W912ES18T0074_Amendment_001_LD7_Rock_IDIQ.pdf
PDF 559 KB Posted
- Attached to
- LD7 Rock IDIQ Federal contract opportunity
- Solicitation number
- W912ES18T0074
About this file
Amendment 001: Scope change
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912ES18T0074_Attachments_Corrected.pdf | ||
| W912ES18T0074_LD7_Rock_IDIQ.pdf | ||
| W912ES18T0074_LD7_Rock_IDIQ.pdf | ||
| W912ES18T0074_Attachments.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W81G6781238159
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to modify the language in the SOW to clarify the type of dump trucks that may be utilized to delivery the rock.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 8
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 28-Jun-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912ES18T0074
X 9B. DATED (SEE ITEM 11)
25-Jun-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
28-Jun-2018
CODE
CONTRACTING DIVISION
USACE - ST PAUL
180 5TH STREET EAST
SUITE 700
ST. PAUL MN 55101-1678
W912ES 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912ES18T0074
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
The following have been modified:
SCOPE OF WORK
TABLE OF CONTENTS
PARAGRAPH DESCRIPTION
PART 1 GENERAL
1.1 SCOPE
1.2 APPLICABLE PUBLICATIONS
1.3 SUBMITTALS
1.4 MEASUREMENT AND PAYMENT
1.5 LIST OF ATTACHMENTS
PART 2 PRODUCTS
2.1 MATERIALS
2.2 SOURCES AND EVALUATION
2.3 TESTS FOR ACCEPTABILITY OF ALTERNATIVE SOURCE MATERIAL
2.4 RIPRAP GRADATION TESTING
PART 3 EXECUTION
3.1 SCHEDULE
3.2 COORDINATION
3.3 DELIVERY LOCATION
3.4 DELIVERY AND BARGE LOADING
3.5 QUALITY CONTROL
3.6 SAFETY
1. GENERAL.
1.1 SCOPE. The Contractor shall provide all plant labor and material necessary to furnish and deliver riprap to Lock and Dam 7 located on the right bank (when looking downstream) of the Upper Mississippi River approximately 3 miles upstream of La Crescent, Minnesota.
1.2 APPLICABLE PUBLICATIONS. The publications listed below form a part of this scope of work to the extent referenced. The publications are referred to in the text by basic designation only.
U.S. Army Corps of Engineers, Engineer Manual (EM).
EM 385-1-1 Safety and Health Requirements Manual, (30 November 2014).
1.3 SUBMITTALS
1.3.1 General. The Contractor shall submit the following as required. Approval of submittals will not relieve the Contractor of responsibility to furnish materials as required. In order to make the submittal process as efficient as possible, the Contracting Officer may give verbal responses to a submittal followed by the written response at a later date. In this case, the submittal response date will be the date that the verbal response was given.
a. Submittal Control Document (ENG Form 4288-R) as specified in PARAGRPAH 1.3.3
b. Material Source as specified in PARAGRAPH: 2.2 Sources and Evaluation
c. Method of Processing Riprap as specified in PARAGRAPH: 2.1.5 Riprap Gradation Processing
d. Gradation Test Results as specified in PARAGRAPH: 2.4 Riprap Gradation Testing
e. Plan Indicating location and schedule of Weighing Operations as specified in PARAGRAPH:
1.4.1.1.1 Measurement
f. Delivery Tickets as specified in PARAGRAPH: 1.4.1.1 Weighing Operations
g. Scale Accuracy Certification as specified in PARAGRAPH: 1.4.1 Measurement
h. Daily Delivery Report as specified in PARAGRAPH: 1.4.1.1 Weighing Operations
1.3.2 Submission of Submittals. Submittals shall be submitted to the Contracting Officer in ample time to secure approval prior to the time the items covered are to be delivered to the site. ENG Form 4025 (Attachment 5) shall be used for the transmittal of submittals. One electronic copy of all submittals shall be provided. Hard copies of submittals are generally not required unless specifically noted. The Government shall be provided at least ten working days to review a submittal unless specified otherwise.
1.3.3 Submittal Control. Within 7 calendar days after contract award date, the Contractor shall submit to the Contracting Officer for review and approval, a submittal control document (ENG Form 4288-R) in electronic format listing and scheduling all items required to be furnished for review by the Government. A blank submittal register is included in Attachment 3. Primary responsibility for submittals shall rest with the Contractor. The Contractor shall furnish submittals for all deviations from the specifications.
1.4 MEASUREMENT AND PAYMENT.
1.4.1 Measurement. Riprap shall be weighed on an accurate, approved scale furnished or made available by the Contractor. Before being approved for use, the scale shall have been tested by the applicable State’s Department of Weights and Measures or by a reliable scale servicing company so as to operate within a degree of error not greater than 1 percent and to be sensitive to a change in load of 1/5 of 1 percent, both percentages being based on the total required weight of material normally weighed as a unit on the scale. The Contractor shall submit the certification document from the appropriate state’s Department of Weights and Measures or scale servicing company that the proposed scale complies with the requirements listed above. Scales shall be spot checked for accuracy and sensitivity as often as directed by the Contracting Officer during stone delivery. When materials are weighed in hauling vehicles, gross weights shall be checked and the vehicle tare weight determined as often as the Contracting Officer directs. The Contractor shall furnish such weights, accessories, and assistance as the Contracting Officer may require for conducting weighing equipment tests.
1.4.1.1 Weighing Operations. Weighing operations shall be performed, as approved, in the presence of the
Contracting Officer, unless waived. Each load shall be accompanied by duplicate copies of delivery tickets certified by the weighmaster. As a minimum, each ticket shall contain the following information:
a. Date and Time.
b. Vehicle Number.
c. Gross Weight.
d. Vehicle Tare Weight.
e. Net Weight of Riprap.
f. Material weighed (Description of Load Contents).
g. Signature of Weighmaster.
The Government will collect a copy of the delivery ticket from each truck as it arrives on site.
The Contractor shall submit a daily report detailing the number of trucks that made deliveries to the site as well as an overall quantity of material delivered to the site that day. All daily reports shall be submitted no later than 24 hours after the report period end date and time.
1.4.1.1.1 A plan indicating the location and proposed schedule of weighing operations shall be submitted for approval in accordance with PARAGRAPH: 1.3 Submittals.
1.4.2 Payment. Riprap material shall be measured and paid for by the net ton (2,000 pounds avoirdupois) of acceptable material delivered as specified to the designated delivery site.
1.5 LIST OF ATTACHMENTS:
1 – USGS La Crescent MN 7.5 Minute Quadrangle Sheet 2 –Approved Material Sources 3 – Blank Submittal Register (ENG Form 4288-R) 4 – Gradation Forms:
R270 Riprap Gradation Curve Riprap Gradation Analysis Worksheet, Method A Riprap Gradation Analysis Worksheet, Method B
5 – Blank Submittal Transmittal Form (ENG Form 4025) 6 – Sample Submittal Register
2. PRODUCTS.
2.1 MATERIALS.
2.1.1 General. Riprap material shall be durable quarried stone of suitable quality to ensure permanence in the
Upper Mississippi River environment. Stone shall be free from cracks, seams and other defects that would unduly increase its deterioration from natural causes. A crack is considered to be detrimental if it is more than four (4) mils wide and is continuous for one-third the dimension of at least two sides of the stone.
2.1.2 Specific Gravity. All Stone shall have a specific gravity of not less than 2.55 and not more than 2.75.
2.1.3 Riprap Shape. Neither the breadth nor thickness of any individual stone shall be less than one-third its length.
2.1.4 Riprap Gradation. Riprap shall be reasonably well graded within the specified limits shown on the riprap gradation curve contained in Attachment 4 to permit construction of relatively dense riprap sections. Inclusion of objectionable quantities of dirt, sand, clay, rock fines, or other deleterious materials will not be allowed or measured for payment.
2.1.5 Riprap Gradation Processing. On the same date the Contractor provides the submittal for material sources, the Contractor shall also submit for approval the method of processing riprap at the quarry that will preclude the inclusion of objectionable amounts of fine material and organic matter. All riprap shall be processed in accordance with the approved method. Quarry-run riprap material will not be accepted. All rock designated for use as riprap shall be processed over a vibratory grizzly or by an approved method to insure the exclusion of poor quality rock.
2.2 SOURCES AND EVALUATION.
2.2.1 Approved material sources are provided in Attachment 2. The Contractor may elect to furnish rock from another source(s) not listed in Attachment 2, provided the source is approved by the Contracting Officer and meets the conditions hereinafter stated. If the Contractor proposes to furnish materials from a source not listed, the Government Geologist will make such investigations and evaluations as necessary to determine whether or not materials meeting the requirements of this contract can be produced from the proposed source. The Contractor shall be responsible for making its own investigations for sources of suitable materials and for making its own arrangements with the owners of the quarries or land for procuring the required quantities of suitable materials.
2.2.1.1 Within 7 calendar days after award of the contract, the Contractor shall designate and submit for approval only one source or combination of sources from which it proposes to furnish the materials specified. If the Contractor proposes to furnish materials from a source or from sources not listed in Attachment 2, it may designate only a single source or a single combination of sources from which to furnish the material specified. Samples for acceptability testing shall be provided as required by the PARAGRAPH: 2.3 Tests for Acceptability of Alternative Source Material. If a source for materials so designated by the Contractor is not approved for use by the Contacting Officer, the Contractor shall not submit for approval other sources but shall furnish the materials from approved sources selected from the list in Attachment 2, at no additional cost to the Government.
2.2.1.2 Approval of a source of material is not to be construed as approval of all material from that source. The right is reserved by the Government to reject materials from certain localized areas, zones, strata, or channels when such material are unsuitable as determined by the Government Geologist. Materials produced from an approved source shall meet all of the requirements of this specification.
2.2.2 No riprap material shall be used from any river facing bluffs that are visible from the Mississippi
River.
2.3 TESTS FOR ACCEPTABILITY OF ALTERNATIVE SOURCE MATERIAL.
2.3.1 Quality tests and service records will be used to determine the acceptability of stone materials. In the event suitable test reports and satisfactory service records are not available, as in the case of newly operated sources, the materials will be tested to determine acceptability. Tests to which the materials may be subjected to include petrographic analysis, specific gravity, soundness, abrasion, absorption, freezing and thawing, and other tests considered necessary to demonstrate acceptability. Tests will be made by, or under the supervision of, the Government and at the Government’s expense.
2.3.2 Samples. When directed by the Contracting Officer, suitable samples of materials shall be submitted for approval prior to delivery of materials to the work site. Samples shall be obtained by the Contractor, in the presence of the Contracting Officer or its designated representative, and delivered at the Contractor’s expense to a point designated by the Contracting Officer, at least 15 calendar days in advance of the date that the material is required to be delivered.
2.4 RIPRAP GRADATION TESTING.
2.4.1 General Requirements. Gradation tests shall be performed by the methods and frequency listed below.
Testing listed herein shall be completed by and at the expense of the Contractor. Gradation testing results shall be submitted utilizing the gradation plots for the required riprap gradation and the WORKSHEET FOR GRADATION ANALYSIS OF RIPRAP (gradation plots and blank copies of the worksheet are included in the attachments section). The Contracting Officer shall direct the time and location of sampling, unless waived. The Contracting Officer shall be informed a minimum of 24 hours before each test is to be performed. The results of all tests, including failing tests shall be submitted on the appropriate gradation plots and worksheets. The Contracting Officer shall be informed immediately of test results and draft copies of test results shall be submitted at the Contracting Officers request. Tests performed on material that does not meet gradation and shape requirements will not be counted as part of the tests required.
2.4.2 Test Method A. Test method A shall consist of weighing all stones larger than 5 pounds in a sample.
Five to seven weight classes shall be selected within the range of stone sizes. Each stone shall be weighed and recorded on the worksheet for method A. The weight of stones shall be summed for each weight class; after which calculations and a plot of the gradation shall be completed in accordance with accepted practice for soil and aggregate gradations.
2.4.3 Test Method B. Test method B shall consist of separating the stones into 5 to 7 piles, ordered by size.
The sample shall be separated on a clean, hard surface that is free of smaller stones that could become mixed with the sample. The stones shall be visually screened to place them into appropriate piles. All stones shall be separated and placed into a pile before weighing. After separating, the smallest and the largest rock in each pile shall be weighed and recorded. The stones shall be adjusted as necessary so that the weight classes do not overlap. After adjustment is adequate and weight classes have been established, each pile of stone shall be weighed and recorded on the worksheet for method B.
Calculations and a plot of the gradation shall be completed in accordance with accepted practice for soil and aggregate gradations.
2.4.4 Scales. Accuracy of scales shall be as required in PARAGRAPH: 1.4.1 Measurement.
2.4.5 Testing. A sample shall be obtained from each approved material source or combination of sources for each gradation required and tested in accordance with either method A or B. A satisfactory test shall be obtained from each source or combination of sources for each gradation prior to hauling any riprap from that quarry. Each sample shall have a minimum gross weight of not less than 25 times the maximum stone size in the specified gradation (25∙W100).
2.4.6 Testing Frequency. Gradation tests will be required at a frequency of 1 per 5,000 tons of each gradation of material from a specific source that is brought on site, with a minimum of one test per gradation. Tests that do not meet gradation requirements will not be counted.
2.4.7 Corrective Action. If materials fail to meet gradation or shape requirements, the Contractor shall adjust its operations and verify with necessary tests that acceptable materials are being produced, or it shall propose another source and verify, with necessary tests, that acceptable material can be produced from that source.
3. EXECUTION.
3.1 SCHEDULE AND ORDERING. The Contracting Officer will notify the Contractor 15 calendar days in advance of when delivery is to commence by issuing a Delivery Order to the Contractor. The Delivery Order will state the quantity of rock to be delivered. The Contractor shall provide the riprap gradation submittals for approval no later than 7 calendar days prior to delivery of materials to the specified delivery location. It is anticipated that commencement of delivery will occur between the dates of 4 September and 1 December 2018. Delivery shall commence no later than 15 calendar days following issuance of the Delivery Order and shall continue on consecutive work days (Monday through Thursday) until completed, unless directed otherwise by the Contracting Officer. The delivery period shall be between the hours of 7:30 a.m. and 5:00 p.m. (local time), Monday through Thursday with the potential for Friday deliveries, unless directed otherwise by the Contracting Officer. No deliveries shall be made on weekends or on Federal holidays. Only the Contracting Officer may issue Delivery Orders under this contract.
3.2 COORDINATION. The Contractor shall not block access to the loading docks or access routes at the on-land delivery sites for extended periods of time and shall coordinate loading access routes and dock use with the following:
Mr. Christopher Stai Chief, Maintenance and Repair
651.290.5144 (office) 612.790.2675(mobile) Christopher.J.Stai@usace.army.mil
Michael Gunderson Foreman/Site Supervisor
651.290.5145 (office)
612.670.2880 (mobile) mailto:Michael.G.Gunderson@usace.army.mil
3.3 DELIVERY LOCATION. All riprap required under this contract shall be delivered to the downstream loading dock at Lock and Dam 7. Lock and Dam 7 is located on the right descending bank of the Mississippi River in Winona County, Minnesota approximately three miles upstream of La Crescent, Minnesota. Lock and Dam 7 is located on the USGS La Crescent 7.5 Minute Quadrangle. This 7.5 minute quadrangle sheet is included as Attachment 1. The center of the loading dock is further specified as the following Military Grid Reference System (MGRS) Grid Coordinate:
15T XJ 35905 58167
The Lock 7 downstream loading dock is located approximately one half mile upstream from the U.S.
Interstate I-90 Mississippi River Bridge.
3.4 DELIVERY AND BARGE LOADING. Delivery of riprap by the Contractor shall include placing material directly from the delivery trucks into a stockpile area on site and/or loading directly from the delivery trucks onto U.S. Government-owned barges. Each barge on which riprap material is to be loaded will have a capacity of 200 tons, with a 20 foot by 85 foot holding area with 2.5 foot high side barriers, with ramps that can be used to drive the delivery trucks directly onto the barges. The barges and access ramps will be maneuvered by Government Personnel. Government personnel and equipment will stockpile material. The Contractor shall provide all other equipment and personnel needed to place the riprap directly onto the barges, except that no secondary loading or repositioning of riprap will be required after the riprap has been dumped from the delivery trucks. The Contracting Officer will direct the Contractor where to unload riprap.
3.4.1 Loading Riprap. Delivery trucks used by the Contractor for loading riprap onto barges or stockpiles shall be straight tandem dump trucks with maximum 18 ton capacity; use of articulated end-dump trailers, side dump, or belly dump trailers will not be allowed.
Delivery trucks used by the Contractor for loading riprap onto barges or stockpiles shall be straight tandem, tri, or quad axle dump trucks with maximum 18 ton capacity. If the maximum capacity of a straight tandem, tri, or quad axle dump truck is greater than 18 tons, it may only be loaded with up to a maximum of 18 tons of cargo. The use of articulated end-dump trailers, side dump, or belly dump trailers will not be allowed. The Contracting Officer reserves the right to reject delivery from any truck that cannot safely discharge its cargo at the point of delivery or adversely affects the stability of the floating plant.
3.4.2 Delivery Rate. The riprap material delivery rate will vary between 100 tons and 800 tons per day, as requested by the Contracting Officer’s Representative. The Contractor shall be required to increase or decrease the delivery rate within the above stated delivery rate range on a daily basis until the required quantity of material is met.
3.5 QUALITY CONTROL. The Contractor shall establish and maintain quality control and shall maintain records of the quality control for work under this section to ensure compliance with contract requirements.
A copy of inspections and tests, as well as corrective actions taken, shall be furnished to the Government.
3.6 SAFETY. The Contractor shall comply with all state and Federal OSHA requirements as well as all pertinent provisions of the latest version of the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1. If a conflict exists between the guidance provided between the sources listed above, the Contractor shall follow the most stringent standard given. A current copy of EM 385-1-1 can be found at https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf
PROTECTION OF GOVERNMENT BUILDINGS, EQUIPMENT, AND VEGETATION. The Contractor shall use reasonable care to avoid damaging existing structures, equipment, and vegetation on the Government site. This contract may require delivery on Government owned barges. Reasonable care shall be used in the loading of material on Government barges as to not damage the barge, barriers, or ramps in the process of unloading material.
If the Contractor’s failure to use reasonable care causes damage to any of this property, the Contractor shall replace or repair the damage at no expense to the Government as the Contracting Officer directs. If the Contractor fails or refuses to make such repair or replacement, the Contractor shall be liable for the cost, which may be deducted from the contract price.