This solicitation requests proposals for the Pigs Eye Lake CAP 204 Project to construct up to six islands, sand benches, marsh habitat, and terrestrial plantings in Pigs Eye Lake, Minnesota. The U.S. Army Corps of Engineers, St. Paul District seeks a contractor to perform work including island berm construction, eagle nest avoidance, borrow site excavation and placement of dredged and stockpiled materials. The total project value is estimated between $10-25 million. Proposals are due from small businesses only classified as NAICS code 237990. The resulting contract will be firm fixed-price. Offerors must register in the System for Award Management to be eligible for award.

View the file

Other files for this federal contract opportunity

Other files attached to Pigs Eye Islands, newest first.
File Type Posted
A22 W912ES20R0002 0004 Solicitation Amendment.pdf PDF
A22 W912ES20R0002 0003 Solicitation Amendment.pdf PDF
PigsEye_2ndRevisedSection_35_20_23.40_13.pdf PDF
2019_PigsEyeTurbidity.xlsx XLSX spreadsheet
PigsEye_RevisedSection_35_20_23.40_13.pdf PDF
A22 W912ES20R0002 0002 Solicitation Amendment.pdf PDF
ExTopo_2019Nov.txt TXT text file
ExTopo2015Oct.txt TXT text file
PigsEye_Tables.xlsx XLSX spreadsheet
A22 W912ES20R0002 0001 Solicitation Amendment.pdf PDF
W912ES20R0002 Plan Set 24-25.pdf PDF
Attachment 1 - Past Performance Questionnaire.docx DOCX document
W912ES20R0002 Plan Set 26-28.pdf PDF
W912ES20R0002 Plan Set 14-23.pdf PDF
W912ES20R0002 Plan Set 1-5.pdf PDF
Attachment 2 - Small Business Participation Commitment Plan.docx DOCX document
W912ES20R0002 Plan Set 29-47.pdf PDF
W912ES20R0002 Plan Set 6-13.pdf PDF
W912ES20R0002 Solicitation and Specifications.pdf PDF
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pigs Eye Islands W912ES20R0002 Revised 21Dec2020

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 14 00.00 13

WORK RESTRICTIONS

PART 1 GENERAL

1.1 MEASUREMENT AND PAYMENT

1.2 STAGING AREAS

1.2.1 Contractor Field Offices

1.2.2 Staging Area Restrictions

1.3 Pre-construction Requirement

1.4 GROUNDS AND ROADWAYS

1.4.1 Parking

1.4.2 Snow Removal

1.5 BLASTING

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION

3.1 ISLAND BERM CONSTRUCTION

3.1.1 Temporary Construction Features

3.1.2 Overwintering Seed Mix

3.2 EAGLE NEST EXCLUSION ZONE RESTRICTIONS

3.2.1 Required Bald Eagle Protection Act Avoidance Measures

3.2.2 Identification of Limits of Eagle Nest Exclusion Zone

3.3 PIGS EYE ISLAND HERON ROOKERY SCIENTIFIC AND NATURAL AREA (SNA)

3.4 FISHERY PROTECTION Zones - Work Exclusion Dates

3.5 ACCESS DREDGING (optional)

3.6 Borrow Sites

3.6.1 GRANULAR FILL BORROW AREA

3.6.2 FINE FILL BORROW AREA

3.7 MARINE STAGING AREAS

3.8 SLOW-NO-WAKE ZONES

3.9 EXISTING UTILITIES

3.9.1 General

3.9.2 Buried Utilities

3.9.3 Interruption of Services

3.9.4 Minnesota One Call Excavation Notice System

3.10 PROTECTION OF TREES

3.11 FLOATING PLANT

3.11.1 Equipment and Personnel

3.11.2 Navigable Waters

3.11.3 Sewage and Bilge Water Disposal

-- End of Section Table of Contents --

SECTION 01 14 00.00 13 Page 1

SECTION 01 14 00.00 13

WORK RESTRICTIONS

PART 1 GENERAL

1.1 MEASUREMENT AND PAYMENT

The Contractor is responsible for the work of this section, without any direct compensation being made other than the payment received for contract line items on the bid schedule.

1.2 STAGING AREAS

All staging area locations, access, and operations shall be indicated on the Contractor's Work and Placement Plan in accordance with SECTION 35 20

23.40 13 PLACEMENT OF DREDGED AND STOCKPILED FILL MATERIAL. As part of the plan include the staging for materials, equipment, supplies, field offices, and parking.

1.2.1 Contractor Field Offices

The location available for the Contractor field offices as well as personnel parking are discussed in SECTION 01 50 02.00 13 TEMPORARY CONSTRUCTION FACILITIES. This location shall NOT be used for loading and unloading of material required for the project,such as riprap.

The Contractor has the option of locating the trailers on a barge at the Contractor's work site, if all requirements can be met. If barge trailers are utilized, onshore parking for the Contractor and Government personnel will still be required. Coordinate the locations for trailers and parking with the Contracting Officer.

1.2.2 Staging Area Restrictions

The use of the staging area site denoted in the contract plans is subject to other contracts and work in this area. Refer to paragraph OTHER CONTRACTS AND WORK in SECTION 01 00 00.00 13 GENERAL.

1.3 Pre-construction Requirement

The Contractor is required to notify the Ramsey-Washington Metro Watershed District prior to beginning construction activity in order to schedule an initial SWPPP inspection. At a minimum the Contractor must notify:

Nicole Soderholm Ramsey-Washington Metro Watershed District 651-792-7976

1.4 GROUNDS AND ROADWAYS

1.4.1 Parking

There will be very limited Contractor parking available. Contractor parking shall be restricted to temporary construction facilities as shown on the drawings.

SECTION 01 14 00.00 13 Page 2

1.4.2 Snow Removal

The Contractor shall be responsible for snow removal in the Contractor's access, work, and parking areas.

1.5 BLASTING

Blasting will not be permitted.

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION

3.1 ISLAND BERM CONSTRUCTION

Place the granular fill material in such a manner as to minimize mud waves and reduce the potential for global stability failure. Refer to SECTION 35 20 23.40 13 PLACEMENT OF DREDGED AND STOCKPILED FILL MATERIAL for definitions, a summary of soil conditions and their anticipated response during construction, and suggestions for the Work and Placement Plan.

3.1.1 Temporary Construction Features

Temporary construction features include, but are not limited to, sand bridges, construction pads, and sand plugs. These temporary features (where shown) are not required, but may be necessary for proper prosecution of work under this contract and are at the option of the Contractor.

If the Contractor determines different or additional locations for temporary features are necessary for the proper prosecution of work under this contract, this information must be submitted in the Work and Placement Plan in accordance with SECTION 35 20 23.40 13 PLACEMENT OF DREDGED AND STOCKPILED FILL MATERIAL, and approved by the Contracting Officer.

Temporary features are considered to be incidental and will not be a separate bid item for payment. If the Contractor chooses to construct the temporary features shown on the plans, the Contractor must reuse the material on the islands, and comply with the Island Construction - Granular Fill Measurement paragraph in SECTION 01 22 0.00 10 MEASUREMENT AND PAYMENT. A spoil site for the temporary feature material will not be provided by the Government.

3.1.2 Overwintering Seed Mix

For construction season 1, after the initial placement of granular material, island berms shall be left without fine fill and unseeded overwinter in order to determine island settlement. After the second construction season, and subsequent seasons, no finished construction area shall be left without fine fill and unseeded during the winter months.

Place overwintering (temporary) seed in accordance with SECTION 32 92

19.00 13 SEEDING

SECTION 01 14 00.00 13 Page 3

3.2 EAGLE NEST EXCLUSION ZONE RESTRICTIONS

Four active eagle nests in the project area were identified in 2016. The nests and the 660 foot buffer are located as shown on the contract plans.

Prior to start of the construction season in spring of 2021 and future years, the United States Fish and Wildlife Service (USFWS) will conduct eagle nest surveys for the project area. If the nests at these locations are determined to be active or if additional active nests are identified within the project area, the USFWS will notify the Contracting Officer.

The Contractor will be notified of new active nest locations and comply with the avoidance measures specified herein.

3.2.1 Required Bald Eagle Protection Act Avoidance Measures

The Contractor's activities near any active eagle nest shall comply with the avoidance measures of the Bald and Golden Eagle Protection Act (16 U.S.C.668-668c) as follows:

(1) Maintain a buffer, identified as the eagle nest exclusion zone, of at least 660 feet (200 meters) between project construction activities and any active nest.

(2) Restrict all project construction activities within 660 feet of any identified active eagle nest to outside the nesting season (i.e. outside the nesting season is from August through mid-January in the Midwest). The USFWS will determine when nesting activity has ended (i.e.,eaglets have fledged) and will notify the Contracting Officer that the Contractor may immediately proceed with construction activities within the eagle nest exclusion zone.

(3) Maintain established landscape buffers that may screen the activity from the nest.

3.2.2 Identification of Limits of Eagle Nest Exclusion Zone

Clearly mark the limits of all eagle nests. Show exclusion zones that overlay with the project features such as site access, dredging, and island construction.

3.3 PIGS EYE ISLAND HERON ROOKERY SCIENTIFIC AND NATURAL AREA (SNA)

The SNA is identified as an EXCLUSION ZONE with RESTRICTIONS, and is denoted on the contract plans. Do not enter the SNA exclusion zone boundary. Clearly mark the limits of the exclusion zone with floating in-water boundary markers in accordance with the Minnesota DNR's Public Waters Work Permit provided as an attachment in SECTION 01 57 20.00 13.

3.4 FISHERY PROTECTION Zones - Work Exclusion Dates

No activity affecting the bed of the protected water may be conducted between April 1 and June 30, to minimize impacts on fish spawning and migration. If this type of work is essential during this timeframe, it shall be done only upon written approval of the Area Fisheries Manager.

See contact list at:

http://files.dnr.state.mn.us/fisheries/management/dnr_fisheries_managers.pdf.

Should work begin elsewhere in the project area within these dates, all exposed soils that are within 200 feet of Public Waters and drain to those waters must complete erosion control measures within 24 hours.

SECTION 01 14 00.00 13 Page 4

All work must be in accordance with the Public Waters Work Permit provided as an attachment in SECTION 01 57 20.00 13.

3.5 ACCESS DREDGING (optional)

Access dredging shall be determined by the Contractor's means and methods, and will not be a separate bid item. The Contractor shall perform access dredging only at locations within the permit limits and as approved by the Contracting Officer.

Water depths in the river and access channel are sufficient for the Contractor's dredging equipment to reach the beginning of Pigs Eye Lake without the need for dredging.

If the Contractor determines to access dredge, an access dredge plan shall be submitted and it shall comply with permit requirements. For placement of the wet fill from access dredging see SECTION 35 20 23.40 13 PLACEMENT OF DREDGED AND STOCKPILED FILL MATERIAL. For purposes of this contract, material from access dredging is considered fine, regardless of actual gradation.

3.6 Borrow Sites

The borrow site is a temporary stockpile location for material obtained from routine channel dredging operations. Access dredging to a borrow site (if applicable) shall be in accordance with SECTION 35 20 23 DREDGING. Borrow site clearing (if applicable) shall be in accordance with SECTION 31 11 00 CLEARING AND GRUBBING. After all required material is excavated from the borrow site, the Contractor shall shape the finished stockpile surface to provide positive drainage in accordance with the contract plans.

3.6.1 GRANULAR FILL BORROW AREA

The first borrow site for granular fill excavation is Pine Bend (river mile ~824). Pine Bend has approximately 200,000 cyds of material for excavation. Pine Bend must be fully excavated, and the quantity excavated from the site approved by the Contracting Officer, prior to excavating granular fill from the second borrow site. Lower Boulanger (river mile ~821.5) is the second borrow site and contains the remaining granular quantity for the Pigs Eye Islands (river mile ~835). The Contracting Officer will designate which stockpiles at each of these locations are classified as granular material for use.

3.6.2 FINE FILL BORROW AREA

The Contractor shall obtain fine fill for island turf establishment from the borrow site at Upper Boulanger (river mile ~821.5). The Contracting Officer will designate which stockpiles at this location are classified as fine material for use.

3.7 MARINE STAGING AREAS

Unless otherwise approved by the Contracting Officer, the Contractor shall have a maximum of one (1) marine staging area within the project work limits. Pushing or nosing into existing project features or shallow areas with marine equipment shall be done only at sites approved by the Contracting Officer.

SECTION 01 14 00.00 13 Page 5

3.8 SLOW-NO-WAKE ZONES

The Contractor shall comply with all local restrictions for no wake zones at material loading or staging areas and access channels.

3.9 EXISTING UTILITIES

3.9.1 General

The Contractor shall coordinate all utility relocation requirements and make payment to the utility companies for all services, fees, and permits required to relocate and reestablish service. The Contractor shall be responsible for all costs related to protecting existing utilities.

3.9.2 Buried Utilities

The approximate locations of known existing buried utilities are shown on the drawings to the extent of available information at the time the drawings were prepared. Prior to commencing excavation, the Contractor shall accurately locate all such installations. The Contracting Officer shall immediately be notified if the Contractor damages any existing utility lines not intended to be removed. Repair of damaged utilities shall be in accordance with CLAUSE 52.236-9 PROTECTION OF EXISTING

VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS.

3.9.3 Interruption of Services

Utility services shall not be interrupted except for brief periods to facilitate cut-ins. The Contractor shall provide temporary service and shall relocate existing utilities as required to construct the work shown and insure uninterrupted service. If interruption of services is unavoidable, the Contractor shall request approval in writing at least 15 calendar days prior to the proposed interruption. This submittal shall fully describe all details of proposed interruption and the reasons why alternatives are not feasible. Information contained in the submittal shall include, but not be limited to, utilities being affected, duration of outage, and any sketches required to support the submittal. The Contractor shall further coordinate with the owner of the utility and notify affected consumers at least 10 calendar days in advance of interruption of services. The Contracting Officer will not in general approve proposals which require interruption of services for more than 4 continuous hours.

3.9.4 Minnesota One Call Excavation Notice System

For contract work performed within the State of Minnesota, the Contractor shall meet the requirements of Minnesota Statutes, Chapter 216D "Excavation Notice System." The Gopher State One Call notification center telephone numbers are:

Twin Cities Metro Area (651) 454-0002 Outstate (800) 252-1166

3.10 PROTECTION OF TREES

It is desired to retain as much perimeter vegetation around the borrow site as possible. No trees shall be removed without the approval of the Contracting Officer.

SECTION 01 14 00.00 13 Page 6

The Contractor shall not operate equipment in vegetated areas outside the work limits or borrow site designated in the contract documents.

3.11 FLOATING PLANT

3.11.1 Equipment and Personnel

Floating plant and personnel shall comply with the applicable U.S. Coast Guard regulations and licensing requirements. Floating plant equipment shall meet the applicable requirements of 46 CFR Chapter 1 Subchapter E 44.05-10.

3.11.2 Navigable Waters

Floating vessels operating on the Mississippi River and its tributaries must be operated in accordance with 33 CFR 207.300, "Ohio River, Mississippi River above Cairo, Ill., and their tributaries; use, administration, and navigation."

3.11.3 Sewage and Bilge Water Disposal

The Contractor's methods for disposal of sanitary sewage, and bilge water accumulated aboard floating plant, shall meet applicable local, State, and Federal requirements.

-- End of Section --

SECTION 01 14 00.00 13 Page 7

DIVISION 01 - GENERAL REQUIREMENTS
01 14 00.00 13 - WORK RESTRICTIONS
PART 1 GENERAL
1.1 MEASUREMENT AND PAYMENT
1.2 STAGING AREAS
1.2.1 Contractor Field Offices
1.2.2 Staging Area Restrictions
1.3 Pre-construction Requirement
1.4 GROUNDS AND ROADWAYS
1.4.1 Parking
1.4.2 Snow Removal

1.5 BLASTING

PART 2 PRODUCTS NOT APPLICABLE
PART 3 EXECUTION
3.1 ISLAND BERM CONSTRUCTION
3.1.1 Temporary Construction Features
3.1.2 Overwintering Seed Mix
3.2 EAGLE NEST EXCLUSION ZONE RESTRICTIONS
3.2.1 Required Bald Eagle Protection Act Avoidance Measures
3.2.2 Identification of Limits of Eagle Nest Exclusion Zone
3.3 PIGS EYE ISLAND HERON ROOKERY SCIENTIFIC AND NATURAL AREA SNA
3.4 FISHERY PROTECTION Zones - Work Exclusion Dates
3.5 ACCESS DREDGING optional
3.6 Borrow Sites
3.6.1 GRANULAR FILL BORROW AREA
3.6.2 FINE FILL BORROW AREA
3.7 MARINE STAGING AREAS
3.8 SLOW-NO-WAKE ZONES
3.9 EXISTING UTILITIES
3.9.1 General
3.9.2 Buried Utilities
3.9.3 Interruption of Services
3.9.4 Minnesota One Call Excavation Notice System
3.10 PROTECTION OF TREES
3.11 FLOATING PLANT
3.11.1 Equipment and Personnel
3.11.2 Navigable Waters
3.11.3 Sewage and Bilge Water Disposal