPA/EQB Levels Lead-Based Paint 1.0 mg/cm2 or 0.5% by weight (or 5,000 ppm) Lead in Dust Floor 40 µg/ft2 Window Sill 250 µg/ft2 Lead in Bare Soil Child-Play Areas (dwelling perimeter and yard) 400 ppm (µg/g) Rest of the Yard(dwelling perimeter and yard) 1200 ppm (µg/g)

2.4 CONDITIONS AND LIMITATIONS—DISCLAIMER

Zimmetry Environmental Management Corp. has performed this lead-based paint inspection in a thorough and professional manner consistent with commonly accepted industry standards. The Preparer cannot guarantee and does not warrant that this evaluation has identified all adverse environmental factors and/or conditions affecting this property on the date of the evaluation.

The results reported and conclusions reached by the Preparer are solely for the benefit of the Owner. The results and opinions in this report, based solely on the conditions found at the property on the date of the evaluation, are valid only on that date. The Preparer assumes no obligation to advise the client of any changes in any real or potential lead-based paint hazards at this residence beyond the date of the property evaluation.

The lead inspection was performed to ready accessible components and surfaces. If ceramic tiles or suspected components that could contain lead are encountered underneath current installed tiles or other construction material, they shall be managed as containing lead until the appropriate test is performed. Due to site conditions if possible that several areas could not be �

ZIMMETRY ENVIRONMENTAL MANAGEMENT CORP.

Lead Based Paint Inspection Punta Salinas Radar Site, Tower IV Toa Baja, PR evaluated. If suspected materials are identified they shall be managed as containing asbestos until the appropriated test is performed.

2.5 ABATEMENT CONDITIONS

Abatement, as defined by HUD and the Puerto Rico Environmental Quality Board (EQB), means any set of measures designed to eliminate lead-based paint and/or lead-based paint hazards permanently. The people providing these services must to be trained in accordance with the EQB licensing/certification requirements. The product manufacturer and/or contractor must warrant abatement methods to last a minimum of 20 years, or these methods must have a design life of at least 20 years.

Abatement activities may include, but are not necessarily limited to: the onsite or offsite removal of lead-based paint from substrates and components; the replacement of components or fixtures painted with lead-based paint; the permanent enclosure of lead-based paint with construction materials mechanically-fastened to the substrate; the encapsulation of leadbased paint with specially designed encapsulant products; or the removal or permanent covering (concrete or asphalt) of soil-lead-based paint hazards. If enclosure or encapsulation is conducted as an abatement method, the lead-based paint remains on the property, so ongoing lead-based paint maintenance is required.

2.6 RECOMMENDATIONS

According to the EQB lead regulations, prior to the demolishing of a structure containing lead based paint, the contaminated surfaces or substrates must be abated or removed. The waste generated has to be characterized to determine if the waste generated is hazardous or non hazardous waste. The firm providing the abatement services must be certified as an abatement firm by the EQB. Workers conducting abatement must be trained and certified as abatement workers by a training provider accredited by the EQB.

2.8 ENVIRONMENTAL ASSESSMENT REPORT CERTIFICATION

Zimmetry Environmental Management Corp. has performed this lead-based paint inspection in a thorough and professional manner consistent with commonly accepted industry standards. The inspection was conducted on March 5, 2010 Alfredo J. Pérez, state-certified inspector 8293-0409-LI-004, and Harry Peña, state-certified risk assessor 3357-1209-RA- 003, qualified by experience, education and training in the recognition of lead based paint and approved sampling techniques using the Niton XLp-300A XRF, SN-18574.

Harry Peña Ruiz, Ms, C.E. I Environmental Building Inspector

ZIMMETRY ENVIRONMENTAL MANAGEMENT CORP.

Lead Based Paint Inspection Punta Salinas Radar Site, Tower IV Toa Baja, PR

SECTION 3: APPENDICES

Appendix A: XRF Sampling Data Appendix B: Location of Positive Materials Appendix C: Project Photographs Appendix D: Certifications, Licenses, and Accreditations

ZIMMETRY ENVIRONMENTAL MANAGEMENT CORP.

Lead Based Paint Inspection Punta Salinas Radar Site, Tower IV Toa Baja, PR

APPENDIX A: XRF SAMPLING DATA

PROJECT: Punta Salinas Radar Site, Tower IV DATE: 3/5/2010 LBP Inspector: Page 1 of 4 Sample ID. Functional Space Location Color Subst. XRF Reading Pos/Neg Comments 1 Calibration 1.00 2 Calibration 1.00 3 Calibration 1.00 4 Area 1-1 Wall A White Wood 0.00 Negative 5 Area 1-1 Wall A White Drywall 0.00 Negative 6 Area 1-1 Wall B White Drywall 0.00 Negative 7 Area 1-1 Wall C White Drywall 0.00 Negative 8 Area 1-1 Wall D White Drywall 0.00 Negative 9 Area 1-1 Column White Metal 0.23 Negative 10 Area 1-1 Ceiling Gray Metal 0.18 Negative 11 Area 1-1 Beam Gray Metal 0.25 Negative 12 Area 1-1 Beam Gray Metal 0.16 Negative 13 Area 1-1 Wall A Gray Metal 0.01 Negative 14 Area 1-1 Ceiling Tile Railing White Metal 0.01 Negative 15 Area 1-1 Column White Metal 0.00 Negative 16 Area 1-1 Stairway Gray Metal 0.00 Negative 17 Area 1-1 Stairway Riser Yellow Metal 2.30 Positive 18 Area 1-1 Handrail Gray Metal 0.00 Negative 19 Area 1-1 Sink White Metal 12.00 Positive 20 Area 1-2 Door Casing White Metal 0.00 Negative 21 Area 1-2 Wall Tile Cream Ceramic 2.20 Positive 22 Area 1-2 Floor Tile Brown Ceramic 0.01 Negative 23 Area 1-2 Wall A White Drywall 0.00 Negative 24 Area 1-2 Wall B White Drywall 0.00 Negative 25 Area 1-2 Wall C White Drywall 0.00 Negative 26 Area 1-2 Wall D White Drywall 0.00 Negative 27 Area 1-2 Column White Metal 0.26 Negative 28 Area 1-2 Toilet White Ceramic 0.00 Negative 29 Area 1-2 Lavatory White Ceramic 0.00 Negative 30 Area 1-3 Door Casing White Metal 0.00 Negative 31 Area 1-3 Wall A White Drywall 0.00 Negative 32 Area 1-3 Wall B White Drywall 0.00 Negative 33 Area 1-3 Wall C White Drywall 0.00 Negative 34 Area 1-3 Wall D White Drywall 0.00 Negative 35 Area 1-3 Wall Tile Cream Ceramic 2.10 Positive 36 Area 1-3 Floor Tile Brown Ceramic 0.00 Negative 37 Area 1-3 Lavatory White Ceramic 20.00 Positive 38 Area 1-3 Toilet White Ceramic 0.00 Negative 39 Area 1-3 Urinal White Ceramic 0.00 Negative 40 Area 1-4 Wall A White Drywall 0.00 Negative 41 Area 1-4 Wall B White Drywall 0.00 Negative 42 Area 1-4 Wall C White Drywall 0.00 Negative 43 Area 1-4 Wall D White Drywall 0.00 Negative 44 Area 1-5 Door Casing White Metal 0.00 Negative 45 Area 1-5 Wall A White Drywall 0.00 Negative 46 Area 1-5 Wall B White Drywall 0.00 Negative 47 Area 1-5 Wall C White Drywall 0.00 Negative 48 Area 1-5 Wall D White Drywall 0.00 Negative 49 Area 1-5 Ceiling Gray Wood 0.03 Negative 50 Area 1-5 Ceiling Gray Metal 0.00 Negative 51 Area 1-5 Beam Gray Metal 0.28 Negative 52 Area 1-5 Column White Metal 0.12 Negative 53 Area 1-6 Wall A White Drywall 0.00 Negative 54 Area 1-6 Wall C White Drywall 0.00 Negative 55 Area 1-6 Wall D White Drywall 0.00 Negative 56 Area 1-6 Wall B Gray Wood 0.00 Negative 57 Area 1-6 Wall B Gray Metal 0.01 Negative 58 Area 1-6 Ceiling Gray Metal 0.00 Negative 59 Area 1-6 Beam Gray Metal 0.00 Negative 60 Area 1-6 Beam Gray Metal 0.00 Negative

CLIENT: PRANG

Harry Peña� PROJECT: Punta Salinas Radar Site, Tower IV DATE: 3/5/2010 LBP Inspector: Page 2 of 4 Sample ID. Functional Space Location Color Subst. XRF Reading Pos/Neg Comments 61 Area 1-6 Support Gray Metal 0.08 Negative 62 Area 1-7 Wall A White Drywall 0.00 Negative 63 Area 1-7 Wall B White Drywall 0.00 Negative 64 Area 1-7 Wall C White Drywall 0.00 Negative 65 Area 1-7 Wall D White Drywall 0.00 Negative 66 Area 1-7 Column White Metal 0.26 Negative 67 Area 1-7 Wall C Gray Metal 0.01 Negative 68 Area 1-7 Ceiling Gray Wood 0.01 Negative 69 Area 1-8 Door Casing White Metal 0.00 Negative 70 Area 1-8 Wall A White Drywall 0.00 Negative 71 Area 1-8 Wall B White Drywall 0.00 Negative 72 Area 1-8 Wall C White Drywall 0.00 Negative 73 Area 1-8 Wall D White Drywall 0.00 Negative 74 Area 1-8 Ceiling Gray Metal 0.24 Negative 75 Area 1-8 Beam Gray Metal 0.03 Negative 76 Area 1-8 Column White Metal 0.17 Negative 77 Area 1-9 Door Casing White Metal 0.00 Negative 78 Area 1-9 Wall A White Drywall 0.00 Negative 79 Area 1-9 Wall B White Drywall 0.00 Negative 80 Area 1-9 Wall C White Drywall 0.00 Negative 81 Area 1-9 Wall D White Drywall 0.00 Negative 82 Area 1-9 Column Cream Metal 0.06 Negative 83 Area 1-10 Door White Metal 0.00 Negative 84 Area 1-10 Door Casing White Metal 0.00 Negative 85 Area 1-10 Wall A White Drywall 0.00 Negative 86 Area 1-10 Wall B White Drywall 0.00 Negative 87 Area 1-10 Wall D Gray Metal 0.00 Negative 88 Area 1-10 Support Beam Gray Metal 0.00 Negative 89 Area 1-10 Electrical Panel Red Metal 0.70 Negative 90 Area 2-1 Door White Metal 0.00 Negative 91 Area 2-1 Door Casing White Metal 0.00 Negative 92 Area 2-1 Wall A Gray Metal 0.00 Negative 93 Area 2-1 Column Gray Metal 0.21 Negative 94 Area 2-1 Support Gray Metal 0.16 Negative 95 Area 2-1 Wall A Gray Metal 0.00 Negative 96 Area 2-1 Column Red Metal 0.12 Negative 97 Area 2-1 Column Gray Metal 0.14 Negative 98 Area 2-1 Floor Gray Metal 0.03 Negative 99 Area 2-1 Floor Orange Metal 0.30 Negative 100 Area 2-1 Wall B White Drywall 0.01 Negative 101 Area 2-1 Wall D Gray Metal 0.10 Negative 102 Area 2-1 Column Gray Metal 0.11 Negative 103 Area 2-1 Beam Support Gray Metal 0.21 Negative 104 Area 2-1 Vertical Ladder Gray Metal 0.14 Negative 105 Area 2-1 Handrail Gray Metal 0.16 Negative 106 Area 2-1 Riser Yellow Metal 1.20 Positive 107 Area 2-1 Cage Gray Metal 0.16 Negative 108 Area 2-2 Door Casing White Metal 0.00 Negative 109 Area 2-2 Wall A White Drywall 0.00 Negative 110 Area 2-2 Wall B White Drywall 0.00 Negative 111 Area 2-2 Wall C White Drywall 0.00 Negative 112 Area 2-2 Wall D White Drywall 0.00 Negative 113 Area 2-2 Column White Metal 0.16 Negative 114 Area 2-2 Floor Gray Metal 0.00 Negative 115 Area 2-3 Wall A White Drywall 0.00 Negative 116 Area 2-3 Wall B White Drywall 0.00 Negative 117 Area 2-3 Wall C White Drywall 0.00 Negative 118 Area 2-3 Wall D White Drywall 0.00 Negative 119 Area 3-1 Floor Gray Metal 0.00 Negative 120 Area 3-1 Crane Gray Metal 0.02 Negative

CLIENT: PRANG

Harry Peña� PROJECT: Punta Salinas Radar Site, Tower IV DATE: 3/5/2010 LBP Inspector: Page 3 of 4 Sample ID. Functional Space Location Color Subst. XRF Reading Pos/Neg Comments 61 Area 1-6 Support Gray Metal 0.08 Negative 62 Area 1-7 Wall A White Drywall 0.00 Negative 63 Area 1-7 Wall B White Drywall 0.00 Negative 64 Area 1-7 Wall C White Drywall 0.00 Negative 65 Area 1-7 Wall D White Drywall 0.00 Negative 66 Area 1-7 Column White Metal 0.26 Negative 67 Area 1-7 Wall C Gray Metal 0.01 Negative 68 Area 1-7 Ceiling Gray Wood 0.01 Negative 69 Area 1-8 Door Casing White Metal 0.00 Negative 70 Area 1-8 Wall A White Drywall 0.00 Negative 71 Area 1-8 Wall B White Drywall 0.00 Negative 72 Area 1-8 Wall C White Drywall 0.00 Negative 73 Area 1-8 Wall D White Drywall 0.00 Negative 74 Area 1-8 Ceiling Gray Metal 0.24 Negative 75 Area 1-8 Beam Gray Metal 0.03 Negative 76 Area 1-8 Column White Metal 0.17 Negative 77 Area 1-9 Door Casing White Metal 0.00 Negative 78 Area 1-9 Wall A White Drywall 0.00 Negative 79 Area 1-9 Wall B White Drywall 0.00 Negative 80 Area 1-9 Wall C White Drywall 0.00 Negative 81 Area 1-9 Wall D White Drywall 0.00 Negative 82 Area 1-9 Column Cream Metal 0.06 Negative 83 Area 1-10 Door White Metal 0.00 Negative 84 Area 1-10 Door Casing White Metal 0.00 Negative 85 Area 1-10 Wall A White Drywall 0.00 Negative 86 Area 1-10 Wall B White Drywall 0.00 Negative 87 Area 1-10 Wall D Gray Metal 0.00 Negative 88 Area 1-10 Support Beam Gray Metal 0.00 Negative 89 Area 1-10 Electrical Panel Red Metal 0.70 Negative 90 Area 2-1 Door White Metal 0.00 Negative 91 Area 2-1 Door Casing White Metal 0.00 Negative 92 Area 2-1 Wall A Gray Metal 0.00 Negative 93 Area 2-1 Column Gray Metal 0.21 Negative 94 Area 2-1 Support Gray Metal 0.16 Negative 95 Area 2-1 Wall A Gray Metal 0.00 Negative 96 Area 2-1 Column Red Metal 0.12 Negative 97 Area 2-1 Column Gray Metal 0.14 Negative 98 Area 2-1 Floor Gray Metal 0.03 Negative 99 Area 2-1 Floor Orange Metal 0.30 Negative 100 Area 2-1 Wall B White Drywall 0.01 Negative 101 Area 2-1 Wall D Gray Metal 0.10 Negative 102 Area 2-1 Column Gray Metal 0.11 Negative 103 Area 2-1 Beam Support Gray Metal 0.21 Negative 104 Area 2-1 Vertical Ladder Gray Metal 0.14 Negative 105 Area 2-1 Handrail Gray Metal 0.16 Negative 106 Area 2-1 Riser Yellow Metal 1.20 Positive 107 Area 2-1 Cage Gray Metal 0.16 Negative 108 Area 2-2 Door Casing White Metal 0.00 Negative 109 Area 2-2 Wall A White Drywall 0.00 Negative 110 Area 2-2 Wall B White Drywall 0.00 Negative 111 Area 2-2 Wall C White Drywall 0.00 Negative 112 Area 2-2 Wall D White Drywall 0.00 Negative 113 Area 2-2 Column White Metal 0.16 Negative 114 Area 2-2 Floor Gray Metal 0.00 Negative 115 Area 2-3 Wall A White Drywall 0.00 Negative 116 Area 2-3 Wall B White Drywall 0.00 Negative 117 Area 2-3 Wall C White Drywall 0.00 Negative 118 Area 2-3 Wall D White Drywall 0.00 Negative 119 Area 3-1 Floor Gray Metal 0.00 Negative 120 Area 3-1 Crane Gray Metal 0.02 Negative

CLIENT: PRANG

Harry Peña� PROJECT: Punta Salinas Radar Site, Tower IV DATE: 3/5/2010 LBP Inspector: Page 4 of 4 Sample ID. Functional Space Location Color Subst. XRF Reading Pos/Neg Comments 121 Area 3-1 Crane Gray Metal 0.30 Negative 122 Area 3-1 Wall A Brown Fiberboard 0.00 Negative 123 Area 3-1 Wall B Brown Fiberboard 0.00 Negative 124 Area 3-1 Wall C Brown Fiberboard 0.00 Negative 125 Area 3-1 Wall D Brown Fiberboard 0.00 Negative 126 Exterior Dome Wall A White Fiberboard 0.00 Negative 127 Exterior Dome Wall C White Fiberboard 0.00 Negative 128 Exterior Riser Yellow Concrete 2.00 Positive 129 Exterior Stringer Yellow Concrete 1.50 Positive 130 Exterior Staircase Base Yellow Concrete 14.80 Positive 131 Exterior Wall A Gray Metal 0.03 Negative 132 Exterior Wall A Gray Concrete 0.00 Negative 133 Exterior Wall B Gray Metal 0.00 Negative 134 Exterior Wall B Gray Concrete 0.00 Negative 135 Exterior Wall C Gray Metal 0.01 Negative 136 Exterior Wall C Gray Concrete 0.00 Negative 137 Exterior Wall D Gray Metal 0.00 Negative 138 Exterior Wall D Gray Concrete 0.03 Negative 139 Calibration 1.00 140 Calibration 1.00 141 Calibration 1.00 Harry Peña

CLIENT: PRANG�

ZIMMETRY ENVIRONMENTAL MANAGEMENT CORP.

Lead Containing Building Materials Inspection Punta Salinas Radar Site, Tower IV Toa Baja, PR

APPENDIX B: LOCATION OF POSITIVE MATERIALS �

ZIMMETRY ENVIRONMENTAL MANAGEMENT CORP.

Lead Based Paint Inspection Punta Salinas Radar Site, Tower IV Toa Baja, PR

APPENDIX C: PROJECT PHOTOGRAPHS

Between 1st & 2nd floors Lead-based painted metal risers Between 2nd & 3rd floors Lead-based painted metal risers Area 1-1 Lead-based painted metal sink Area 1-2 Lead containing ceramic wall tiles

ZIMMETRY ENVIRONMENTAL MANAGEMENT CORP.

Lead Based Paint Inspection Punta Salinas Radar Site, Tower IV Toa Baja, PR

APPENDIX C: PROJECT PHOTOGRAPHS

Area 1-3 Lead containing ceramic wall tiles Area 1-3 Lead containing ceramic lavatory Exterior Lead-based painted concrete staircase (stringers, risers & staircase base)

ZIMMETRY ENVIRONMENTAL MANAGEMENT CORP.

Lead Based Paint Inspection Punta Salinas Radar Site, Tower IV Toa Baja, PR

APPENDIX D: CERTIFICATIONS, LICENSES, AND

ACCREDITATIONS

ZIMMETRY ENVIRONMENTAL MANAGEMENT CORP.

Lead Based Paint Inspection Punta Salinas Radar Site, Tower IV Toa Baja, PR

APPENDIX D: CERTIFICATIONS, LICENSES, AND

ACCREDITATIONS

Other files for this federal contract opportunity

Other files attached to Demolish Radome Tower # 4, newest first.
File Type Posted
ModR0011.pdf PDF
METER-ROOF-CHILLER-TOWER.pdf PDF
NewTDrawings —
NewSOW DEMO RADOME Tower 4 —
pd215.pdf PDF
pd215.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .