Site Visit Info W912EF20B0009.pdf

PDF 229 KB Posted

Attached to
Mill Creek Maintenance Building Interior Federal contract opportunity
Solicitation number
W912EF20B0009
Issued by
Department of the Army Corps of Engineers Engineering District Walla Walla

About this file

This document contains details for a federal construction solicitation for interior renovations to a maintenance building near Walla Walla, Washington. The solicitation will be issued by the U.S. Army Corps of Engineers Walla Walla District as an invitation for bids for a firm fixed-price contract. Scope of work includes construction of interior walls, electrical and lighting work, installation of HVAC systems, plumbing, and other interior finishes. Exterior work includes demolition and construction of an asphalt roadway and drainage improvements. The estimated construction value is between $250,000-$500,000. The solicitation is designated as a women-owned small business set-aside with a response deadline approximately 30 days after posting to beta.sam.gov in late May 2020. The apparent low bidder must submit responsibility criteria and performance and payment bonds will be required.

View the file

Other files for this federal contract opportunity

Other files attached to Mill Creek Maintenance Building Interior, newest first.
File Type Posted
B.08.02 20B0009_Plans.pdf PDF
B.08.02 20B0009_TechSpecs.pdf PDF
B.08.02 Solicitation W912EF20B0009.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912EF20B0009

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from Walla Walla US Army Corps of Engineers, Contracting Division, 201 North 3rd, Walla Walla, Washington 99362- 1876.

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of provision)

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

27 August 2020 starting at 8:00 a.m. and ending at 4:00 p.m. Registered firms will be assigned a specific time.

USACE Mill Creek Project Office 3211 Reservoir Rd Walla Walla, WA 99362

There will be only one site visit offered. Offerors planning to attend must register for the site by sending an email to: david.c.boone@usace.army.mil

Firms must register no later than the day before the site visit.

Site visit attendees must provide the following information: 1) Solicitation Number; 2) Project Title; 3) Names of individuals who will attend the site visit; 4) a statement as to whether the individual is a US citizen. If not a US citizen, please refer to ACCESS FOR FOREIGN NATIONALS in Section 00 73 00 of this document; 5) Name of company being represented 6) Phone number of company being represented. All firms MUST register not later than 5:00 PM local time on 25 August 2020 by email to Mr. David Boone at david.c.boone@usace.army.mil.

Registered firms will be notified not later than 5:00 PM local time on 26 August 2020 of the specific date and time allocated for their site visit. Maximum duration of site visit is two hours.

Each individual attending the site visit must submit the Center for Disease Control (CDC) Active Screening questionnaire not later than 5:00 PM local time on 24 August 2020. Registered attendees that have not provided a completed questionnaire will not be permitted on-site due to ongoing COVID-19 concerns.

Each firm is allowed no more than three attendees for the site visit due to size of gathering restrictions. Once all locations have been visited, potential offerors will be escorted back to the Main Gate security desk and the site visit walkthrough is complete. To ensure consistent information is shared among all potential offerors, all questions must be submitted through the ProjNet bidder inquiry process outlined in this solicitation. No questions will be answered at the site visit.

Each individual attending the site visit must have picture identification on his/her person while at the project site.

There can be no substitutions of one individual for another. If an individual arrives at the site visit without having registered and/or without having picture identification, that individual may not be allowed on the site.

W912EF20B0009

Participants of site visits must abide by the U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1, latest version) in accordance with Section 5, “Personal Protective and Safety Equipment. (PPE)” It is the responsibility of participants to wear personal protective and safety equipment as required by this regulation.

Failure to comply could result in denial of access to site visit location.

All attendees must follow federal, state, and local guidelines for the mitigation of COVID 19 when attending this site visit. Please ensure all attendees have PPE with them in order to comply with COVID 19 mitigation measures.

The ACCESS FOR FOREIGN NATIONALS requirement in Section 00 73 00 applies to site visits as well as to performance of the work.

Site Visit Guidelines:

The RSVP Cut-off date is 25 Aug 2020 at 5:00pm to allow team to ensure enough Government staff is present to support.

Appropriate masks will be required at all times while on site.

Start times will be assigned and are staggered starting at 8:00 am. Length of site visit is estimated to be 1 hour.

Government staff will read the script (Description of the project).

No questions will be answered during site visit.

Completion and submission of the CDC Active Screening Questionnaire by each attendee prior to travel is required (see CDC Active Screening Questionnaire attachment provided with the solicitation). The Government will not be answering any questions during the walkthrough. Potential offerors will be allowed to take equipment specific pictures and measurements of equipment that is along the predetermined pathway only.

Once site visit is complete, contractor attendees will be escorted back to the Visitor Center and the site visit walkthrough is complete.

To ensure consistent information is shared among all potential offerors, all questions must be submitted through the ProjNet bidder inquiry process outlined in the solicitation.

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov/

File details come from the government source that posted it. Updated .