Amendment W912EK21T0024-0002.pdf

PDF 118 KB Posted

Attached to
Upgrades to Direct Digital Control System (DDCS) Federal contract opportunity
Solicitation number
W912EK21T0024
Issued by
Department of the Army Corps of Engineers Engineering District Rock Island

View the file

Other files for this federal contract opportunity

Other files attached to Upgrades to Direct Digital Control System (DDCS), newest first.
File Type Posted
Amendment W912EK21T0024-0001.pdf PDF
AHU-205-2-1 Drawings.pdf PDF
Solicitation W912EK21T0024.pdf PDF
AHU-205-1-1 Drawings.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

96514710922463

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

The Purpose of Amendment 0002 to Solicitation W912EK21T0024 is to incorporate the Goverment answ er to a Contractor Question.

All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 20-May-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EK21T0024

X 9B. DATED (SEE ITEM 11)

07-May-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

20-May-2021

CODE

CONTRACTING DIVISION

US ARMY CORPS OF ENGINEERS 1500 ROCK ISLAND D

ROCK ISLAND IL 61201

W912EK 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EK21T0024

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

AMENDMENT 0002

Contractor Q&A

Question 1: It appears in the specs that this upgrade to the DDC system is for the new equipment being updated. I am not sure if there is an existing head end software system on site, but the specs mention Niagara. Does the new system need to tie into the existing or are you looking for new controls including new head end software?

Answer 1: The existing building automation system (BAS) in the Clock Tower Annex complex consist of a Niagara Jace with BACnet, Lon, and Proprietary Robert Shaw controller/hardware. The purpose of this project is to eliminate the obsolete, Proprietary Robert

Shaw controllers and its associated communication bus. The project involves replacing obsolete, proprietary Robert Shaw controls in three locations. The controller in the Basement of the Clock

Tower building controls the building rest room exhaust fans and has a space temperature sensor attached to it. The control of the exhaust fan is to be moved to an existing spare Binary Output in a BACnet controller (MNB-300) located in the basement. The controller on the First Floor of the Clock Tower operates an existing VAV AHU. The details of I/O and programming requirements are laid out on the drawings. The controller on the Second Floor of the Clock

Tower operates an existing VAV AHU. The details of I/O and programming requirements are laid out on the drawings. The existing BACnet MSTP Bus is to be modified to add the new controllers for the VAV AHU’s located on the First and Second floors. The contractor shall provide programming of the new hardware and integrate the new controller data into the existing

JACE. The graphic screens in the JACE shall be updated to properly link the new control hardware to the existing BAS. As long as the new hardware installed can be programmed thru the existing programming tools (Workplace Tech suite) loaded on the operator work station, the contractor is not required to provide additional software. A site visit is highly recommended in order for the contractor to see the existing BAS, Niagara Screens, and OWS.

File details come from the government source that posted it. Updated .