Amendment 0002. Disregard the a designation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_Opening_Sign_In_Sheet.pdf | ||
| Bid_Opening_Abstract_Global_ASNT.pdf | ||
| W912JB-19-B-5008_Solicitation_Amendment_0004.pdf | ||
| W912JB-19-B-5008_Solicitation_Amendment_0005.pdf | ||
| W912JB-19-B-5008_Solicitation_Amendment_0003.pdf | ||
| Addendum_01_GASNT.pdf | ||
| 0303FP__Bsmnt_Flr.pdf | ||
| GLOBAL_ASNT_RFI'S_1_V2.pdf | ||
| Site_Visit_Minutes_Global.pdf | ||
| Sign_In_Sheet.pdf | ||
| W912JB-19-B-5008_Solicitation_Amendment_0001.pdf | ||
| Presolicitation_Notice2_Global_ASNT.pdf | ||
| Presolicitation_Notice_Global_ASNT.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
F1GT109126AW03
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
This Solicitation Update adds in Amendment 0002 that incorporates the most current Wage Determination - Mod 03, cleaned upped bid due dates in solicitation documents, and updates period of performance from 180 calendar days to 60 calendar days. The 180 calendar days w as entered in error. Official period of performance is 60 calendar days after Notice To Proceed is issued.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 16
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 23-Jul-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912JB19B5008
X 9B. DATED (SEE ITEM 11)
10-Jul-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
23-Jul-2019
CODE
127 MSC - FA6221
43200 MAPLE ST
BLDG 105, RM 16
SELFRIDGE ANGB MI 48045-5213
W912JB 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912JB19B5008
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The contractor period of performance end date has decreased by 120 days from 180 days to 60 days.
The required performance has changed from Project Title: Construct Global ASNT Platform at Selfridge Air National Guard Base, MichiganProject#: VGLZ 192031Location: Selfridge ANGB, MI (Harrison Township, MI - 48045)Period of Performance (POP): 180 Calendar Days1) Set-aside: 100% Small Business2) Small Business Size Standard: $36.5M3) NAICS Code: 236220 - General Construction Contractors4) Project Magnitude: Between $250,000.00 and $500,000.006) Prospective bidders are highly encouraged to attend a pre-bid conference to be conducted on 23 July 2019 at 10:00 AM ET. (See Solicitation for Access Requirements)Funds are presently available for this contract. Award will be made to the responsible bidder whose bid conforms to the invitation for bids and is most advantageous to the Government considering only price and price related factors. to Project Title:
Construct Global ASNT Platform at Selfridge Air National Guard Base, MichiganProject#: VGLZ 192031Location:
Selfridge ANGB, MI (Harrison Township, MI - 48045)Period of Performance (POP): 60 Calendar Days1) Set-aside: 100% Small Business2) Small Business Size Standard: $36.5M3) NAICS Code: 236220 - General Construction Contractors4) Project Magnitude: Between $250,000.00 and $500,000.006) Prospective bidders are highly encouraged to attend a pre-bid conference to be conducted on 23 July 2019 at 10:00 AM ET. (See Solicitation for Access Requirements)Funds are presently available for this contract. Award will be made to the responsible bidder whose bid conforms to the invitation for bids and is most advantageous to the Government considering only price and price related factors..
DELIVERIES AND PERFORMANCE
The following Delivery Schedule item for CLIN 0001 has been changed from:
DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
180 dys. ANP 1 127 CES
TODD RUPRIGHT
28900 SELFRIDGE AVE
BLDG 127
SELFRIDGE ANGB MI 48045-5223
586-239-4658 FOB: Destination
F8Y36P
To:
DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
60 dys. ANP 1 127 CES
TODD RUPRIGHT
28900 SELFRIDGE AVE
BLDG 127
SELFRIDGE ANGB MI 48045-5223
586-239-4658
The following Delivery Schedule item for CLIN 0002 has been changed from:
CAGE
180 dys. ANP 1 127 CES
TODD RUPRIGHT
28900 SELFRIDGE AVE
BLDG 127
SELFRIDGE ANGB MI 48045-5223
586-239-4658
To:
CAGE
60 dys. ANP 1 127 CES
TODD RUPRIGHT
28900 SELFRIDGE AVE
BLDG 127
SELFRIDGE ANGB MI 48045-5223
586-239-4658
SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS
The following have been modified:
INSTRUCTIONS TO BIDDERS
SECTION 00100 INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
1. Description of the Project: This project generally consists of installing a concrete pad, running electrical from bldg. 303 underground to pad, installing ANST platform, waterproofing bldg. 303 basement, and constructing fence around ANST location. Please refer to project drawings, details and specs, and Statement of Work (SOW) for further details on project.
2. Instructions to Bidders:
2.1. You are invited to submit a bid in response to our Invitation for Bids (IFB) entitled W912JB-19-B-5008 entitled Install Global ASNT Platform, Project Number VGLZ 192031, at Selfridge ANGB, MI.
2.2. As a result of this solicitation, the Government intends to award a Firm Fixed Price (FFP) contract resulting from this solicitation to the responsible bidder whose bid, conforming to the invitation for bids, will be most advantageous to the Government, considering only price.
2.3. This solicitation is set-aside 100% for small business concerns contractors under NAICS 237110 which has a size standard of $36.5M.
2.4. Facsimile transmission of a bid is not authorized. Electronic submission of bids will not be accepted.
Bids must be hand carried to the bid opening or mailed.
2.5. A formatted disk (CD) shall be submitted with your bid that includes all those things required in the bid submission. The Formatted disk shall be labeled
-Solicitation # (W912JB-19-B-5008) -Name / Company Name and Address of Bidder
3. NOTICE OF PRE-BID CONFERENCE AND SITE VISIT:
3.1. A pre-bid conference will be conducted on Tuesday, 23 July 2019 at 10:00am ET for the purposes of briefing on the bid requirements and answering questions regarding this solicitation. This conference will be held at 43200 Maple Street, Bldg 105, Room 20, Selfridge ANGB, MI 48045 (Contracting- Conference Room). Interested Contractors are highly encouraged to attend the pre-bid conference. The site visit will be held following the conference.
3.2. Due to security conditions, all offerors must register to attend this conference and site visit. Email the following information for all attendees to David Brown and Steven Stocking at the following addresses:
david.a.brown202.civ@mail.mil and steven.a.stocking3.mil@mail.mil. You may call us at (586) 239-5867/4881 with questions/concerns.
Firm/Company Name and Telephone Number Visitor’s Full Name and Last 4 of Social Security #.
Driver’s License # / State Issued Date of Birth Gender Race Citizenship
3.3. This information must be provided in advance, 3 business days prior to the meeting, in order to ensure access to the military base and conference site and ensure adequate seating for the conference attendees. Even if you have access to the base you must register to ensure adequate seating. The furnishing of the above information is voluntary; however, your failure to furnish all or part of the requested information may result in the Government’s denial of your access to the pre-proposal conference. This information will be provided to the Base Security Forces who will authorize your entrance to the site.
3.4. Visitors must pick up their passes at the Installation’s Main Entry Gate (M-59 / Rosso Hwy Road Gate) prior to arrival. You will be required to present the following information upon arrival: (1) Vehicle Registration,
(2) Valid Drivers License, (3) Proof of Insurance for Vehicle, (4) Safety Inspection and Car Rental agreement if applicable.(5) for those who have not received a pass in the past year, may be required to show either a social security card, tax ID number, or certificate of naturalization at the time of issue. Any of the above information furnished by you is protected under the Privacy Act and shall not be released unless permitted by law and/or you have consented to such.
3.5. Information provided at this conference or site visit shall not qualify the terms and conditions of the solicitation and specifications. Terms of the solicitation and specifications remain unchanged unless the solicitation is amended in writing. If an amendment is issued, normal procedures relating to the acknowledgment and receipt of solicitation amendments shall apply. All amendments will be posted to FBO.gov, and it should be noted that local ‘plan rooms’ do NOT typically distribute amendments in a timely manner. Please always refer to FBO.gov.
3.6. A record of the conference shall be made and furnished to all prospective bidders via posting at FBO.gov.
The record will include minutes of the meeting, including questions (on a non-attribution basis) and answers.
4. FORMAL COMMUNICATION, OFFEROR EXPLANATIONS:
4.1. Submit all questions in the format shown below by email to the contracting office at the addresses show below. Do NOT contact AE or Engineering personnel directly. Doing so will only delay your answer. All questions must come through the Contracting Office.
Subject Line: Reference No. SOLICITATION W912JB-19-B-5008 Email: Contracting Officer Steven A. Stocking – steven.a.stocking3.mil@mail.mil and Contract Specialist David Brown – david.a.brown202.civ@mail.mil
PRE-BID INQUIRY FORMAT
Date of Bid Inquiry: _______________
From: ______________________________ Company Name: ________________________________
Address:_____________________________________________________________________________
Phone Number: _____________________________ Fax Number:______________________________
Email address: ________________________________________________________________________
Bid Inquiry: (Please clearly state your question) (If sent via an attachment word docs are preferred to facilitate posting of answers to the master Q&A document.)
4.1. Any explanation desired by an offeror regarding the meaning or interpretation of the solicitation, or proposals, drawings, specifications, etc. must be requested in writing and with sufficient time allowed for a reply to reach bidders before the submission of their bid.
4.2. All questions and requests for information (RFI) must be received NOT LATER THAN the fifth working day prior to bid opening. OFFERORS ARE STRONGLY ENCOURAGED TO SUBMIT QUESTIONS
EARLY IN THIS PROCESS.
4.3. Any changes to the drawings, specifications, etc. will be issued in the form of an amendment.
However, any answers that clarify or provide an interpretation to the drawings, specifications, etc. will NOT be posted via amendment but rather as a response to the RFI on FBO at http://www.fbo.gov
4.4. Receipt by the offeror must be acknowledged in the space provided on the SF 1442 or by returning a signed copy of the amendment by the time set for receipt of bids.
4.5. For security reasons, all technical and engineering data related to this solicitation will be distributed using the Federal Business Opportunities (FedBizOpps.gov or fbo.gov) system. Plans and specifications are locked on FBO and require Contractors to request explicit access from the Contracting Officer OR export controlled access through DLA. See complete instructions on FBO. FedBizOpps is a web-based dissemination tool designed to safeguard acquisition-related information for all Federal agencies. Interested bidders/offerors must register with FedBizOpps before accessing the system.
4.5.1. Amendments, if/when issued will be posted to FBO.gov for electronic downloading. This will normally be the only method of distributing amendments prior to closing; therefore, it is the offerors responsibility to check the website periodically for any amendments to the solicitation. Websites are occasionally inaccessible due to various reasons.
5. BID REPOSITORY AND BID OPENING:
5.1. A bid repository is provided for hand carried bids and is located at 43200 Maple Street, Bldg 105, Contracting Front Office (Directly across from Room 20), Selfridge ANGB, MI 48045. Hand carried bids must be deposited in the repository prior to the time established for opening of bids. Bidders are cautioned that they will be required to sign-in and obtain a visitor’s pass to enter the facility and should allow time to accomplish this. See instructions to obtain access to the base in the Site Visit instruction. Follow the same instruction for obtaining entry to hand carry bid. Late receipt of bids due to entry delays may not be deemed excusable and the Contracting Officer may declare the bid “late” in accordance with FAR 14.304.
5.2. The bid opening will occur at the time and date specified in Block 13 of the SF1442 15 August 2019 at
2:00pm EST. All interested offerors and their major subcontractors are encouraged to attend the bid opening.
www.time.gov will be referenced for Eastern Time at the bid repository location.
6. WAGE DETERMINATION:
6.1. Construction Wage Rates are applicable to this project are MI20190091 07/05/2019 as shown in Section
00800.
7. BID PREPARATION EXPENSES AND PRE-CONTRACT COSTS: This IFB does not commit the Government to pay costs incurred in preparation and submission of bids or for other costs incurred prior to award of a formal contract.
8. CLAUSES:
8.1. Clauses and provisions from the Federal Acquisition Regulation (FAR) and supplements thereto are incorporated in this document by reference and in full text. Those incorporated by reference have the same force and effect as if they were given in full text.
9. DISPOSITION OF UNSUCCESSFUL BIDS:
In compliance with FAR Subpart 4.8, the Government will retain one copy of all unsuccessful bids including the bid bond.
10. OFFERORS QUALIFICATIONS:
To establish its responsibility, the apparent low bidder may be requested by the Government prior to award, to submit a statement regarding his previous experience in performing comparable work, his business and technical organization, financial and bonding resources and plant available to be used in performing the work. This action may be requested to determine if the contractor is responsible.
11. BRAND NAME JUSTIFICATION: N/A
Summary:
This project generally consists of installing a reinforced concrete pad that can resist Michigan winters with no frost heaves, a parameter fence, a metal platform on top of the cement pad for mounting of Glabal ASNT, and underground wiring and conduit into building 303. Concrete pad is to be sized per supplied specs and drawings to accommodate a Global ASNT system.
SECTION 00700 - CONTRACT CLAUSES
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 30 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 60 calendar days from the notice to proceed. The time stated for completion shall include final cleanup of the premises.
(End of clause)
SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS
WAGE DETERMINATION
"General Decision Number: MI20190091 07/05/2019
Superseded General Decision Number: MI20180091
State: Michigan
Construction Type: Building
County: Macomb County in Michigan.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.60 for calendar year 2019 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.60 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2019. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/04/2019 1 01/18/2019 2 02/15/2019 3 07/05/2019
ASBE0025-002 06/01/2018
Rates Fringes
ASBESTOS WORKER/HEAT & FROST
INSULATOR........................$ 31.58 32.32
BOIL0169-001 03/01/2018
Rates Fringes
BOILERMAKER......................$ 38.65 26.22
BRMI0001-001 06/01/2018
Rates Fringes
BRICKLAYER.......................$ 34.18 21.22
TILE FINISHER....................$ 27.94 19.12
TILE SETTER......................$ 34.66 19.12
CARP0687-003 06/01/2018
Rates Fringes
CARPENTER (Including Acoustical Ceiling Installation, Drywall Hanging, Form Work, Metal Stud Installation & Scaffold Building)........................$ 32.00 27.82
CARP1045-001 06/01/2018
Rates Fringes
CARPENTER (Floor Layer - Carpet, Resilient, & Vinyl Flooring)........................$ 28.60 23.88
CARP1102-002 06/01/2018
Rates Fringes
MILLWRIGHT.......................$ 33.65 32.25
ELEC0058-001 07/01/2018
Rates Fringes
ELECTRICIAN (Low Voltage Wiring and Installation of Alarms) Installer...................$ 24.25 12.38 Technician..................$ 35.01 14.08
ELECTRICIAN......................$ 38.73 23.85
ELEV0036-002 01/01/2019
Rates Fringes
ELEVATOR MECHANIC................$ 51.96 33.705
* ENGI0324-017 06/01/2019
Rates Fringes
OPERATOR: Power Equipment
GROUP 1....................$ 41.89 24.45
GROUP 2....................$ 40.39 24.45
GROUP 3....................$ 38.89 24.45
GROUP 4....................$ 38.59 24.45
GROUP 5....................$ 37.77 24.45
GROUP 6....................$ 36.91 24.45
GROUP 7....................$ 35.94 24.45
GROUP 8....................$ 34.23 24.45
GROUP 9....................$ 25.89 24.45
FOOTNOTES:
Tower cranes: to be paid the crane operator rate determined by the combined length of the mast and the boom. If the worker must climb 50 ft. or more to the work station, $.25 per hour additional.
Derrick and cranes where the operator must climb 50 ft. or more to the work station, $.25 per hour additional to the applicable crane operator rate.
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Crane with boom and jib or leads 400' or longer
GROUP 2: Crane with boom and jib or leads 300' or longer
GROUP 3: Crane with boom and jib or leads 220' or longer
GROUP 4: Crane with boom and jib or leads 140' or longer
GROUP 5: Crane with boom and jib or leads 120' or longer
GROUP 6: Regular crane operator, and concrete pump with boom operator
GROUP 7: Backhoe/Excavator/Trackhoe, bobcat/skid Loader, broom/sweeper, bulldozer, grader/blade, highlift, hoist, loader, roller, scraper, tractor & trencher
GROUP 8: Forklift & extend-a-boom forklift
GROUP 9: Oiler
IRON0025-019 06/01/2018
Rates Fringes
IRONWORKER
REINFORCING.................$ 28.48 27.74
STRUCTURAL..................$ 35.52 28.65
IRON0025-022 06/01/2018
Rates Fringes
IRONWORKER STRUCTURAL (Metal Building Erection Only)..........$ 35.52 28.65
LABO0259-002 08/01/2017
Rates Fringes
LABORER: Asbestos Abatement (Removal from Floors, Walls & Ceilings)........................$ 27.86 12.87
LABO0334-005 06/01/2018
Rates Fringes
LABORER: Landscape & Irrigation
GROUP 1.....................$ 20.52 6.90
GROUP 2.....................$ 18.52 6.90
CLASSIFICATIONS
GROUP 1: Landscape specialist, including air, gas and diesel equipment operator, lawn sprinkler installer, skidsteer (or equivalent)
GROUP 2: Landscape laborer: small power tool operator, material mover, truck driver and lawn sprinkler installer tender
LABO1191-002 06/01/2018
LABORER
Common or General; Grade Checker; Mason Tender - Brick/Cement/Concrete;
Pipelayer; Sandblaster......$ 28.20 16.80
PAIN0022-003 06/01/2015
Rates Fringes
PAINTER: Brush and Roller.......$ 26.06 17.66 PAINTER: Drywall Finishing/Taping.................$ 27.05 18.26 PAINTER: Spray..................$ 26.86 17.66
PAIN0357-002 06/01/2017
Rates Fringes
GLAZIER..........................$ 31.72 18.71
PAID HOLIDAYS: New Year's Day, Decoration Day, Fourth of July, Labor Day, Thanksgiving Day and Christmas Day;
provided that the employee has worked the last full regular scheduled work day prior to the holiday, and the first full regular scheduled work day following the holiday, provided the employee is physically able to work.
PLAS0067-001 04/01/2014
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 30.63 14.07
PLAS0067-004 04/01/2014
Rates Fringes
PLASTERER........................$ 30.63 14.07
PLUM0098-001 06/05/2018
Rates Fringes
PLUMBER, Excludes HVAC Pipe and Unit Installation............$ 39.77 27.13
PLUM0636-003 06/05/2017
PIPEFITTER, Includes HVAC Pipe and Unit Installation.......$ 40.41 29.35
ROOF0149-001 06/01/2018
Rates Fringes
ROOFER...........................$ 32.40 21.88
SFMI0704-001 01/01/2019
Rates Fringes
SPRINKLER FITTER (Fire Sprinklers)......................$ 43.65 27.27
SHEE0080-004 07/01/2018
Rates Fringes
SHEET METAL WORKER (Including HVAC Duct Installation;
Excluding HVAC System Installation)....................$ 41.05 26.66
TEAM0247-002 06/01/2018
Rates Fringes
TRUCK DRIVER
GROUP 1
Dump; Flatbed; Pickup......$ 26.71 0.70+a
GROUP 2
Semi.......................$ 26.86 0.70+a
GROUP 3
Lowboy.....................$ 26.96 0.70+a
PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day. If any of the above holidays fall on a Sunday, the following Monday shall be considered the holiday and, if work is performed, the rate shall be double time.
FOOTNOTE:
a. $456.70 per week, plus $67.10 per day.
SUMI2011-016 02/01/2011
Rates Fringes
INSTALLER - OVERHEAD DOOR........$ 27.98 0.00
IRONWORKER, ORNAMENTAL...........$ 18.48 7.93
TRUCK DRIVER: Tractor Haul
Truck............................$ 13.57 1.18
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION"