Preproposal_minutes_W912L717B0004.pdf
PDF 17 KB Posted
- Attached to
- Add Alter Airfield Utilities Federal contract opportunity
- Solicitation number
- W912L7-17-B-0004
About this file
Pre-proposal minutes
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912L717B0004_Amendment_2.pdf | ||
| W912L717B0004_Amendment_1.pdf | ||
| Site_Visit_Slides_19_Jul_2017.pdf | ||
| 17B0004_Sign_in_Sheet.pdf | ||
| Plans.zip | ZIP file | |
| Specs.zip | ZIP file | |
| W912L717B0004_Final_5_Jul_2017.pdf | ||
| Wage_Decision_TN170148_6_Jan_2017_Hwy.pdf | ||
| Construction_PWS,_PSXE152014_ADAL_Airfield_Utilities.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TENNESSEE AIR NATIONAL GUARD
HEADQUARTERS 134TH AIR REFUELING WING
MCGHEE TYSON AIR NATIONAL GUARD BASE TENNESSEE
19 July 2017
MEMORANDUM FOR RECORD
SUBJECT: MINUTES OF PRE-PROPOSAL CONFERENCE AND SITE VISIT, SOLICITATION
W912L7-17-B-0004, Add Alter Airfield Utilities
Date: 19 July 2017, 0900 - 1015
1. The list of contractors attending the meeting is shown on the attached sign-in sheet. The following
Government representatives attended the subject meeting:
Name Position
CMSgt Richard Lusby 134 Contracting Office
Maj David Barrett 134 Civil Engineering
Lt Travis Vaughn 134 Civil Engineering
SSgt Lisa Maxwell 134 Contracting Office
2. The following items were discussed during the Pre-proposal Conference:
a. SSgt Maxwell provided an over view of the solicitation requirements to attendees. (Power
Point presentation attached)
b. SSgt Maxwell stressed the importance of question asked must be submitted in writing in order to be official.
c. Major Barrett discussed the scope of the project and specified that a transformer would have to be re-located.
3. Attendees visited the flight line, transformer location, and fire hydrant locations
4. Questions must be submitted in writing via email, especially technical questions to:
richard.m.lusby.mil@mail.mil. DO NOT CONTACT the Design Engineers or the Government Engineers.
All questions must be routed through the Contracting Office. All Contractor questions when answered will be posted to FedBiz Ops. If a question arises that will result in a change to the plans or specifications, an official amendment will be issued. All correspondence, questions and answers, amendments etc. will be issued via email.
5. Any amendments that are issued will posted to FedBiz Ops. Contractors were advised to check the website frequently.
6. The pre-proposal conference and site visit concluded at 1015 hours.
RICHARD M. LUSBY, TNANG
CONTRACTING OFFICER
Attachment