This document contains an abstract of bids received in response to Solicitation Number W912ES22B0006 for the Lock and Dam 4 Sheet Pile Installation and construction project issued by the Department of the Army Corps of Engineers Engineering District St Paul on July 8, 2022.

The solicitation sought bids for various construction items including bonds, miscellaneous metals, sheet pile installation, select granular fill, timber fenders, grout hole drilling, excavation, handrails, riprap and bedding, instrumentation and monitoring, and piezometers. Six contractors submitted bids by the August 24, 2022 deadline: American Mine Services LLC, Dubuque Barge & Fleeting Serivce Co. d/b/a Newt Marine Service, PDSI Contractors, Tunheim Construction, LLC, Togiak Management Services, LLC, and PM Jenkins Group LLC dba W4 Construction Group. Bid amounts ranged from $4,157,599 to $4,995,568. The contracting officer certified that all bids received in response to the solicitation were opened and recorded on the abstract.

View the file

Other files for this federal contract opportunity

Other files attached to Lock and Dam 4 Sheet Pile Installation/construction, newest first.
File Type Posted
22B0006 LD4 Amendment 0005.pdf PDF
22B0006 LD4 Amendment 0004.pdf PDF
22B0006 LD4 Amendment 0003.pdf PDF
22B0006 LD4 Amendment 0002.pdf PDF
LD 4 Pre-bid Contractor Site Visit Sheet Pile Install.pdf PDF
22B0006 LD4 Amendment 0001.pdf PDF
LD4 Site Visit Meeting Location.pdf PDF
LD4 Plans W912ES22B0006.pdf PDF
LD4 Solicitation and Specifications W912ES22B0006.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LD4 Sheet Pile, Alma, Wisconsin Solicitation: W912ES22B0006 Solicitation: W912ES22B0006

US Army Corps of Engineers. 180 East 5th Street, Suite 700. Saint Paul, Minnesota 55101 BID OPENING: 24 August 2022 @ 1400

Contracting Officer: Gwen Davis Contract Specialist: Roberta Just

Unit Unit Unit Unit Unit Unit Unit Item Description Quantity Unit Price Amount Price Amount Price Amount Price Amount Price Amount Price Amount Price Amount

0001 Bonds (Performance and Payment) 1 Job $52,581.00 $52,581.00 $41,164.00 $41,164.00 $33,500.00 $33,500.00 $41,870.00 $41,870.00 $20,650.00 $20,650.00 $63,843.00 $63,843.00 $55,000.00 $55,000.00 0002 Furnish and Install Miscellaneous Metals 1 Job $721,255.00 $721,255.00 $560,896.00 $560,896.00 $495,177.00 $495,177.00 $489,031.00 $489,031.00 $460,944.93 $460,944.93 $562,479.00 $562,479.00 $1,100,000.00 $1,100,000.00

Furnis and Install Sheet Pile - Closure Cell Sides Along Existing Monoliths and Downstream 12,090 SF $147.29 $1,780,736.10 $84.00 $1,015,560.00 $88.60 $1,071,174.00 $84.00 $1,015,560.00 $104.91 $1,268,361.90 $88.46 $1,069,481.40 $93.60 $1,131,624.00

0004 Furnish and Install Sheet Pile - General 12,490 SF $128.83 $1,609,086.70 $84.00 $1,049,160.00 $88.60 $1,106,614.00 $85.00 $1,061,650.00 $104.91 $1,310,325.90 $88.46 $1,104,865.40 $93.60 $1,169,064.00 0005 Furnish and Install Select Granular Fill 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

0005AA First 2700 CY 2,700 CY $52.25 $141,075.00 $39.00 $105,300.00 $40.90 $110,430.00 $41.00 $110,700.00 $33.13 $89,451.00 $40.83 $110,241.00 $38.00 $102,600.00 0005AB Over 2700 CY 920 CY $51.51 $47,389.20 $36.00 $33,120.00 $40.90 $37,628.00 $41.00 $37,720.00 $26.00 $23,920.00 $38.57 $35,484.40 $34.00 $31,280.00

0006 Furnish and Install Timber Fenders 1 Job $49,643.00 $49,643.00 $125,371.00 $125,371.00 $139,728.00 $139,728.00 $134,070.00 $134,070.00 $66,261.08 $66,261.08 $139,501.00 $139,501.00 $82,500.00 $82,500.00 0007 Grout Hole Driling through Soil 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

0007AA First 190 LF 190 LF $322.22 $61,221.80 $700.00 $133,000.00 $705.45 $134,035.50 $677.00 $128,630.00 $441.74 $83,930.60 $704.31 $133,818.90 $840.00 $159,600.00 0007AB Over 190 LF 66 LF $347.55 $22,938.30 $621.00 $40,986.00 $705.45 $46,559.70 $701.00 $46,266.00 $400.00 $26,400.00 $665.37 $43,914.42 $700.00 $46,200.00

0008 Grout Hole Drilling through Derrick Stone or Riprap 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 0008AA First 60 LF 60 LF $361.39 $21,683.40 $700.00 $42,000.00 $704.32 $42,259.20 $701.00 $42,060.00 $883.48 $53,008.80 $703.17 $42,190.20 $840.00 $50,400.00 0008AB Over 60 LF 20 LF $398.45 $7,969.00 $621.00 $12,420.00 $704.32 $14,086.40 $701.00 $14,020.00 $800.00 $16,000.00 $664.30 $13,286.00 $700.00 $14,000.00

0009 Furnish and Place Microfine Cement Grout 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 0009AA First 75 CY 75 CY $4,980.00 $373,500.00 $5,200.00 $390,000.00 $5,620.92 $421,569.00 $5,393.00 $404,475.00 $3,589.14 $269,185.50 $5,612.00 $420,900.00 $6,000.00 $450,000.00 0009AB Over 75 CY 25 CY $4,980.00 $124,500.00 $4,948.00 $123,700.00 $5,620.92 $140,523.00 $5,393.00 $134,825.00 $3,000.00 $75,000.00 $5,301.52 $132,538.00 $6,000.00 $150,000.00

0010 Firnish and Place San-Cement-Bentonite Grout 30 CY $3,265.00 $97,950.00 $2,372.00 $71,160.00 $2,694.60 $80,838.00 $2,585.00 $77,550.00 $2,000.00 $60,000.00 $2,690.20 $80,706.00 $3,100.00 $93,000.00 0011 Excavation of Riverbed Material 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

0011AA First 700 CY 700 CY $77.78 $54,446.00 $95.00 $66,500.00 $90.88 $63,616.00 $87.00 $60,900.00 $331.30 $231,910.00 $90.73 $63,511.00 $94.00 $65,800.00 0011AB Over 700 CY 300 CY $80.38 $24,114.00 $80.00 $24,000.00 $90.88 $27,264.00 $91.00 $27,300.00 $68.00 $20,400.00 $85.72 $25,716.00 $79.00 $23,700.00

0012 Furnish Handrail 1 Job $48,492.00 $48,492.00 $50,000.00 $50,000.00 $35,784.00 $35,784.00 $35,595.00 $35,595.00 $22,826.94 $22,826.94 $35,726.00 $35,726.00 $30,800.00 $30,800.00 0013 Furnish and Place Riprap & Bedding 1 Job $9,121.00 $9,121.00 $65,000.00 $65,000.00 $31,808.00 $31,808.00 $31,640.00 $31,640.00 $6,652.33 $6,652.33 $31,756.00 $31,756.00 $5,000.00 $5,000.00 0014 Instrumentation and Monitoring 1 Job $22,845.00 $22,845.00 $72,262.00 $72,262.00 $79,520.00 $79,520.00 $75,495.00 $75,495.00 $117,779.07 $117,779.07 $75,772.00 $75,772.00 $95,000.00 $95,000.00 0015 Furnish and Install Piezometer 4 Each $34,860.00 $139,440.00 $34,000.00 $136,000.00 $31,246.75 $124,987.00 $117,726.00 $470,904.00 $23,898.17 $95,592.68 $74,987.00 $299,948.00 $35,000.00 $140,000.00

TOTAL $5,409,986.50 $4,157,599.00 $4,237,100.80 $4,440,261.00 $4,318,600.73 $4,485,677.72 $4,995,568.00

American Mine Services LLC 11808 Highway 93

Boulder, CO 80303

Dubuque Barge & Fleeting Serivce Co. d/b/a Newt Marine

Service 5 Jones St

Dubuque, IA 52001Government Estimate PDSI Contractors

20 W. Huron Pontiac, MI 48342

Tunheim Construction, LLC 3950 25th St N

Fargo, ND 58102

Togiak Management Services, LLC

4141 B Street, Suite 306 Anchorage, AK 99503

PM Jenkins Group LLC dba W4 Construction Group 4341 S Westnedge Ave, 2200 Kalamazoo, MI 49008

I certify that I have opened, read, and recorded on this abstract all bids received in response to this solicitation.

Gwendolyn K. Davis Contracting Officer