Q A_3.docx
DOCX document 12 KB Posted
- Attached to
- HEMTT Spill Containment System Federal contract opportunity
- Solicitation number
- W912K6-16-Q-0037
About this file
Questions and Answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Q A_Cont2.docx | DOCX document | |
| Q A_Cont.docx | DOCX document | |
| QUESTIONS_AND_ANSWERS_FOR_SOLICITATION_W912K6.docx | DOCX document | |
| HEMIT_Spill_Containment_FBO_solicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question and Answers:
Question: I am working on the quote for the containment pads and wanted to know if you have a snow load requirement for the structures covering the pads themselves? I understand the 85mph wind requirement and wanted to see if there was a snow load factor that should be considered with the design of the trusses for the shelters.
Answer: There is not a requirement for snow load factors in the canopy design.