W912BV-16-R-0104_0002.pdf

PDF 1013 KB Posted

Attached to
Park Cleaning SVS Federal contract opportunity
Solicitation number
W912BV-16-R-0104
Issued by
Department of the Army Corps of Engineers Engineering District Tulsa

About this file

Amendment 0002

View the file

Other files for this federal contract opportunity

Other files attached to Park Cleaning SVS, newest first.
File Type Posted
W912BV-16-R-0104_0001.pdf PDF
W912BV-16-R-0104.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment is to incorporate a revised Price Schedule. The RFP due date is extended from 21 March 2016 to 23 March 2015 at 4:00 PM CST.

POC: Rudy Morales 918-669-7275

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 18-Mar-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912BV-16-R-0104

X 9B. DATED (SEE ITEM 11)

25-Feb-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

18-Mar-2016

CODE

CONTRACTING DIV

USACE, TULSA 1645 S 101 E AVE

TULSA OK 74128-4609

W912BV 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912BV-16-R-0104

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION B - SUPPLIES OR SERVICES AND PRICES

The following have been added by full text:

PRICE SCHEDULE (REVISED)

SEE SECTION J FOR PRICE SCHEDULE

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Scope of Work 23-FEB-2016 Attachment 2 PRICING SCHEDULE 24-FEB-2016 Attachment 3 BID Schedule 07-MAR-2016 to:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Scope of Work 23-FEB-2016 Attachment 2 PRICING SCHEDULE 24-FEB-2016 Attachment 3 BID Schedule 07-MAR-2016 Attachment 4 PRICE SCHEDULE

(REVISED)

18-MAR-2016

(End of Summary of Changes)

PRICING SCHEDULE

TENKILLER & WEBBERS FALLS LAKES

OKLAHOMA

MAINTENANCE CONTRACT

FOR

PARK CLEANING

IN ACCORDANCE WITH ATTACHED PRICING SCHEDULE

PROVIDE PER COST LINE ITEM TOTALS TO REFLECT:

01 April through 31 October 2016 (7 Months of Cleaning Service)

SCHEDULE I – TENKILLER LAKE

LINE ITEM 0001 – CARTER’S LANDING (A), TENKILLER LAKE

BASE YEAR: 01 April through 31 October 2016

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Picnic Shelters (3 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Fee Station (3 times per week) $ $ Item 5: Grounds – Park, Access Roads, & Parking Area (2 times per week) $ $

TOTAL BASE YEAR (Line Item 0001) $_________

LINE ITEM 0002 – CARTER’S LANDING (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Picnic & Camping Sites (1 time per week) $ $ Item 3: Grounds – Park, Access Roads, Parking Area & Boat Ramps. (2 times per week) $ $

TOTAL BASE YEAR (Line Item 0002) $_________

LINE ITEM 0003 – SIZEMORE LANDING, TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Picnic Shelters (3 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Fee Station (3 times per week) $ $ Item 5: Courtesy Docks (1 time per week) $ $ Item 6: Grounds – Park, Access Roads, Parking Areas

TOTAL BASE YEAR (Line Item 0003) $__________

LINE ITEM 0004 – SIZEMORE LANDING (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Picnic Shelters (3 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Grounds – Park, Access Roads, Parking Areas

TOTAL BASE YEAR (Line Item 0004) $_________

LINE ITEM 0005 – TROUT STREAM, TENKILLER LAKE

BASE YEAR: 01 April through 31October 2016

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Grounds – Park, Access Roads, & Parking Areas (2 times per week) $ $ Item 3: Grounds – Fishing Areas, Sidewalks, & Docks

TOTAL BASE YEAR (Line Item 0005) $_________

LINE ITEM 0006 – CHICKEN CREEK AREA (A), TENKILLER LAKE

BASE YEAR: 01 April through 31October 2016

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Trailer Dump Stations (3 times per week) $ $ Item 6: Fee Stations (3 times per week) $ $ Item 7: Grounds – Park, Access Roads, Parking Areas, & Playgrounds (3 times per week) $ $

TOTAL BASE YEAR (Line Item 0006) $________

LINE ITEM 0007 – CHICKEN CREEK AREA (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Grounds – Park, Access Roads, & Parking Areas (3 times per week) $ $

TOTAL BASE YEAR (Line Item 0007) $________

LINE ITEM 0008 – CHICKEN CREEK SOUTH AREA (C), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (6 times per week) $ $ Item 2: Picnic Shelters (4 time per week) $ $ Item 3: Fee Stations (3 times per week) $ $ Item 4: Courtesy Docks (1 time per week) $ $ Item 5: Grounds – Park, Access Roads, Parking Areas, & Swim Beaches (3 times per week) $ $

TOTAL BASE YEAR (Line Item 0008) $________

LINE ITEM 0009 – COOKSON BEND (A), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Trailer Dump Stations (3 times per week) $ $ Item 5: Fee Stations (3 times per week) $ $ Item 6: Courtesy Docks (1 time per week) $ $ Item 7: Grounds – Park, Access Roads, Parking Areas, Playgrounds, & Swim Beaches (3 times per week) $ $

TOTAL BASE YEAR (Line Item 0009) $_________

LINE ITEM 0010 – COOKSON BEND (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Picnic Shelters (4 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Grounds – Park, Access Roads, & Parking Areas (3 times per week) $ $

TOTAL BASE YEAR (Line Item 0010) $________

LINE ITEM 0011 – COOKSON BEND (C), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (6 times per week) $ $ Item 2: Picnic & Camping Sites (1 time per week) $ $ Item 3: Grounds – Park, Access Roads, & Parking Areas

TOTAL BASE YEAR (Line Item 0011) $________

LINE ITEM 0012 – ELK CREEK LANDING, TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Trailer Dump Stations (3 times per week) $ $ Item 6: Fee Stations (3 times per week) $ $ Item 7: Courtesy Docks (1 time per week) $ $ Item 8: Grounds – Park, Access Roads, & Parking Areas

TOTAL BASE YEAR (Line Item 0012) $________

LINE ITEM 0013 – OVERLOOK, TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Grounds – Park, Access Roads, Parking Areas, Playgrounds, & Esplanade (3 times per week) $ $

TOTAL BASE YEAR (Line Item 0013) $________

LINE ITEM 0014 – PETTIT BAY I (A), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Trailer Dump Stations (3 times per week) $ $ Item 6: Fee Stations (3 times per week) $ $ Item 7: Courtesy Docks (1 time per week) $ $ Item 8: Grounds – Park, Access Roads, Parking Areas, & Playgrounds (3 times per week)

TOTAL BASE YEAR (Line Item 0014) $________

LINE ITEM 0015 – PETTIT BAY II (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Fee Stations (3 times per week) $ Item 6: Courtesy Docks (1 time per week) $ $ Item 7: Grounds – Park, Access Roads, & Parking Areas (3 times per week)

TOTAL BASE YEAR (Line Item 0015) $________

LINE ITEM 0016 – SNAKE CREEK (A), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Trailer Dump Stations (3 times per week) $ $ Item 6: Fee Stations (3 times per week) $ $ Item 7: Courtesy Docks (1 time per week) $ $ Item 8: Grounds – Park, Access Roads, Parking Areas, Playgrounds, & Swim Beaches (3 times per week)

TOTAL BASE YEAR (Line Item 0016) $________

LINE ITEM 0017 – SNAKE CREEK (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Picnic Shelters (4 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Grounds – Park, Access Roads, Parking Areas, & Playgrounds (3 times per week)

TOTAL BASE YEAR (Line Item 0017) $________

LINE ITEM 0018 – STRAYHORN LANDING (A), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Trailer Dump Stations (3 times per week) $ $ Item 6: Fee Stations (3 times per week) $ $ Item 7: Grounds – Park, Access Roads, Parking Areas, TOTAL BASE YEAR (Line Item 0018) $________

LINE ITEM 0019 – STRAYHORN LANDING (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (6 times per week) $ $ Item 2: Picnic Shelters (4 times per week) $ $ Item 3: Fee Stations (3 times per week) $ $ Item 4: Courtesy Docks (1 time per week) $ $ Item 5: Grounds – Park, Access Roads, & Parking Areas

TOTAL BASE YEAR (Line Item 0019 $________

LINE ITEM 0020 – SECOND CLEANINGS, TENKILLER LAKE

Service Item Item Cost

No. of Each

Total Cost

Reference subparagraphs 2.4. (Perform between 2 p.m. & 6 p.m.), 3.1.9. (Second cleanings of toilets on holidays & weekends), 3.1.9.1. (Saturday & Sunday second cleanings May 15 thru Jul 15), and

3.1.9.2. (Holiday weekend second cleanings, Memorial Day, Fourth of July, and Labor Day holidays & weekends).

Item 1: Chicken Creek (A) (26 times per year) $ 26 $ Item 2: Chicken Creek (B) (26 times per year) $ 26 $ Item 3: Chicken Creek South (C) (26 times per year) $ 26 $ Item 4: Cookson Bend (A) (26 times per year) $ 26 $ Item 5: Cookson Bend (B) (26 times per year) $ 26 $ Item 6: Cookson Bend (C) (26 times per year) $ 26 $ Item 7: Elk Creek Landing (26 times per year) $ 26 $ Item 8: Pettit Bay I (A) (26 times per year) $ 26 $ Item 9: Pettit Bay II (B) (26 times per year) $ 26 $ Item 10: Snake Creek (A) (26 times per year) $ 26 $ Item 11: Snake Creek (B) (26 times per year) $ 26 $ Item 12: Strayhorn Landing (A) (26 times per year) $ 26 $ Item 13: Strayhorn Landing (B) (26 times per year) $ 26 $

TOTAL BASE YEAR (Line Item 0020) $________

SCHEDULE II – WEBBERS FALLS LAKE

LINE ITEM 0021 – BREWER’S BEND (A), WEBBERS FALLS LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic & Camping Sites (1 times per week) $ $ Item 4: Trailer Dump Stations (2 times per week) $ $ Item 5: Fee Stations (2 times per week) $ $ Item 6: Courtesy Docks (1 time per week) $ $ Item 7: Grounds – Park, Access Roads, & Parking Areas

TOTAL BASE YEAR (Line Item 0021) $________

LINE ITEM 0022 – BREWER’S BEND (B), WEBBERS FALLS LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (6 times per week) $ $ Item 2: Picnic Shelters (3 times per week) $ $ Item 3: Grounds – Park, Access Roads, Parking Areas, & Swimming Beaches (3 times per week) $ $

TOTAL BASE YEAR (Line Item 0022) $________

LINE ITEM 0023 – SPANIARD CREEK AREA A, WEBBERS FALLS LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (3 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Trailer Dump Stations (2 times per week) $ $ Item 6: Fee Stations (2 times per week) $ $ Item 7: Courtesy Docks (1 time per week) $ $ Item 8: Grounds – Park, Access Roads, Parking Areas, & Playgrounds (3 times per week) $ $ Item 9: Grounds—Fishing Areas, includes Fish Cleaning Station

TOTAL BASE YEAR (Line Item 0023) $________

LINE ITEM 0024 – SPANIARD CREEK AREA B, WEBBERS FALLS LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (6 times per week) $ $ Item 2: Courtesy Docks (1 times per week) $ $ Item 3: Grounds – Park, Access Roads, & Parking Areas

TOTAL BASE YEAR (Line Item 0024) $________

LINE ITEM 0025 – BLUFF VIEW & POWERHOUSE ACCESS ROAD,

WEBBERS FALLS LAKE

BASE YEAR: 01 April through 31 October 2016

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Grounds – Park, Access Roads, & Parking Areas (3 times per week) $ $ Item 3: Grounds – Fishing Areas (2 times per week) $ $

TOTAL BASE YEAR (Line Item 0025) $________

LINE ITEM 0026 – HIGHWAY 10 LANDING, WEBBERS FALLS LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Fee Stations (1 time per week) $ $ Item 3: Courtesy Docks (1 times per week) $ $ Item 4: Grounds – Park, Access Roads, & Parking Areas

TOTAL BASE YEAR (Line Item 0026) $________

LINE ITEM 0027 – LOCK VIEW LANDING & LOCK ACCESS ROAD,

WEBBERS FALLS LAKE PROJECT OFFICE ROADWAY

BASE YEAR: 01 April through 31 October 2016

Service Item Item Cost

No. of Days

Total Cost

Item 1: Grounds – Park, Access Roads, & Parking Areas (3 times per week) Item 2: Webbers Falls Project Office Roadway (1 times per month)

TOTAL BASE YEAR (Line Item 0027) $________

LINE ITEM 0028 – OVERLOOK, WEBBERS FALLS LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Grounds – Park, Access Roads, Parking Areas, & Esplanade (4 times per week) $ $

TOTAL BASE YEAR (Line Item 0028) $________

LINE ITEM 0029 – SECOND CLEANINGS, WEBBERS FALLS LAKE

Service Item Item Cost

No. of Each

Total Cost

Reference subparagraphs 2.4. (Perform between 2 p.m. & 6 p.m.), 3.1.9. (Second cleanings of toilets on holidays & weekends), 3.1.9.1. (Saturday & Sunday second cleanings May 15 thru Jul 15), and

3.1.9.2. (Holiday weekend second cleanings, Memorial Day, Fourth of July, and Labor Day holidays & weekends).

Item 1: Spaniard Creek (A) (26 times per year) $ $ Item 2: Spaniard Creek (B) (26 times per year) $ $ Item 3: Brewer’s Bend (A) (26 times per year) $ $ Item 4: Brewer’s Bend (B) (26 times per year) $ $

TOTAL BASE YEAR (Line Item 0029) $________

WINTER SCHEDULE

LINE ITEM 0030 – WINTER CLEANINGS TENKILLER LAKE

BASE YEAR: 01 November 2016 through 30 March 2017 (5 Months)

Service Item Item Cost No. of Days

Total Cost

Item 1: Vault Toilet Only Cookson Bend (A) (One time per week on Tuesday) Chicken Creek (C) (One time per week on Tuesday) Chicken Creek (South) (One time per week on Tuesday) Pettit Bay (A) (One time per week on Tuesday) Overlook (One time per week on Tuesday) Strayhorn (B) (One time per week on Tuesday) Trout Stream (One time per week on Tuesday) Highway 10 Landing (One time per week on Monday)

TOTAL BASE YEAR(Line Item 0030) $__________

LINE ITEM 0031 – WINTER CLEANINGS WEBBERS FALLS LAKE

BASE YEAR: 01 November 2016 through 30 March 2017 (5 Months)

Service Item Item Cost No. of Days

Total Cost

Brewer’s Bend (A) (One time per week on Monday) Spaniard Creek (A) (One time per week on Monday) Spaniard Creek (B) (One time per week on Monday)

TOTAL BASE YEAR (Line Item 0031) $________

TOTAL BASE YEAR AMOUNT OF LINE ITEMS 0001-0031 $_________________

1ST OPTION YEAR

LINE ITEM 1001 – CARTER’S LANDING (A), TENKILLER LAKE

1ST OPTION YEAR: 01 April through 31 October 2017

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Picnic Shelters (3 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Fee Station (3 times per week) $ $ Item 5: Grounds – Park, Access Roads, & Parking Area

TOTAL1ST OPTION YEAR (Line Item 1001) $_________

1ST OPTION YEAR

LINE ITEM 1002 – CARTER’S LANDING (B), TENKILLER LAKE

1ST OPTION YEAR: 01 April through 31 October 2017

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Picnic & Camping Sites (1 time per week) $ $ Item 3: Grounds – Park, Access Roads, Parking Area

TOTAL1ST OPTION YEAR (Line Item 1002) $_________

LINE ITEM 1003 – SIZEMORE LANDING, TENKILLER LAKE

1ST OPTION YEAR: 01 April through 31 October 2017

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Picnic Shelters (3 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Fee Station (3 times per week) $ $ Item 5: Courtesy Docks (1 time per week) $ $ Item 6: Grounds – Park, Access Roads, Parking Areas

TOTAL 1ST OPTION YEAR (Line Item 1003) $_________

LINE ITEM 1004 – SIZEMORE LANDING (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Picnic Shelters (3 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Grounds – Park, Access Roads, Parking Areas

TOTAL 1ST OPTION YEAR (Line Item 1004) $_________

LINE ITEM 1005 – TROUT STREAM, TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Grounds – Park, Access Roads, & Parking Areas (2 times per week) $ $ Item 3: Grounds – Fishing Areas, Sidewalks, & Docks

TOTAL 1ST OPTION YEAR (Line Item 1005) $________

LINE ITEM 1006 – CHICKEN CREEK AREA (A), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Trailer Dump Stations (3 times per week) $ $ Item 6: Fee Stations (3 times per week) $ $ Item 7: Grounds – Park, Access Roads, Parking Areas, &

TOTAL 1ST OPTION YEAR (Line Item 1006) $________

LINE ITEM 1007 – CHICKEN CREEK AREA (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Grounds – Park, Access Roads, & Parking Areas

TOTAL 1ST OPTION YEAR (Line Item 1007) $________

LINE ITEM 1008 – CHICKEN CREEK SOUTH AREA (C), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (6 times per week) $ $ Item 2: Picnic Shelters (4 time per week) $ $ Item 3: Fee Stations (3 times per week) $ $ Item 4: Courtesy Docks (1 time per week) $ $ Item 5: Grounds – Park, Access Roads, Parking Areas, &

TOTAL 1ST OPTION YEAR (Line Item 1008) $________

LINE ITEM 1009 – COOKSON BEND (A), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Trailer Dump Stations (3 times per week) $ $ Item 5: Fee Stations (3 times per week) $ $ Item 6: Courtesy Docks (1 time per week) $ $ Item 7: Grounds – Park, Access Roads, Parking Areas, TOTAL 1ST OPTION YEAR (Line Item 1009) $________

LINE ITEM 1010 – COOKSON BEND (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Picnic Shelters (4 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Grounds – Park, Access Roads, & Parking Areas

TOTAL 1ST OPTION YEAR (Line Item 1010) $________

LINE ITEM 1011 – COOKSON BEND (C), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (6 times per week) $ $ Item 2: Picnic & Camping Sites (1 time per week) $ $ Item 3: Grounds – Park, Access Roads, & Parking Areas

TOTAL 1ST OPTION YEAR (Line Item 1011) $________

LINE ITEM 1012 – ELK CREEK LANDING, TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Trailer Dump Stations (3 times per week) $ $ Item 6: Fee Stations (3 times per week) $ $ Item 7: Courtesy Docks (1 time per week) $ $ Item 8: Grounds – Park, Access Roads, & Parking Areas

TOTAL 1ST OPTION YEAR (Line Item 1012) $________

LINE ITEM 1013 – OVERLOOK, TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Grounds – Park, Access Roads, Parking Areas, TOTAL 1ST OPTION YEAR (Line Item 1013) $________

LINE ITEM 1014 – PETTIT BAY I (A), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Trailer Dump Stations (3 times per week) $ $ Item 6: Fee Stations (3 times per week) $ $ Item 7: Courtesy Docks (1 time per week) $ $ Item 8: Grounds – Park, Access Roads, Parking Areas, & Playgrounds (3 times per week)

TOTAL 1ST OPTION YEAR (Line Item 1014) $________

LINE ITEM 1015 – PETTIT BAY II (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Fee Stations (3 times per week) $ Item 6: Courtesy Docks (1 time per week) $ $ Item 7: Grounds – Park, Access Roads, & Parking Areas (3 times per week)

TOTAL 1ST OPTION YEAR (Line Item 1015) $________

LINE ITEM 1016 – SNAKE CREEK (A), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Trailer Dump Stations (3 times per week) $ $ Item 6: Fee Stations (3 times per week) $ $ Item 7: Courtesy Docks (1 time per week) $ $ Item 8: Grounds – Park, Access Roads, Parking Areas, Playgrounds, & Swim Beaches (3 times per week)

TOTAL 1ST OPTION YEAR (Line Item 1016) $________

LINE ITEM 1017 – SNAKE CREEK (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Picnic Shelters (4 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Grounds – Park, Access Roads, Parking Areas, & Playgrounds (3 times per week)

TOTAL 1ST OPTION YEAR (Line Item 1017) $________

LINE ITEM 1018 – STRAYHORN LANDING (A), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Trailer Dump Stations (3 times per week) $ $ Item 6: Fee Stations (3 times per week) $ $ Item 7: Grounds – Park, Access Roads, Parking Areas, TOTAL 1ST OPTION YEAR (Line Item 1018) $________

LINE ITEM 1019 – STRAYHORN LANDING (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (6 times per week) $ $ Item 2: Picnic Shelters (4 times per week) $ $ Item 3: Fee Stations (3 times per week) $ $ Item 4: Courtesy Docks (1 times per week) $ $ Item 5: Grounds – Park, Access Roads, & Parking Areas

TOTAL 1ST OPTION YEAR (Line Item 1019) $_______

LINE ITEM 1020 – SECOND CLEANINGS, TENKILLER LAKE

Service Item Item Cost

No. of Each

Total Cost

Reference subparagraphs 2.4. (Perform between 2 p.m. & 6 p.m.), 3.1.9. (Second cleanings of toilets on holidays & weekends), 3.1.9.1. (Saturday & Sunday second cleanings May 15 thru Jul 15), and

3.1.9.2. (Holiday weekend second cleanings, Memorial Day, Fourth of July, and Labor Day holidays & weekends).

Item 1: Chicken Creek (A) (26 times per year) $ 26 $ Item 2: Chicken Creek (B) (26 times per year) $ 26 $ Item 3: Chicken Creek South (C) (26 times per year) $ 26 $ Item 4: Cookson Bend (A) (26 times per year) $ 26 $ Item 5: Cookson Bend (B) (26 times per year) $ 26 $ Item 6: Cookson Bend (C) (26 times per year) $ 26 $ Item 7: Elk Creek Landing (26 times per year) $ 26 $ Item 8: Pettit Bay I (A) (26 times per year) $ 26 $ Item 9: Pettit Bay II (B) (26 times per year) $ 26 $ Item 10: Snake Creek (A) (26 times per year) $ 26 $ Item 11: Snake Creek (B) (26 times per year) $ 26 $ Item 12: Strayhorn Landing (A) (26 times per year) $ 26 $

TOTAL 1ST OPTION YEAR (Line Item 1020) $________

LINE ITEM 1021 – BREWER’S BEND (A), WEBBERS FALLS LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic & Camping Sites (1 times per week) $ $ Item 4: Trailer Dump Stations (2 times per week) $ $ Item 5: Fee Stations (2 times per week) $ $ Item 6: Courtesy Docks (1 time per week) $ $ Item 7: Grounds – Park, Access Roads, & Parking Areas

TOTAL 1ST OPTION YEAR (Line Item 1021) $________

LINE ITEM 1022 – BREWER’S BEND (B), WEBBERS FALLS LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (6 times per week) $ $ Item 2: Picnic Shelters (3 times per week) $ $ Item 3: Grounds – Park, Access Roads, Parking Areas, &

TOTAL 1ST OPTION YEAR (Line Item 1022) $________

LINE ITEM 1023 – SPANIARD CREEK AREA A, WEBBERS FALLS LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (3 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Trailer Dump Stations (2 times per week) $ $ Item 6: Fee Stations (2 times per week) $ $ Item 7: Courtesy Docks (1 time per week) $ $ Item 8: Grounds – Park, Access Roads, Parking Areas, & Playgrounds (3 times per week) $ $ Item 9: Grounds—Fishing Areas, includes Fish Cleaning Station

TOTAL 1ST OPTION YEAR (Line Item 1023) $________

LINE ITEM 1024 – SPANIARD CREEK AREA B, WEBBERS FALLS LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (6 times per week) $ $ Item 2: Courtesy Docks (1 times per week) $ $ Item 3: Grounds – Park, Access Roads, & Parking Areas

TOTAL 1ST OPTION YEAR (Line Item 1024) $________

LINE ITEM 1025 – BLUFF VIEW & POWERHOUSE ACCESS ROAD,

1ST OPTION YEAR: 01 April through 31 October 2017

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Grounds – Park, Access Roads, & Parking Areas (3 times per week) $ $

TOTAL 1ST OPTION YEAR (Line Item 1025) $________

LINE ITEM 1026 – HIGHWAY 10 LANDING, WEBBERS FALLS LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Fee Stations (1 time per week) $ $ Item 3: Courtesy Docks (1 times per week) $ $ Item 4: Grounds – Park, Access Roads, & Parking Areas

TOTAL 1ST OPTION YEAR (Line Item 1026) $________

LINE ITEM 1027 – LOCK VIEW LANDING & LOCK ACCESS ROAD,

1ST OPTION YEAR: 01 April through 31 October 2017

Service Item Item Cost

No. of Days

Total Cost

Item 1: Grounds – Park, Access Roads, & Parking Areas (3 times per week) Item 2: Webbers Falls Project Office Roadway (1 times monthly) $ $

TOTAL 1ST OPTION YEAR (Line Item 1027) $________

LINE ITEM 1028 – OVERLOOK, WEBBERS FALLS LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Grounds – Park, Access Roads, Parking Areas, &

TOTAL 1ST OPTION YEAR (Line Item 1028) $________

LINE ITEM 1029 – SECOND CLEANINGS, WEBBERS FALLS LAKE

Service Item Item Cost

No. of Each

Total Cost

Reference subparagraphs 2.4. (Perform between 2 p.m. & 6 p.m.), 3.1.9. (Second cleanings of toilets on holidays & weekends), 3.1.9.1. (Saturday & Sunday second cleanings May 15 thru Jul 15), and 3.1.9.2.

(Holiday weekend second cleanings, Memorial Day, Fourth of July, and Labor Day holidays & weekends).

Item 1: Spaniard Creek (A) (26 times per year) $ 26 $ Item 2: Spaniard Creek (B) (26 times per year) $ 26 $ Item 3: Brewer’s Bend (A) (26 times per year) $ 26 $ Item 4: Brewer’s Bend (B) (26 times per year) $ 26 $

TOTAL 1ST OPTION YEAR (Line Item 1029) $________

LINE ITEM 1030 – WINTER CLEANINGS TENKILLER LAKE

1ST OPTION YEAR: 01 November 2017 through 30 March 2018 (5 Months)

Service Item Item Cost No. of Days

Total Cost

Item 1: Vault Toilet Only Cookson Bend (A) (One time per week on Tuesday) Chicken Creek I (One time per week on Tuesday) Chicken Creek (South) (One time per week on Tuesday) Pettit Bay (A) (One time per week on Tuesday) Overlook (One time per week on Tuesday) Strayhorn (B) (One time per week on Tuesday) Trout Stream (One time per week on Tuesday)

TOTAL 1st OPTION YEAR (Line Item 1030) $________

LINE ITEM 1031 – WINTER CLEANINGS WEBBERS FALLS LAKE

1ST OPTION YEAR: 01 November 2017 through 30 March 2018 (5 Months)

Service Item Item Cost No. of Days

Total Cost

Brewer’s Bend (A) (One time per week on Monday) Spaniard Creek (A) (One time per week on Monday)

TOTAL 1st OPTION YEAR (Line Item 1031) $___________

TOTAL 1ST OPTION YEAR AMOUNT LINE ITEMS 1001 – 1031) $ _____________

2ND OPTION YEAR

LINE ITEM 2001 – CARTER’S LANDING (A), TENKILLER LAKE

2ND OPTION YEAR: 01 April through 31 October 2018

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Picnic Shelters (3 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Fee Station (3 times per week) $ $ Item 5: Grounds – Park, Access Roads, & Parking Area

TOTAL 2ND OPTION YEAR (Line Item 2001) $_________

2ND OPTION YEAR

LINE ITEM 2002 – CARTER’S LANDING (B), TENKILLER LAKE

2ND OPTION YEAR: 01 April through 31 October 2018

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Picnic & Camping Sites (1 time per week) $ $ Item 3: Grounds – Park, Access Roads, Parking Area

TOTAL 2ND YEAR (Line Item 2002) $_________

LINE ITEM 2003 – SIZEMORE LANDING, TENKILLER LAKE

2ND OPTION YEAR: 01 April through 31 October 2018

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Picnic Shelters (3 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Fee Station (3 times per week) $ $ Item 5: Courtesy Docks (1 time per week) $ $ Item 6: Grounds – Park, Access Roads, Parking Areas

TOTAL 2ND YEAR (Line Item 2003) $________

LINE ITEM 2004 – SIZEMORE LANDING (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Picnic Shelters (3 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Grounds – Park, Access Roads, Parking Areas

TOTAL 2ND YEAR (Line Item 2004) $________

LINE ITEM 2005 – TROUT STREAM, TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Grounds – Park, Access Roads, & Parking Areas (2 times per week) $ $ Item 3: Grounds – Fishing Areas, Sidewalks, & Docks

TOTAL 2ND YEAR (Line Item 2005) $________

LINE ITEM 2006 – CHICKEN CREEK AREA (A), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Trailer Dump Stations (3 times per week) $ $ Item 6: Fee Stations (3 times per week) $ $ Item 7: Grounds – Park, Access Roads, Parking Areas, &

TOTAL 2ND YEAR (Line Item 2006) $_______

LINE ITEM 2007 – CHICKEN CREEK AREA (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Grounds – Park, Access Roads, & Parking Areas

TOTAL 2ND YEAR (Line Item 2007) $________

LINE ITEM 2008 – CHICKEN CREEK SOUTH AREA I, TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (6 times per week) $ $ Item 2: Picnic Shelters (4 time per week) $ $ Item 3: Fee Stations (3 times per week) $ $ Item 4: Courtesy Docks (1 time per week) $ $ Item 5: Grounds – Park, Access Roads, Parking Areas, &

TOTAL 2ND YEAR (Line Item 2008) $________

LINE ITEM 2009 – COOKSON BEND (A), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Trailer Dump Stations (3 times per week) $ $ Item 5: Fee Stations (3 times per week) $ $ Item 6: Courtesy Docks (1 time per week) $ $ Item 7: Grounds – Park, Access Roads, Parking Areas, TOTAL 2ND YEAR (Line Item 2009) $________

LINE ITEM 2010 – COOKSON BEND (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Picnic Shelters (4 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Grounds – Park, Access Roads, & Parking Areas

TOTAL 2ND YEAR (Line Item 2010) $________

LINE ITEM 2011 – COOKSON BEND I, TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (6 times per week) $ $ Item 2: Picnic & Camping Sites (1 time per week) $ $ Item 3: Grounds – Park, Access Roads, & Parking Areas

TOTAL 2ND YEAR (Line Item 2011) $________

LINE ITEM 2012 – ELK CREEK LANDING, TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Trailer Dump Stations (3 times per week) $ $ Item 6: Fee Stations (3 times per week) $ $ Item 7: Courtesy Docks (1 time per week) $ $ Item 8: Grounds – Park, Access Roads, & Parking Areas

TOTAL 2ND YEAR (Line Item 2012) $________

LINE ITEM 2013 – OVERLOOK, TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Grounds – Park, Access Roads, Parking Areas, TOTAL 2ND YEAR (Line Item 2013) $________

LINE ITEM 2014 – PETTIT BAY I (A), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Trailer Dump Stations (3 times per week) $ $ Item 6: Fee Stations (3 times per week) $ $ Item 7: Courtesy Docks (1 time per week) $ $ Item 8: Grounds – Park, Access Roads, Parking Areas, & Playgrounds (3 times per week)

TOTAL 2ND YEAR (Line Item 2014) $________

LINE ITEM 2015 – PETTIT BAY II (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Fee Stations (3 times per week) $ Item 6: Courtesy Docks (1 time per week) $ $ Item 7: Grounds – Park, Access Roads, & Parking Areas (3 times per week)

TOTAL 2ND YEAR (Line Item 2015) $________

LINE ITEM 2016 – SNAKE CREEK (A), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Trailer Dump Stations (3 times per week) $ $ Item 6: Fee Stations (3 times per week) $ $ Item 7: Courtesy Docks (1 time per week) $ $ Item 8: Grounds – Park, Access Roads, Parking Areas, Playgrounds, & Swim Beaches (3 times per week)

TOTAL 2ND YEAR (Line Item 2016) $________

LINE ITEM 2017 – SNAKE CREEK (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Picnic Shelters (4 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Grounds – Park, Access Roads, Parking Areas, & Playgrounds (3 times per week)

TOTAL 2ND YEAR (Line Item 2017) $________

LINE ITEM 2018 – STRAYHORN LANDING (A), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Trailer Dump Stations (3 times per week) $ $ Item 6: Fee Stations (3 times per week) $ $ Item 7: Grounds – Park, Access Roads, Parking Areas, TOTAL 2ND YEAR (Line Item 2018) $________

LINE ITEM 2019 – STRAYHORN LANDING (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (6 times per week) $ $ Item 2: Picnic Shelters (4 times per week) $ $ Item 3: Fee Stations (3 times per week) $ $ Item 4: Courtesy Docks (1 times per week) $ $ Item 5: Grounds – Park, Access Roads, & Parking Areas

TOTAL 2ND YEAR (Line Item 2019) $________

LINE ITEM 2020 – SECOND CLEANINGS, TENKILLER LAKE

Service Item Item Cost

No. of Each

Total Cost

Reference subparagraphs 2.4. (Perform between 2 p.m. & 6 p.m.), 3.1.9. (Second cleanings of toilets on holidays & weekends), 3.1.9.1. (Saturday & Sunday second cleanings May 15 thru Jul 15), and

3.1.9.2. (Holiday weekend second cleanings, Memorial Day, Fourth of July, and Labor Day holidays & weekends).

Item 1: Chicken Creek (A) (26 times per year) $ 26 $ Item 2: Chicken Creek (B) (26 times per year) $ 26 $ Item 3: Chicken Creek South I (26 times per year) $ 26 $ Item 4: Cookson Bend (A) (26 times per year) $ 26 $ Item 5: Cookson Bend (B) (26 times per year) $ 26 $ Item 6: Cookson Bend I (26 times per year) $ 26 $ Item 7: Elk Creek Landing (26 times per year) $ 26 $ Item 8: Pettit Bay I (A) (26 times per year) $ 26 $ Item 9: Pettit Bay II (B) (26 times per year) $ 26 $ Item 10: Snake Creek (A) (26 times per year) $ 26 $ Item 11: Snake Creek (B) (26 times per year) $ 26 $ Item 12: Strayhorn Landing (A) (26 times per year) $ 26 $

TOTAL 2ND YEAR (Line Item 2020) $________

LINE ITEM 2021 – BREWER’S BEND (A), WEBBERS FALLS LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic & Camping Sites (1 times per week) $ $ Item 4: Trailer Dump Stations (2 times per week) $ $ Item 5: Fee Stations (2 times per week) $ $ Item 6: Courtesy Docks (1 time per week) $ $ Item 7: Grounds – Park, Access Roads, & Parking Areas

TOTAL 2ND YEAR (Line Item 2021) $________

LINE ITEM 2022 – BREWER’S BEND (B), WEBBERS FALLS LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (6 times per week) $ $ Item 2: Picnic Shelters (3 times per week) $ $ Item 3: Grounds – Park, Access Roads, Parking Areas, &

TOTAL 2ND YEAR (Line Item 2022) $________

LINE ITEM 2023 – SPANIARD CREEK AREA A, WEBBERS FALLS LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (3 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Trailer Dump Stations (2 times per week) $ $ Item 6: Fee Stations (2 times per week) $ $ Item 7: Courtesy Docks (1 time per week) $ $ Item 8: Grounds – Park, Access Roads, Parking Areas, & Playgrounds (3 times per week) $ $ Item 9: Grounds—Fishing Areas, includes Fish Cleaning Station

TOTAL 2ND YEAR (Line Item 2023) $________

LINE ITEM 2024 – SPANIARD CREEK AREA B, WEBBERS FALLS LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (6 times per week) $ $ Item 2: Courtesy Docks (1 times per week) $ $ Item 3: Grounds – Park, Access Roads, & Parking Areas

TOTAL 2ND YEAR (Line Item 2024) $________

LINE ITEM 2025 – BLUFF VIEW & POWERHOUSE ACCESS ROAD,

2ND OPTION YEAR: 01 April through 31 October 2018

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Grounds – Park, Access Roads, & Parking Areas (3 times per week) $ $

TOTAL 2ND YEAR (Line Item 2025) $________

LINE ITEM 2026 – HIGHWAY 10 LANDING, WEBBERS FALLS LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Fee Stations (1 time per week) $ $ Item 3: Courtesy Docks (1 times per week) $ $ Item 4: Grounds – Park, Access Roads, & Parking Areas

TOTAL 2ND YEAR (Line Item 2026) $________

LINE ITEM 2027 – LOCK VIEW LANDING & LOCK ACCESS ROAD,

2ND OPTION YEAR: 01 April through 31 October 2018

Service Item Item Cost

No. of Days

Total Cost

Item 1: Grounds – Park, Access Roads, & Parking Areas (3 times per week) Item 2: Webbers Falls Project Office Roadway (1 times monthly) $ $

TOTAL 2ND YEAR (Line Item 2027) $________

LINE ITEM 2028 – OVERLOOK, WEBBERS FALLS LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Grounds – Park, Access Roads, Parking Areas, &

TOTAL 2ND YEAR (Line Item 2028) $________

LINE ITEM 2029 – SECOND CLEANINGS, WEBBERS FALLS LAKE

Service Item Item Cost

No. of Each

Total Cost

Reference subparagraphs 2.4. (Perform between 2 p.m. & 6 p.m.), 3.1.9. (Second cleanings of toilets on holidays & weekends), 3.1.9.1. (Saturday & Sunday second cleanings May 15 thru Jul 15), and

3.1.9.2. (Holiday weekend second cleanings, Memorial Day, Fourth of July, and Labor Day holidays & weekends).

Item 1: Spaniard Creek (A) (26 times per year) $ 26 $ Item 2: Spaniard Creek (B) (26 times per year) $ 26 $ Item 3: Brewer’s Bend (A) (26 times per year) $ 26 $ Item 4: Brewer’s Bend (B) (26 times per year) $ 26 $

TOTAL 2ND YEAR (Line Item 2029) $________

LINE ITEM 2030 – WINTER CLEANINGS TENKILLER LAKE

2ND OPTION YEAR: 01 November 2018 through 30 March 2019 (5 Months)

Service Item Item Cost No. of Days

Total Cost

Item 1: Vault Toilet Only Cookson Bend (A) (One time per week on Tuesday) Chicken Creek I (One time per week on Tuesday) Chicken Creek (South) (One time per week on Tuesday) Pettit Bay (A) (One time per week on Tuesday) Overlook (One time per week on Tuesday) Strayhorn (B) (One time per week on Tuesday) Trout Stream (One time per week on Tuesday) Highway 10 Landing (One time per week on Monday)

TOTAL 2ND OPTION YEAR (Line Item 2030)

LINE ITEM 2031 – WINTER CLEANINGS WEBBERS FALLS LAKE

2nd OPTION YEAR: 01 November 2018 through 30 March 2019 (5 Months)

Service Item Item Cost No. of Days

Total Cost

Brewer’s Bend (A) (One time per week on Monday)

TOTAL 2ND OPTION YEAR (Line Item 2031) $________

TOTAL 2nd OPTION YEAR LINE ITEMS 2001 – 2031 $ ______________

OPTION YEAR NO. 3 SCHEDULE I – TENKILLER LAKE

LINE ITEM 3001 – CARTER’S LANDING (A), TENKILLER LAKE

3RD OPTION YEAR: 01 April through 31 October 2019

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Picnic Shelters (3 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Fee Station (3 times per week) $ $ Item 5: Grounds – Park, Access Roads, & Parking Area

TOTAL 3RD OPTION YEAR (Line Item 3001) $_________

LINE ITEM 3002 – CARTER’S LANDING (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Picnic & Camping Sites (1 time per week) $ $ Item 3: Grounds – Park, Access Roads, Parking Area

TOTAL 3RD YEAR (Line Item 3002) $_________

LINE ITEM 3003 – SIZEMORE LANDING, TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Picnic Shelters (3 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Fee Station (3 times per week) $ $ Item 5: Courtesy Docks (1 time per week) $ $ Item 6: Grounds – Park, Access Roads, Parking Areas

TOTAL 3RD YEAR (Line Item 3003) $________

LINE ITEM 3004 – SIZEMORE LANDING (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Picnic Shelters (3 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Grounds – Park, Access Roads, Parking Areas

TOTAL 3RD YEAR (Line Item 3004) $________

LINE ITEM 3005 – TROUT STREAM, TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (4 times per week) $ $ Item 2: Grounds – Park, Access Roads, & Parking Areas (2 times per week) $ $ Item 3: Grounds – Fishing Areas, Sidewalks, & Docks

TOTAL 2ND YEAR (Line Item 3005) $________

LINE ITEM 3006 – CHICKEN CREEK AREA (A), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic Shelters (4 times per week) $ $ Item 4: Picnic & Camping Sites (1 time per week) $ $ Item 5: Trailer Dump Stations (3 times per week) $ $ Item 6: Fee Stations (3 times per week) $ $ Item 7: Grounds – Park, Access Roads, Parking Areas, &

TOTAL 3RD YEAR (Line Item 3006) $_______

LINE ITEM 3007 – CHICKEN CREEK AREA (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Grounds – Park, Access Roads, & Parking Areas

TOTAL 3RD YEAR (Line Item 3007) $________

LINE ITEM 3008 – CHICKEN CREEK SOUTH AREA I, TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (6 times per week) $ $ Item 2: Picnic Shelters (4 time per week) $ $ Item 3: Fee Stations (3 times per week) $ $ Item 4: Courtesy Docks (1 time per week) $ $ Item 5: Grounds – Park, Access Roads, Parking Areas, &

TOTAL 3RD YEAR (Line Item 3008) $________

LINE ITEM 3009 – COOKSON BEND (A), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Toilets, Vault (6 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Trailer Dump Stations (3 times per week) $ $ Item 5: Fee Stations (3 times per week) $ $ Item 6: Courtesy Docks (1 time per week) $ $ Item 7: Grounds – Park, Access Roads, Parking Areas, TOTAL 3RD YEAR (Line Item 3009) $________

LINE ITEM 3010 – COOKSON BEND (B), TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Waterborne with Showers (6 times per week) $ $ Item 2: Picnic Shelters (4 times per week) $ $ Item 3: Picnic & Camping Sites (1 time per week) $ $ Item 4: Grounds – Park, Access Roads, & Parking Areas

TOTAL 3RD YEAR (Line Item 3010) $________

LINE ITEM 3011 – COOKSON BEND I, TENKILLER LAKE

Service Item Item Cost

No. of Days

Total Cost

Item 1: Toilets, Vault (6 times per week) $ $ Item 2: Picnic & Camping Sites (1 time per week) $ $ Item 3: Grounds – Park, Access Roads, & Parking Areas

TOTAL 3RD YEAR (Line Item 3011) $________

LINE ITEM 3012 – ELK CREEK LANDING, TENKILLER LAKE

Service Item Item…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .