G24_Bid_Abstract_.xlsx
XLSX spreadsheet 17 KB Posted
- Attached to
- JJRTC Paving Repair Federal contract opportunity
- Solicitation number
- W912DR-16-B-0023
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912DR-16-B-0025-0005.pdf | ||
| W912DR-16-B-0023-0004.pdf | ||
| W912DR-16-B-0023-0003.pdf | ||
| W912DR-16-B-0023-0002.pdf | ||
| W912DR-16-B-0023-0001.pdf | ||
| A2_Plans_and_Specs.pdf | ||
| W912DR-16-B-0023.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Chart1
| SERVICE | All costs in connection with the Mill and Overlay (2”)Removal at Merletti | ||||||||||||||||||||||||||||||||||||||||||||||
| Parking Lot complet | All costs in connection with the Mill and Overlay (2”)Removal at other areas complete as shown and specified | All costs in connection with the Mill and replace full pavement depth at Merletti Parking Lot and other areas complete as shown and specified. | All costs in connection with the stabilization with full stone base reconstruction where required complete as shown on drawings and specified. | All costs in connection with the Sidewalk and Curb Reconstruction at Merletti Lot complete as shown on drawings and specified. | All costs in connection with Protective Operations Driving Course (PODC) striping complete as shown and specified | All costs in connection with the PODC sealing complete as shown and specified | All costs in connection with the new concrete pavement behind the Wilson Bldg. complete as shown and specified | All costs in connection with the Mill and Overlay (2”)Removal complete as shown and specified | All costs in connection with the Mill and replace full pavement depth complete as shown and specified. | All costs in connection with the stabilization with full stone base in place where required complete as shown on drawings and specified | All costs in connection with the Sidewalk and Curb Reconstruction complete as shown on drawings and specified. | TOTAL = | PERCENT ABOVE/BELOW IGE = | AMOUNT OVER IGE = | BID ABSTRACT FOR W912DR-16-B-0023 JJRTC Paving Repair | LOCATION: Laurel, MD | LINE | CLIN 0001 | CLIN 0002 | CLIN 0003 | CLIN 0004 | CLIN 0005 | CLIN 0006 | CLIN 0007 | CLIN 0008 | CLIN 0009 | CLIN 0010 | CLIN 0011 | CLIN 0012 | 0 | 385571 | 582584 | 420532 | 17900 | 34072 | 5524 | 124799 | 43059 | 862416 | 778607 | 325968 | 34072 | 3615104 | SERVICE | All costs in connection with the Mill and Overlay (2”)Removal at Merletti | ||
| Parking Lot complet | All costs in connection with the Mill and Overlay (2”)Removal at other areas complete as shown and specified | All costs in connection with the Mill and replace full pavement depth at Merletti Parking Lot and other areas complete as shown and specified. | All costs in connection with the stabilization with full stone base reconstruction where required complete as shown on drawings and specified. | All costs in connection with the Sidewalk and Curb Reconstruction at Merletti Lot complete as shown on drawings and specified. | All costs in connection with Protective Operations Driving Course (PODC) striping complete as shown and specified | All costs in connection with the PODC sealing complete as shown and specified | All costs in connection with the new concrete pavement behind the Wilson Bldg. complete as shown and specified | All costs in connection with the Mill and Overlay (2”)Removal complete as shown and specified | All costs in connection with the Mill and replace full pavement depth complete as shown and specified. | All costs in connection with the stabilization with full stone base in place where required complete as shown on drawings and specified | All costs in connection with the Sidewalk and Curb Reconstruction complete as shown on drawings and specified. | TOTAL = | PERCENT ABOVE/BELOW IGE = | AMOUNT OVER IGE = | BID ABSTRACT FOR W912DR-16-B-0023 JJRTC Paving Repair | LOCATION: Laurel, MD | LINE | CLIN 0001 | CLIN 0002 | CLIN 0003 | CLIN 0004 | CLIN 0005 | CLIN 0006 | CLIN 0007 | CLIN 0008 | CLIN 0009 | CLIN 0010 | CLIN 0011 | CLIN 0012 | 0 | 254444.85 | 385052.25 | 367953.3 | 46215 | 38000 | 3750 | 51420 | 24000 | 553052.5 | 657828.6 | 654563 | 38000 | 3074279.5 | 0.14960136693162907 | -540824.5 | SERVICE | All costs in connection with the Mill and Overlay (2”)Removal at Merletti |
| Parking Lot complet | All costs in connection with the Mill and Overlay (2”)Removal at other areas complete as shown and specified | All costs in connection with the Mill and replace full pavement depth at Merletti Parking Lot and other areas complete as shown and specified. | All costs in connection with the stabilization with full stone base reconstruction where required complete as shown on drawings and specified. | All costs in connection with the Sidewalk and Curb Reconstruction at Merletti Lot complete as shown on drawings and specified. | All costs in connection with Protective Operations Driving Course (PODC) striping complete as shown and specified | All costs in connection with the PODC sealing complete as shown and specified | All costs in connection with the new concrete pavement behind the Wilson Bldg. complete as shown and specified | All costs in connection with the Mill and Overlay (2”)Removal complete as shown and specified | All costs in connection with the Mill and replace full pavement depth complete as shown and specified. | All costs in connection with the stabilization with full stone base in place where required complete as shown on drawings and specified | All costs in connection with the Sidewalk and Curb Reconstruction complete as shown on drawings and specified. | TOTAL = | PERCENT ABOVE/BELOW IGE = | AMOUNT OVER IGE = | BID ABSTRACT FOR W912DR-16-B-0023 JJRTC Paving Repair | LOCATION: Laurel, MD | LINE | CLIN 0001 | CLIN 0002 | CLIN 0003 | CLIN 0004 | CLIN 0005 | CLIN 0006 | CLIN 0007 | CLIN 0008 | CLIN 0009 | CLIN 0010 | CLIN 0011 | CLIN 0012 | 0 | 1572000 | 275000 | 177000 | 28000 | 28000 | 130000 | 2210000 | -5.9952038369304558E-2 | -125000 | SERVICE | All costs in connection with the Mill and Overlay (2”)Removal at Merletti | ||||||
| Parking Lot complet | All costs in connection with the Mill and Overlay (2”)Removal at other areas complete as shown and specified | All costs in connection with the Mill and replace full pavement depth at Merletti Parking Lot and other areas complete as shown and specified. | All costs in connection with the stabilization with full stone base reconstruction where required complete as shown on drawings and specified. | All costs in connection with the Sidewalk and Curb Reconstruction at Merletti Lot complete as shown on drawings and specified. | All costs in connection with Protective Operations Driving Course (PODC) striping complete as shown and specified | All costs in connection with the PODC sealing complete as shown and specified | All costs in connection with the new concrete pavement behind the Wilson Bldg. complete as shown and specified | All costs in connection with the Mill and Overlay (2”)Removal complete as shown and specified | All costs in connection with the Mill and replace full pavement depth complete as shown and specified. | All costs in connection with the stabilization with full stone base in place where required complete as shown on drawings and specified | All costs in connection with the Sidewalk and Curb Reconstruction complete as shown on drawings and specified. | TOTAL = | PERCENT ABOVE/BELOW IGE = | AMOUNT OVER IGE = | BID ABSTRACT FOR W912DR-16-B-0023 JJRTC Paving Repair | LOCATION: Laurel, MD | LINE | CLIN 0001 | CLIN 0002 | CLIN 0003 | CLIN 0004 | CLIN 0005 | CLIN 0006 | CLIN 0007 | CLIN 0008 | CLIN 0009 | CLIN 0010 | CLIN 0011 | CLIN 0012 | SERVICE | All costs in connection with the Mill and Overlay (2”)Removal at Merletti | ||||||||||||||||
| Parking Lot complet | All costs in connection with the Mill and Overlay (2”)Removal at other areas complete as shown and specified | All costs in connection with the Mill and replace full pavement depth at Merletti Parking Lot and other areas complete as shown and specified. | All costs in connection with the stabilization with full stone base reconstruction where required complete as shown on drawings and specified. | All costs in connection with the Sidewalk and Curb Reconstruction at Merletti Lot complete as shown on drawings and specified. | All costs in connection with Protective Operations Driving Course (PODC) striping complete as shown and specified | All costs in connection with the PODC sealing complete as shown and specified | All costs in connection with the new concrete pavement behind the Wilson Bldg. complete as shown and specified | All costs in connection with the Mill and Overlay (2”)Removal complete as shown and specified | All costs in connection with the Mill and replace full pavement depth complete as shown and specified. | All costs in connection with the stabilization with full stone base in place where required complete as shown on drawings and specified | All costs in connection with the Sidewalk and Curb Reconstruction complete as shown on drawings and specified. | TOTAL = | PERCENT ABOVE/BELOW IGE = | AMOUNT OVER IGE = | BID ABSTRACT FOR W912DR-16-B-0023 JJRTC Paving Repair | LOCATION: Laurel, MD | LINE | CLIN 0001 | CLIN 0002 | CLIN 0003 | CLIN 0004 | CLIN 0005 | CLIN 0006 | CLIN 0007 | CLIN 0008 | CLIN 0009 | CLIN 0010 | CLIN 0011 | CLIN 0012 | SERVICE | All costs in connection with the Mill and Overlay (2”)Removal at Merletti | ||||||||||||||||
| Parking Lot complet | All costs in connection with the Mill and Overlay (2”)Removal at other areas complete as shown and specified | All costs in connection with the Mill and replace full pavement depth at Merletti Parking Lot and other areas complete as shown and specified. | All costs in connection with the stabilization with full stone base reconstruction where required complete as shown on drawings and specified. | All costs in connection with the Sidewalk and Curb Reconstruction at Merletti Lot complete as shown on drawings and specified. | All costs in connection with Protective Operations Driving Course (PODC) striping complete as shown and specified | All costs in connection with the PODC sealing complete as shown and specified | All costs in connection with the new concrete pavement behind the Wilson Bldg. complete as shown and specified | All costs in connection with the Mill and Overlay (2”)Removal complete as shown and specified | All costs in connection with the Mill and replace full pavement depth complete as shown and specified. | All costs in connection with the stabilization with full stone base in place where required complete as shown on drawings and specified | All costs in connection with the Sidewalk and Curb Reconstruction complete as shown on drawings and specified. | TOTAL = | PERCENT ABOVE/BELOW IGE = | AMOUNT OVER IGE = | BID ABSTRACT FOR W912DR-16-B-0023 JJRTC Paving Repair | LOCATION: Laurel, MD | LINE | CLIN 0001 | CLIN 0002 | CLIN 0003 | CLIN 0004 | CLIN 0005 | CLIN 0006 | CLIN 0007 | CLIN 0008 | CLIN 0009 | CLIN 0010 | CLIN 0011 | CLIN 0012 | 1 | SERVICE | All costs in connection with the Mill and Overlay (2”)Removal at Merletti | |||||||||||||||
| Parking Lot complet | All costs in connection with the Mill and Overlay (2”)Removal at other areas complete as shown and specified | All costs in connection with the Mill and replace full pavement depth at Merletti Parking Lot and other areas complete as shown and specified. | All costs in connection with the stabilization with full stone base reconstruction where required complete as shown on drawings and specified. | All costs in connection with the Sidewalk and Curb Reconstruction at Merletti Lot complete as shown on drawings and specified. | All costs in connection with Protective Operations Driving Course (PODC) striping complete as shown and specified | All costs in connection with the PODC sealing complete as shown and specified | All costs in connection with the new concrete pavement behind the Wilson Bldg. complete as shown and specified | All costs in connection with the Mill and Overlay (2”)Removal complete as shown and specified | All costs in connection with the Mill and replace full pavement depth complete as shown and specified. | All costs in connection with the stabilization with full stone base in place where required complete as shown on drawings and specified | All costs in connection with the Sidewalk and Curb Reconstruction complete as shown on drawings and specified. | TOTAL = | PERCENT ABOVE/BELOW IGE = | AMOUNT OVER IGE = | BID ABSTRACT FOR W912DR-16-B-0023 JJRTC Paving Repair | LOCATION: Laurel, MD | LINE | CLIN 0001 | CLIN 0002 | CLIN 0003 | CLIN 0004 | CLIN 0005 | CLIN 0006 | CLIN 0007 | CLIN 0008 | CLIN 0009 | CLIN 0010 | CLIN 0011 | CLIN 0012 | 1 | SERVICE | All costs in connection with the Mill and Overlay (2”)Removal at Merletti | |||||||||||||||
| Parking Lot complet | All costs in connection with the Mill and Overlay (2”)Removal at other areas complete as shown and specified | All costs in connection with the Mill and replace full pavement depth at Merletti Parking Lot and other areas complete as shown and specified. | All costs in connection with the stabilization with full stone base reconstruction where required complete as shown on drawings and specified. | All costs in connection with the Sidewalk and Curb Reconstruction at Merletti Lot complete as shown on drawings and specified. | All costs in connection with Protective Operations Driving Course (PODC) striping complete as shown and specified | All costs in connection with the PODC sealing complete as shown and specified | All costs in connection with the new concrete pavement behind the Wilson Bldg. complete as shown and specified | All costs in connection with the Mill and Overlay (2”)Removal complete as shown and specified | All costs in connection with the Mill and replace full pavement depth complete as shown and specified. | All costs in connection with the stabilization with full stone base in place where required complete as shown on drawings and specified | All costs in connection with the Sidewalk and Curb Reconstruction complete as shown on drawings and specified. | TOTAL = | PERCENT ABOVE/BELOW IGE = | AMOUNT OVER IGE = | BID ABSTRACT FOR W912DR-16-B-0023 JJRTC Paving Repair | LOCATION: Laurel, MD | LINE | CLIN 0001 | CLIN 0002 | CLIN 0003 | CLIN 0004 | CLIN 0005 | CLIN 0006 | CLIN 0007 | CLIN 0008 | CLIN 0009 | CLIN 0010 | CLIN 0011 | CLIN 0012 | SERVICE | All costs in connection with the Mill and Overlay (2”)Removal at Merletti | ||||||||||||||||
| Parking Lot complet | All costs in connection with the Mill and Overlay (2”)Removal at other areas complete as shown and specified | All costs in connection with the Mill and replace full pavement depth at Merletti Parking Lot and other areas complete as shown and specified. | All costs in connection with the stabilization with full stone base reconstruction where required complete as shown on drawings and specified. | All costs in connection with the Sidewalk and Curb Reconstruction at Merletti Lot complete as shown on drawings and specified. | All costs in connection with Protective Operations Driving Course (PODC) striping complete as shown and specified | All costs in connection with the PODC sealing complete as shown and specified | All costs in connection with the new concrete pavement behind the Wilson Bldg. complete as shown and specified | All costs in connection with the Mill and Overlay (2”)Removal complete as shown and specified | All costs in connection with the Mill and replace full pavement depth complete as shown and specified. | All costs in connection with the stabilization with full stone base in place where required complete as shown on drawings and specified | All costs in connection with the Sidewalk and Curb Reconstruction complete as shown on drawings and specified. | TOTAL = | PERCENT ABOVE/BELOW IGE = | AMOUNT OVER IGE = | BID ABSTRACT FOR W912DR-16-B-0023 JJRTC Paving Repair | LOCATION: Laurel, MD | LINE | CLIN 0001 | CLIN 0002 | CLIN 0003 | CLIN 0004 | CLIN 0005 | CLIN 0006 | CLIN 0007 | CLIN 0008 | CLIN 0009 | CLIN 0010 | CLIN 0011 | CLIN 0012 |
Sheet1 BID ABSTRACT FOR W912DR-16-B-0023 JJRTC Paving Repair
| LOCATION: Laurel, MD | ||||
| LINE | SERVICE | IGE | Ribeiro | Blanchard |
| CLIN 0001 | All costs in connection with the Mill and Overlay (2”)Removal at Merletti | ||||
| Parking Lot complet | $385,571.00 | $254,444.85 | $269,470.00 | ||
| CLIN 0002 | All costs in connection with the Mill and Overlay (2”)Removal at other areas complete as shown and specified | $582,584.00 | $385,052.25 | $388,377.00 | |
| CLIN 0003 | All costs in connection with the Mill and replace full pavement depth at Merletti Parking Lot and other areas complete as shown and specified. | $420,532.00 | $367,953.30 | $408,057.00 | |
| CLIN 0004 | All costs in connection with the stabilization with full stone base reconstruction where required complete as shown on drawings and specified. | $17,900.00 | $46,215.00 | $94,967.00 | |
| CLIN 0005 | All costs in connection with the Sidewalk and Curb Reconstruction at Merletti Lot complete as shown on drawings and specified. | $34,072.00 | $38,000.00 | $53,489.00 | |
| CLIN 0006 | All costs in connection with Protective Operations Driving Course (PODC) striping complete as shown and specified | $5,524.00 | $3,750.00 | $27,562.00 | |
| CLIN 0007 | All costs in connection with the PODC sealing complete as shown and specified | $124,799.00 | $51,420.00 | $84,070.00 | |
| CLIN 0008 | All costs in connection with the new concrete pavement behind the Wilson Bldg. complete as shown and specified | $43,059.00 | $24,000.00 | $66,326.00 | |
| CLIN 0009 | All costs in connection with the Mill and Overlay (2”)Removal complete as shown and specified | $862,416.00 | $553,052.50 | $539,049.00 | |
| CLIN 0010 | All costs in connection with the Mill and replace full pavement depth complete as shown and specified. | $778,607.00 | $657,828.60 | $735,161.00 | |
| CLIN 0011 | All costs in connection with the stabilization with full stone base in place where required complete as shown on drawings and specified | $325,968.00 | $654,563.00 | $677,016.00 | |
| CLIN 0012 | All costs in connection with the Sidewalk and Curb Reconstruction complete as shown on drawings and specified. | $34,072.00 | $38,000.00 | $477,992.00 | |
| TOTAL = | $3,615,104.00 | $3,074,279.50 | $3,821,536.00 | ||
| PERCENT ABOVE/BELOW IGE = | 14.96% | -5.71% | |||
| AMOUNT OVER IGE = | -$540,824.50 | $206,432.00 |