A.03.09 - Specifications - W912HP20B0003 - Post 45 Dredging Contract 4.pdf

PDF 38 MB Posted

Attached to
Post 45 Lower Harbor Dredging Contract 4 Federal contract opportunity
Solicitation number
W912HP20B0003
Issued by
Department of the Army Corps of Engineers Engineering District Charleston

About this file

This document provides details for a federal dredging contract opportunity with the U.S. Army Corps of Engineers Engineering District Charleston. The contract is for maintenance and new work dredging of approximately 6,076,000 cubic yards of unclassified material from the Charleston Lower Harbor Channel and Cooper River in Charleston and Berkeley Counties, South Carolina. Material dredged will be placed upland in designated placement areas or in the Ocean Dredged Materials Disposal Area. The work includes complying with environmental regulations. Due to environmental considerations, hopper dredges may not be utilized. The magnitude of work is estimated between $25,000,000 to $100,000,000. Survey data is provided for early review while other information will be included in the forthcoming solicitation expected on or around May 18, 2020. Offerors should monitor for the formal solicitation.

View the file

Other files for this federal contract opportunity

Other files attached to Post 45 Lower Harbor Dredging Contract 4, newest first.
File Type Posted
C.04.01 - Abstract Complete (signed) - W912HP20B0003 - Post 45 Dredging Contract 4.pdf PDF
C.04.01 - Bid Opening Login Sheet - W912HP20B0003 - Post 45 Dredging Contract 4.pdf PDF
B.08.03 - Solicitation Amendment 0008 (released) - W912HP20B0003 - Post 45 Dredging Contract 4.pdf PDF
B.08.03 - Conformed Solicitation Amendment 0008 (released) - W912HP20B0003 - Post 45 Dredging Contract 4.pdf PDF
Amendment 0008 - Utilities - SCEG.zip ZIP file
Specifications Section 35 20 23_Dredging_REVb.pdf PDF
Amendment 0008 - Utilities - CPW.zip ZIP file
FY20 LiDAR - DI Wando Cell.zip ZIP file
B.08.03 - Solicitation Amendment 0007 (released) - W912HP20B0003 - Post 45 Dredging Contract 4.pdf PDF
Drawing - 9612W-HP0006_REVa.pdf PDF
B.08.03 - Conformed Solicitation Amendment 0007 (released) - W912HP20B0003 - Post 45 Dredging Contract 4.pdf PDF
Specifications Section 35 20 23_Dredging_REVa.pdf PDF
DHEC - 2017-01482 HLT Dredging - ODMDS Permit mod - Signed.pdf PDF
A.03.09 - Specifications Revised Amendment 0007 - W912HP20B0003 - Post 45 Dredging Contract 4.pdf PDF
SAC-2017-01482 HLT ocean disposal modification.040919.pdf PDF
Drawing - 9612W-HP0005_REVa.pdf PDF
Post 45 Contract 4 - Solicitation OPTIONS.zip ZIP file
B.08.02 - Solicitation Released - W912HP20B0003 - Post 45 Dredging Contract 4.pdf PDF
Clouter Creek Middle Cell_Daniel Island Wando Cell.zip ZIP file
Post 45 Contract 4 - Solicitation 2020.zip ZIP file
A.03.09 - Plans - W912HP20B0003 - Post 45 Dredging Contract 4.pdf PDF
B.01.03 - Geotech Supporting Investigations - W912HP20B0003 - Post 45 Dredging Contract 4.pdf PDF
B.01.03 - Contract 4 Drawings Draft - W912HP20B0003 - Post 45 Dredging Contract 4.pdf PDF
B.01.03 - Geotechnical Data - W912HP20B0003 - Post 45 Dredging Contract 4.pdf PDF
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INVITATION FOR BIDS NO. W912HP20B0003

US Army Corps Of Engineers Charleston District

Post 45 Charleston Lower Harbor to Hugh Leatherman Terminal Maintenance and New Work Dredging

Charleston and Berkeley Counties, South Carolina

U. S. Army Corps of Engineers Charleston District 69A Hagood Avenue Charleston, South Carolina 29403-5107

Construction Solicitation and Specification

POST 45 CHARLESTON LOWER HARBOR W912HP20B0003

TO HUGH LEATHERMAN TERMINAL

MAINTENANCE AND NEW WORK DREDGING

PKGE FOR CONTRACTING

TABLE OF CONTENTS

SECTION TITLE

00 10 00 SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE

00 21 13 INSTRUCTIONS TO BIDDERS

00 45 00 REPRESENTATIONS AND CERTIFICATIONS

00 70 00 CONDITIONS OF THE CONTRACT

00 73 00 SUPPLEMENTARY CONDITIONS

DIVISION 01 GENERAL REQUIREMENTS

01 10 00 GENERAL

01 33 00 SUBMITTAL PROCEDURES

01 35 29 SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 45 04.00 10 CONTRACTOR QUALITY CONTROL

01 57 20.00 10 ENVIRONMENTAL PROTECTION

DIVISION 35 WATERWAY AND MARINE CONSTRUCTION

35 20 23 DREDGING

35 20 23.13 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM (DQM) - SCOW

ULLAGE PROFILE

35 20 23.33 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM (DQM) –

PIPELINE HYDRAULIC DREDGE

ATTACHMENTS

Section 00 10 00

SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE

DESCRIPTION OF WORK:

The work consists of base and option amount of approximately 7,048,000 cubic yards of unclassified maintenance and new work material from the Charleston Lower Harbor Channel and Cooper River. All materials dredged from Acceptance Sections 1, 6, & 7, as well as all BASE maintenance material and any interim-shoaling that occurs between acceptance of the maintenance requirement and the start of new work dredging shall either be placed upland in Clouter Creek Placement Area (Middle Cell) and Daniel Island Placement Area (Wando Cell), and/or in the Ocean Dredged Materials Disposal Area (ODMDS). New Work materials dredged from Acceptance Sections 2, 3, 4, 5, 8, & 9, and Option O&M Shoals 2, 3, 3A, 4, & 4A shall be placed in the ODMDS. The work is located in Charleston and Berkeley Counties, South Carolina. The work includes complying with the requirements of the Endangered Species Act and Marine Mammals Protection Act.

Due to environmental considerations, Hopper Dredges may not be utilized in the execution of work under this contract.

MAGNITUDE OF WORK: $25,000,000 TO $100,000,000

SECTION 00 10 00

SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE

ITEM NO. DESCRIPTION ESTIMATED

QUANTITY U/I UNIT PRICE AMOUNT

BASE

0001 MOBILIZATION AND DEMOBILIZATION -

MAINTENANCE AND NEW WORK DREDGING

IN CHARLESTON LOWER HARBOR AND

COOPER RIVER

ACCEPTANCE SECTIONS 1 to 9

1 JA JOB $_________

0002 DREDGING OF UNCLASSIFIED NEW WORK

MATERIAL IN CHARLESTON LOWER

HARBOR AND COOPER RIVER

ACCEPTANCE SECTION 1

UPLAND/ODMDS PLACEMENT

224,000 CY $_________ $_________

0003 DREDGING OF UNCLASSIFIED NEW WORK

MATERIAL IN CHARLESTON LOWER

HARBOR AND COOPER RIVER

ACCEPTANCE SECTION 2

ODMDS PLACEMENT

474,000 CY $_________ $_________

0004 DREDGING OF UNCLASSIFIED NEW WORK

MATERIAL IN CHARLESTON LOWER

HARBOR AND COOPER RIVER

ACCEPTANCE SECTION 3

ODMDS PLACEMENT

214,000 CY $_________ $_________

0005 DREDGING OF UNCLASSIFIED NEW WORK

MATERIAL IN CHARLESTON LOWER

HARBOR AND COOPER RIVER

ACCEPTANCE SECTION 4

ODMDS PLACEMENT

546,000 CY $_________ $_________

0006 DREDGING OF UNCLASSIFIED

NEW WORK MATERIAL IN CHARLESTON

LOWER HARBOR AND COOPER RIVER

ACCEPTANCE SECTION 5

ODMDS PLACEMENT

269,000 CY $_________ $_________

0007 DREDGING OF UNCLASSIFIED

MAINTENANCE & INTERIM-SHOALING

MATERIAL IN CHARLESTON LOWER

HARBOR AND COOPER RIVER

ACCEPTANCE SECTIONS 6, 7, 8, 9

UPLAND/ODMDS PLACEMENT

695,000 CY $_________ $_________

0008 DREDGING OF UNCLASSIFIED NEW WORK

MATERIAL IN COOPER RIVER

ACCEPTANCE SECTIONS 6 & 7

UPLAND/ODMDS PLACEMENT

2,955,000 CY $_________ $_________

MAINTENANCE AND NEW WORK DREDGING

0009 DREDGING OF UNCLASSIFIED NEW WORK

MATERIAL IN COOPER RIVER

ACCEPTANCE SECTIONS 8 & 9

ODMDS PLACEMENT

824,000 CY $_________ $_________

0010 COMPLIANCE WITH ENDANGERED SPECIES

ACT AND MARINE MAMMALS PROTECTION

ACT (CHARLESTON LOWER HARBOR AND

COOPER RIVER CHANNELS)

1 JA JOB $_________

TOTAL (COMBINATION OF BASE BID

ITEMS 0001-0010)

OPTION

0011 MOBILIZATION AND DEMOBILIZATION -

MAINTENANCE DREDGING IN CHARLESTON

LOWER HARBOR

SHOALS 2, 3, 3A, 4, & 4A

1 JA JOB $_________

0012 DREDGING OF UNCLASSIFIED

MAINTENANCE MATERIAL IN CHARLESTON

LOWER HARBOR

SHOALS 2, 3, 3A, 4, & 4A

ODMDS PLACEMENT

847,000 CY $_________ $_________

TOTAL (COMBINATION OF OPTION BID

ITEMS 0011-0012)

TOTAL (COMBINATION OF BASE &

OPTION BID ITEMS 0001-0012)

STATEMENT

Enter prices where space is provided for ALL items. Failure to follow this instruction may render the bid non-responsive and the bid will not be considered for award.

All bidders are advised materially unbalanced bids may be rejected as non-responsive. See FAR 52.214-19 Contract Award – Sealed Bidding – Construction.

Quantities indicated are ESTIMATED and are comprised of material within the required channel prism including the maximum pay slope material and the allowable overdepth as defined in the contract drawings.

SECTION 00 70 00 PAGE 1

SECTION 00 70 00

CONDITIONS OF THE CONTRACT

CLAUSES INCORPORATED BY FULL TEXT

FAR 52.211-0010 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract (see supplemental instructions), (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than (see supplemental instructions). The time stated for completion shall include final cleanup of the premises.

(End of Clause)

Supplemental Instructions:

(a) Prosecution of Work

The actual dredging work required shall be completed in its entirety, including cleanup operations by 29 JULY 2022, with the Order Of Work dredging requirement of Acceptance Sections 1, 2, and 3 being completed no later than 31 MARCH 2021, and maintenance dredging in Acceptance Sections 6, 8, & 9 being completed within 180 days of receipt of the NTP.

The Contractor shall provide the Government a schedule not later than 10 calendar days after date of the Notice to Proceed depicting, at a minimum, the following information.

- Commencement dates of initial mobilization and all subsequent demobilizations (if any) and remobilizations (if any) including the final demobilization

- Date dredging shall begin following each mobilization effort

- Duration of dredging (must at least meet specified completion date)

- Date dredging is to be completed, at a minimum, for each acceptance section

- Anticipated schedule of earnings

Once this schedule is approved, it will be incorporated into the contract by a no cost modification and become the performance period for the contract.

Liquidated damages will be assessed for every day work continues beyond this incorporated scheduled completion date (as adjusted for excusable delays as allowed per other clauses within the contract).

(End of supplemental instructions)

FAR 52.211-12 LIQUIDATED DAMAGES-CONSTRUCTION (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of ___$4,628__ for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

SECTION 00 70 00 PAGE 2

FAR 52.236-0001 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)

The Contractor shall perform on the site, and with its own organization, work equivalent to at least forty (40%) of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.

FAR 52.236-0004 PHYSICAL DATA (APR 84)

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The physical conditions indicated on the drawings and in the specifications are the results of surveys and site investigations performed by the Charleston District, Corps of Engineers personnel, and surveys and site investigations performed by contracted personnel through Corps of Engineers contracts.

(b) Weather conditions, transportation facilities and other pertinent information may be found in Section 01 10 00, paragraph PHYSICAL CONDITIONS

AND DATA.

DFARS 252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)

(a) The Government will provide the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall-

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors which might have been avoided by complying with this paragraph (b); and,

(5) Reproduce and print contract drawings and specifications as needed.

(c) In General—

(1) Large scale drawings shall govern small scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:

SECTION 00 70 00 PAGE 3

TITLE FILE DRAWING NO.

POST 45 CHARLESTON LOWER HARBOR

(in 12 sheets)

W912HP20B0003

DFARS 252.236-7004 PAYMENT FOR MOBILIZATION AND DEMOBILIZATION (DEC 1991)

(a) The Government will pay all costs for the mobilization and demobilization of all of the Contractor's plant and equipment at the contract lump sum price for this item.

(1) Sixty (60%) percent of the lump sum price upon completion of the Contractor's mobilization at the work site.

(2) The remaining forty (40%) percent upon completion of demobilization.

(b) The Contracting Officer may require the Contractor to furnish cost data to justify this portion of the bid if the Contracting Officer believes that the percentages in paragraphs (a)(1) and (2) of this clause do not bear a reasonable relation to the cost of the work in this contract.

(1) Failure to justify such price to the satisfaction of the Contracting Officer will result in payment, as determined by the Contracting Officer, of-

(i) Actual mobilization costs at completion of mobilization;

(ii) Actual demobilization costs at completion of demobilization; and,

(iii) The remainder of this item in the final payment under this contract.

(2) The Contracting Officer's determination of the actual costs in paragraph (b)(1) of this clause is not subject to appeal.

SECTION 00 70 00 PAGE 4

SECTION 00 73 00

SUPPLEMENTARY CONDITIONS

FAR 52.211-18 VARIATIONS IN ESTIMATED QUANTITY

If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity.

If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgment of the Contracting Officer, is justified.

PROJECT TABLE OF CONTENTS PAGE 1

PROJECT TABLE OF CONTENTS

DIVISION 01 – GENERAL REQUIREMENTS

01 10 00 GENERAL

01 33 00 SUBMITTAL PROCEDURES

01 35 29 SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 45 04.00 10 CONTRACTOR QUALITY CONTROL

01 57 20.00 10 ENVIRONMENTAL PROTECTION

DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION

35 20 23 DREDGING

35 20 23.13 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM (DQM) – SCOW

ULLAGE PROFILE

35 20 23.33 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM (DQM) –

PIPELINE HYDRAULIC DREDGE

ATTACHMENTS (See section for list of contents)

SECTION 01 10 00 PAGE 1

SECTION 01 10 00

GENERAL

PART 1 GENERAL

1.1. SUMMARY

1.2. PAYMENT

1.3. SUBMITTALS

1.4. PRECONSTRUCTION CONFERENCE

1.4.1. Conference

1.4.2. Letter of Record

1.5. CONSTRUCTION PROGRESS CHARTS

1.5.1. Submittal of Construction Progress Chart

1.5.2. Preparation of Construction Progress Chart

1.5.3. Modifications to Construction Progress Chart

1.6. CERTIFICATES OF COMPLIANCE

1.7. PHYSICAL CONDITIONS AND DATA

1.7.1. General

1.7.2. Physical Conditions

1.7.3. Weather Conditions

1.7.4. Transportation Facilities

1.7.5. Tidal Information

1.7.7. Obstruction of Channel

1.7.8. Condition of Site

1.7.9. Subsurface Investigations

1.7.10. Utility Crossings

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 10 00 PAGE 2

PART 1 GENERAL

1.1. SUMMARY

This section requires the Contractor to implement practices and procedures for general contract requirements.

1.2. PAYMENT

Separate payment will not be made for general contract requirements, and all associated costs therewith shall be included in the applicable unit prices or JOB (lump sum) prices contained in the Bidding Schedule.

1.3. SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.

SD-01 Preconstruction Submittals

Construction Progress Charts (Reference Subsection CONSTRUCTION

PROGRESS CHARTS)

1.4. PRECONSTRUCTION CONFERENCE

1.4.1. Conference

A Preconstruction Conference will be arranged by the Contracting Officer's Representative after award of contract and before commencement of work. The Contracting Officer's Representative will notify the Contractor of the time and date set for the meeting. At this conference, the Contractor shall be oriented with respect to Government procedures and line of authority, contractual, administrative, and construction matters. Additionally, a schedule of required submittals will be discussed. The Contractor shall bring to the preconstruction conference the required preconstruction submittals in completed form.

1.4.2. Letter of Record

A Letter of Record will be written documenting all items discussed at the conference and a copy will be furnished by the Contracting Officer's Representative to all in attendance.

1.5. CONSTRUCTION PROGRESS CHARTS

In accordance with Contract Clause SCHEDULES FOR CONSTRUCTION CONTRACTS, the Contractor shall be guided by the following requirements and procedures as pertaining to submission of an initial and subsequent periodic construction progress chart. These charts as accepted and updated shall provide the basis for determination of the amounts of progress payments.

(a) The Contractor shall within ten (10) days after the Notice to Proceed prepare and submit to the Contracting Officer for acceptance three copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and

SECTION 01 10 00 PAGE 3

completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.

(b) The Contractor shall enter the actual progress on the chart as directed by the Contracting Officer, and upon doing so shall immediately deliver three copies of the annotated schedule to the Contracting Officer. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.

(c) Failure of the Contractor to comply with the requirements of the Contracting Officer under this clause shall be grounds for a determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor’s right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.

1.5.1. Submittal of Construction Progress Chart

Progress Charts shall be established and maintained within the Quality Control System (QCS) in accordance Section 01 45 02.00 10 QUALITY CONTROL

SYSTEM.

1.5.2. Preparation of Construction Progress Chart

The Contractor shall indicate on the progress chart the bid items contained in the contract, showing the amount of the item and its relative weighted percentage of the total contract. The Contractor may separate features of work under each item to show salient work elements such as procurement of materials, plant, and equipment, and supplemental work elements such as excavation, reinforcing steel, backfill, etc. These salient features shall total to the cost and weighted percentages shown for the major bid item. When quantity variations impact the weighted percentage of a separate item by five percent or more, the Contractor shall revise the contract progress charts to accurately reflect the impact of such variations.

1.5.3. Modifications to Construction Progress Chart

Modifications to the contract which are minor in nature shall be listed and scheduled separately in order of their issuance and as reported on the associated request for progress payment. Completion of work on minor modifications shall be noted as work progresses. When major modifications are issued in which one or more of the bid items are significantly changed

SECTION 01 10 00 PAGE 4

monetarily or in time of completion, the progress schedule should be revised to incorporate such changes showing revised item completion dates and overall new completion date, as applicable.

1.6. CERTIFICATES OF COMPLIANCE

Any certificates required for demonstrating proof of compliance of materials with specification requirements shall be executed in three (3) copies unless otherwise specified. Each certificate shall be signed by an official authorized to certify in behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfactory material, if, after tests are performed on selected samples, the material is found not to meet the specific requirements.

1.7. PHYSICAL CONDITIONS AND DATA

1.7.1. General

In accordance with contract Clause FAR 52.236-4, data and information furnished or referred to below are for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

1.7.2. Physical Conditions

The physical conditions indicated on the drawings and in the specifications are the results of site investigations by the U.S. Army Corps of Engineers, Charleston District (USACE-SAC). It is the responsibility of prospective bidders to conduct their own investigations and decide for themselves the character and dredgeability of the materials, the volumes of different types of materials, and the difficulties of performing the work.

1.7.3. Weather Conditions

The areas in which work is to be done under these specifications are workable during the entire year; however, tropical storms may require that operations be suspended temporarily. The season for tropical storms is during the period June - November; during such disturbances precaution should be taken to secure all plant and equipment.

1.7.4. Transportation Facilities

The Port of Charleston is served by the CSX Railroad Company. Marine repair facilities, docking and fueling facilities, provisions, and marine supplies are also available.

1.7.5. Tidal Information

Tidal benchmark information may be obtained from U.S. Department of Commerce, National Oceanic and Atmospheric Administration, National Ocean Service at the NOS website, www.co-ops.nos.noaa.gov.

1.7.6. Channel Traffic

http://www.co-ops.nos.noaa.gov/

SECTION 01 10 00 PAGE 5

Charleston Harbor is served by large commercial ocean-going vessels, small freight boats, tugs, tow boats, barges, launches, pleasure crafts and fishing vessels. It may be necessary to suspend dredging operations temporarily and swing the dredge to the side of the channel for the passage of the larger of these vessels.

1.7.7. Obstruction of Channel

The Government will not undertake to keep the channel free from vessels or other obstructions, except to the extent of such regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the Rivers and Harbors Act approved 8 August 1917. The Contractor will be required to conduct the work in such a manner as to obstruct navigation as little as possible, and in case the Contractor's plant so obstructs the channel as to make it difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage. Upon completion of the work the Contractor shall promptly remove his plant, including ranges, buoys, piles and other markers placed by him under the contract in navigation waters or on the shore.

1.7.8. Condition of Site

It is the responsibility of prospective bidders examine the areas of work, prior to submission of bids, in order to determine for themselves the accessibility for transportation of personnel, supplies and equipment and also to familiarize themselves as to the nature and general arrangement of work areas. The Contractor shall obtain any and all right-of-entries across private lands which he may use.

1.7.9. Subsurface Investigations

Boring logs and other subsurface investigation information are included in

ATTACHMENTS.

1.7.10. Utility Crossings

The Contractor shall be responsible for coordinating with utility owners to locate and identify where such crossings exist within the harbor. The Contractor shall be responsible for implementing operational measures so as not to disturb existing utilities via dredging, anchoring, etc.

PART 2 PRODUCTS (Not Applicable)

-- End of Section --

MAINTENANCE AND NEW WORK DREDGING

SECTION 01 33 00 PAGE 1

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

SUMMARY

DEFINITIONS

Approving Authority Work Submittal Descriptions

PAYMENT

SUBMITTALS

SUBMITTAL CLASSIFICATION

Government Approved Information Only

PREPARATION

Transmittal Form Electronic File Format

INFORMATION ONLY SUBMITTALS

VARIATIONS

Considering Variations Proposing Variations Warranting That Variations are Compatible Review Schedule is Modified

SUBMITTAL REGISTER

Use of Submittal Register Updating Submittal Register

SCHEDULING

GOVERNMENT APPROVING AUTHORITY

DISAPPROVED SUBMITTALS

APPROVED SUBMITTALS

APPROVED SAMPLES

WITHHOLDING OF PAYMENT

STAMPS

MAINTENANCE AND NEW WORK DREDGING

SECTION 01 33 00 PAGE 2

PART 1 GENERAL

SUMMARY

The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.

Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.

Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Contractor's Quality Control (CQC) System Manager shall check and approve all items prior to submittal. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:

Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.

Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Contractor shall pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.

DEFINITIONS

Approving Authority

Office or designated person authorized to approve submittal.

Work

As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD- 01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.

Submittal Descriptions

Submittals requirements are specified in the technical sections. Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Preconstruction Submittals

Submittals which are required prior to issuance of contract notice to proceed include schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

MAINTENANCE AND NEW WORK DREDGING

SECTION 01 33 00 PAGE 3

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-04 Samples

Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.

Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.

Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged.

Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.

SD-05 Design Data

Design calculations, mix designs, analyses or other data pertaining to a part of work.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets

MAINTENANCE AND NEW WORK DREDGING

SECTION 01 33 00 PAGE 4

specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.

SD-08 Manufacturer's Instructions

Preprinted material describing installation of a product, system or material, including special notices and (MSDS) concerning impedances, hazards and safety precautions.

SD-09 Manufacturer's Field Reports

Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing laboratory or agency and must state the test results; and indicate whether the material, product, or system has passed or failed the test.

SD-10 Operation and Maintenance Data

Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.

This data is intended to be incorporated in an operations and maintenance manual or control system.

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings.

PAYMENT

Separate payment will not be made for submittal requirements, and all associated costs therewith shall be included in the applicable unit prices or lump sum prices contained in the Bidding Schedule.

SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will

MAINTENANCE AND NEW WORK DREDGING

SECTION 01 33 00 PAGE 5

review the submittal for the Government. Submit the following in accordance with this section.

SD-01 Preconstruction Submittals

Submittal Register (Reference Subsection SUBMITTAL REGISTER)

SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

Government Approved

Governmental approval (G) is required for extensions of design, critical materials, deviations, and other items as designated by the Contracting Officer. Government approval is required for any deviations from the Solicitation or Accepted Proposal and other items as designated by the Contracting Officer. Within the terms of the Contract Clause 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered “shop drawings.”

Information Only

Submittals not requiring Government approval will be for information only.

They are not considered “shop drawings” within the terms of the Contract Clause referred to above.

PREPARATION

Transmittal Form

A transmittal form (ENG Form 4025-R) shall be used for submitting both Government approved and information only submittals in accordance with the instructions on the second page of the form. This form is included in the RMS module that the Contractor is required to use for this contract. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.

Electronic File Format

Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. Compile the submittal file as a single, complete document, to include the Transmittal Form described within.

Name the electronic submittal file specifically according to its contents, coordinate the file naming convention with the Contracting Officer.

Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. Generate PDF files from original documents with bookmarks so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. Set PDF Document Properties for the Initial View, Navigation Tab to display "Bookmarks Panel and Page." When required, the electronic file must include a valid electronic signature, or scan of a signature.

MAINTENANCE AND NEW WORK DREDGING

SECTION 01 33 00 PAGE 6

Email electronic submittal documents fewer than 10MB to an email address as directed by the Contracting Officer. Provide electronic documents over 10MB through an electronic file sharing system such as the AMRDEC SAFE Web Application located at the following website:

https://safe.amrdec.army.mil/safe/. Follow local procedures for notifying, maintaining records, and transmitting records of all file transfers as directed by the Contracting Officer.

Provide hard copies of submittals when requested by the Contracting Officer.

Up to 1 additional hard copy of any submittal may be requested at the discretion of the Contracting Officer, at no additional cost to the Government.

INFORMATION ONLY SUBMITTALS

Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;

and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

VARIATIONS

Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION and will be considered where advantageous to Government.

Considering Variations

Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).

Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.

Proposing Variations

When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.

Check the column "variation" of ENG Form 4025 for submittals which include proposed deviations requested by the Contractor. Set forth in writing the reason for any deviations and annotate such deviations on the submittal. The Government reserves the right to rescind inadvertent approval of submittals

MAINTENANCE AND NEW WORK DREDGING

SECTION 01 33 00 PAGE 7

containing unnoted deviations.

Warranting That Variations are Compatible

When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.

Review Schedule is Modified

In addition to normal submittal review period, a period of ten (10) working days will be allowed for consideration by the Government of submittals with variations.

SUBMITTAL REGISTER

Prepare and maintain submittal register, as the work progresses. Do not change data which as delivered by Government; retain data as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment.

This list may not be all inclusive and additional submittals may be required.

Maintain a submittal register for the project in accordance with Section 01 45 00.15 10 RESIDENT SYSTEM MANAGER CONTRACTOR MODE (RMS-CM). The Government will provide the initial submittal register with the following fields completed, to the extent that will be required by the Government during subsequent usage.

Section: Lists specification section in which submittal is required.

Spec Paragraph Number: Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.

Description of Submittal: Lists a brief description of each submittal by section.

Type of Submittal: Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section.

Classification: Indicate approving authority for each submittal.

The Contractor is to track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government.

Use of Submittal Register

Submit submittal register with QC plan and project schedule. Verify that all submittals required for project are listed and add missing submittals.

Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:

Activity No: Activity number from the project schedule.

Contractor Submit Needed By: Scheduled date for approving authority to receive submittals.

Contractor Approval Needed By: Date Contractor needs approval of

MAINTENANCE AND NEW WORK DREDGING

SECTION 01 33 00 PAGE 8

submittal.

Contractor Material Needed By: Date that Contractor needs material delivered to Contractor control.

Updating Submittal Register

Submittal Register shall be maintained in RMS and shall be updated continually as a condition of each invoice.

SCHEDULING

Schedule and submit concurrent submittals covering component items forming a system or items that are interrelated. Include certifications to be submitted with the pertinent drawings at the same time. Adequate time (a minimum of thirty (30) calendar days exclusive of mailing time) shall be allowed on the register for review and approval. No delay damages or time extensions will be allowed for time lost in late submittals.

Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.

Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation.

Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A."

Re-submit register and annotate monthly by the Contractor with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.

Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register".

GOVERNMENT APPROVING AUTHORITY

When approving authority is the Contracting Officer, the Government will:

Note date on which submittal was received.

Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.

Upon completion of review of submittals requiring Government approval, stamp and date approved submittals. Two (2) copies of the approved submittal will be retained by the Contracting Officer and one (1) copy of the submittal will be returned to the Contractor.

DISAPPROVED SUBMITTALS

Contractor shall make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the clause entitled, "Changes", is to be given to the

MAINTENANCE AND NEW WORK DREDGING

SECTION 01 33 00 PAGE 9

Contracting Officer. Contractor is responsible for the dimensions and design of connection details and construction of work. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.

If changes are necessary to submittals, the Contractor shall make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.

APPROVED SUBMITTALS

The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for.

After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

APPROVED SAMPLES

Approval of a sample is only for the characteristics or use named in such approval and is not be construed to change or modify any contract requirements. Before submitting samples, the Contractor to assure that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.

Match the approved samples for materials and equipment incorporated in the work. If requested, approved samples, including those which may be damaged in testing, will be returned to the Contractor, at his expense, upon completion of the contract. Samples not approved will also be returned to the Contractor at its expense, if so requested.

Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. Government reserves the right to disapprove any material or equipment which previously has proved unsatisfactory in service.

Samples of various materials or equipment delivered on the site or in place may be taken by the Contracting Officer for testing. Samples failing to meet contract requirements will automatically void previous approvals. Contractor is required to replace such materials or equipment to meet the contract requirements.

Approval of the Contractor's samples by the Contracting Officer does not relieve the Contractor of his responsibilities under the contract.

WITHHOLDING OF PAYMENT

Payment for materials incorporated in the work will not be made if required Government approvals have not been obtained. No payment will be made for any materials incorporated into the work for any information only submittals found to contain errors or deviations from the Solicitation or Accepted Proposal.

MAINTENANCE AND NEW WORK DREDGING

SECTION 01 33 00 PAGE 10

STAMPS

Stamps used by the Contractor on the submittal data to certify that the submittal meets contract requirements shall be similar to the following:

CONTRACTOR

(Firm Name)

_____ Approved

_____ Approved with corrections as noted on submittal data and/or attached sheets(s).

SIGNATURE: __________________________________________________________

TITLE: ______________________________________________________________

DATE: _______________________________________________________________

SECTION 01 35 29 PAGE 1

SECTION 01 35 29

SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS

1.2. REFERENCES

1.3. DEFINITIONS

1.4. PAYMENT

1.5. SUBMITTALS

1.6. REGULATORY REQUIREMENTS

1.6.1. Revisions to Safety Manual, EM 385-1-1

1.7. ACCIDENT PREVENTION PLAN

1.7.1. Emergency Response Procedure

1.7.2. Certificate of Compliance for the Contractor Program and the

Dredge(s)

1.8. SAFETY PROGRAM CONFERENCE

1.9. ACTIVITY HAZARD ANALYSIS

1.10. SAFETY MEETINGS

1.11. SAFETY PROGRAM STAFF REQUIREMENTS

1.11.1. Site Safety and Health Officers (SSHO) Staffing for Dredging Contracts

1.11.2. SSHO Requirements for Dredging

1.11.3. Designated Representative (DR) Requirements for Dredging

1.11.4. Safety Personnel Training Requirements for Dredging

1.11.5. SSHO Responsibilities

1.12. SAFETY PROGRAM FOR FLOATING PLANT

1.12.1. Certification of Floating Plant

1.12.1.1. Seagoing Barge Act--Special Standard of Responsibility

1.12.2. National Association of Marine Surveyors or the Society of

Accredited Marine Surveyors

1.12.3. Personal Flotation Device

1.12.4. Safety Drills

1.12.5. Smoke Alarms

1.12.6. CO Monitors

1.12.7. Fire Extinguisher - Mobile Construction Equipment

1.12.8. Electrical Installations

1.12.9. Safe Clearance Procedures

1.12.10. Work in Confined Spaces

1.12.11. Hazard Communication Program and Material Safety Data Sheets

1.12.12. Severe Weather Plan

1.13. SAFETY INSPECTION

1.13.1. Contractor Safety Inspection

1.14. EMERGENCY RESPONSE PROCEDURES

1.14.1. Emergency Response Procedures

1.14.2. Communications

1.14.3. Telephone Numbers, Call Signs and Instructions

1.14.4. Machinery and Mechanized Equipment Checklist

SECTION 01 35 29 PAGE 2

1.14.5. Welding Equipment

1.14.6. Anchor Points

1.14.7. Accident Notification

1.14.8. Exceptions

1.15. NOTICE TO MARINERS

PART 3 EXECUTIONS (Not Applicable)

SECTION 01 35 29 PAGE 3

This section requires Contractors to implement practices and procedures for working safely and in compliance with OSHA and USACE regulation.

1.2. REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)

ASSE/SAFE A10.34 Protection of the Public on or Adjacent to Construction Sites

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 302 Fire Protection Standard for Pleasure and Commercial Motor Craft

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 Safety and Health Requirements Manual

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910 Occupational Safety and Health Standards

29 CFR 1910.146 Permit-required Confined Spaces

29 CFR 1926 Safety and Health Regulations for Construction

29 CFR 1926.16 Rules of Construction

1.3. DEFINITIONS

(a) High Visibility Accident. Any mishap which may generate publicity or high visibility.

(b) Medical Treatment. Treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by a physician or registered personnel.

(c) Recordable Injuries or Illnesses. Any work-related injury or illness that results in:

(1) Death, regardless of the time between the injury and death, or the length of…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .