W912CL20R0003 Att. 4 DD254.pdf
PDF 139 KB Posted
- Attached to
- Apiay Base Operations Support Services Federal contract opportunity
- Solicitation number
- W912CL-20-R-0003
About this file
This document provides an independent government cost estimate (IGCE) for base operations support services at Luis Gomez Nino Air Base in Colombia under solicitation number W912CL-20-R-0003 issued by the Department of the Army Materiel Command Army Contracting Command. The total estimated cost over five years is $2,539,240.25, which includes a base year of $276,346.60 plus four option years with escalating costs of $532,888.93, $554,204.49, $576,372.66, and $599,427.57 respectively. The services required include repair and maintenance of facilities and equipment, grounds maintenance, housekeeping, janitorial services, administrative support, property accountability, cargo movement, and management of billeting facilities at the 94-room operational support complex.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912CL20R0003 Att. 2 Apiay footprint.pdf | ||
| W912CL20R0003 Att. 1 QASP.pdf | ||
| W912CL20R0003.pdf | ||
| W912CL20R0003 Att. 3 PP Questionnaire.docx | DOCX document | |
| W912CL20R0003 Att. 5 GFP.XLSX | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Summary
By Contract Periods
Base year $276,346.60
Option 1 $532,888.93
Option 2 $554,204.49
Option 3 $576,372.66
Option 4 $599,427.57
TOTAL $2,539,240.25
BY Fiscal Year
FY21 Base period of 6 months plus 6 months of Option 1 $542,791.06
FY22 6 months of Option 1 plus 6 months of Option 2 $543,546.71
FY23 6 months of Option 2 plus 6 months of Option 3 $565,288.57
FY24 6 months of Option 3 plus 6 months of Option 4 $587,900.12
FY25 6 months of Option 4 $299,713.79
$2,539,240.25
Prepared by:
Chief, CD/CN; 2416 Budget Manager and Analyst
Approved by: Mr William "Dave" Jackson
G3 Executive Officer
Dale A. Papka
Base on workload requirements, personnel salary and benefits and other cost.
Plus 4% of the Base Year Estimated Cost
Plus 4% of the Option 1 Estimated Cost
Plus 4% of the Option 2 Estimated Cost
Plus 4% of the Option 3 Estimated Cost
Certification: The IGCE preparer and IGCE approving reviewer certify the IGCE was developed independently and prior to seeking a formal proposal from any contractor.
***SEE ENCLOSED ROLL-UP SHEET FOR DETAILS
09APR20
| 2020-04-23T09:03:58-0500 | |
| JACKSON.WILLIAM.DAVID.1131919421 |