Amendment_0003.pdf
PDF 1011 KB Posted
- Attached to
- Emergency Sluice Gate Bulkhead, Libby Dam, Libby, MT Federal contract opportunity
- Solicitation number
- W912DW19R0016
About this file
Amendment 0003
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_0002.pdf | ||
| W912DW19R0016_Amendment_0001.pdf | ||
| Request_for_Visitation_Authority_(RVA).pdf | ||
| Libby_Emergency_Sluice_Gate_FINAL_Contract_Drawings.pdf | ||
| Libby_Emergency_Sluice_Gate_Reference_Drawings.pdf | ||
| W912DW19R0016.pdf | ||
| Libby_Emergency_Sluice_Gate_-_Attachment_A_-_Eval_Criteria.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Amendment 0003
(Please see continuation sheet)
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 04-Jun-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DW19R0016
X 9B. DATED (SEE ITEM 11)
08-May-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
04-Jun-2019
CODE
USA ENGINEER DISTRICT, SEATTLE
ATTN: CENWS-CT
4735 EAST MARGINAL WAY SOUTH, BLDG. 1202
SEATTLE WA 98134-2388
W912DW 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DW19R0016
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0003
1. This amendment provides for the following changes:
a. Includes Gate Repair Pit As-Built Drawings
2. Attached are currently available answers to bidder inquiries.
3. The bid submittal time and date of 10 June 2019 at 1:00 PM PT is NOT CHANGED.
4. NOTICE: Bidders must acknowledge receipt of this amendment by number and date on offer.
Attch:
Answers to bidder inqueries Gate Repair Pit As-Built Drawings
(End of Summary of Changes)
1) In reviewing the supplied reference drawings, we do not see any as‐builts of the gate repair pit;
and a tour of the repair pit was not offered during the scheduled site visit. Please provide as‐ built drawings (Plan & Sectional Views) of the gate repair pit so contractor can determine if there are any potential issues with being able to perform final assembly on site. Specifically the upper ballast assemblies.
a. As‐Builts of gate repair pit are included in this amendment.
| Gate Repair Pit As Builts.pdf |
| A024 Non-Overflow Monos 14 to 19 Plan, Elevation & Sections |
| A025 Non-Overflow Monos 14 to 19 Elevation & Sections |
| A045 Non-Overflow Monos - Details XIII |
| A046 Non-Overflow Monos - Details XIV |
File details come from the government source that posted it.