W9128F23R0022_SPECS_GBSD-ICC(fea5).pdf
PDF 15 MB Posted
- Attached to
- GBSD Integrated Command Center - FE Warren AFB Federal contract opportunity
- Solicitation number
- W9128F23R0022
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Am-0008_W9128F23R0022.pdf | ||
| Am-0007_W9128F23R0022.pdf | ||
| Am-0006_W9128F23R0022.pdf | ||
| Am-0005_W9128F23R0022.pdf | ||
| Am-0004_W9128F23R0022.pdf | ||
| Am-0003_W9128F23R0022.pdf | ||
| GBSD ICC Design Summary 2023-06-29.pdf | ||
| Am-0002_W9128F23R0022.pdf | ||
| Site-Visit-Sign-In-Sheet_06.28.2023_GBSD-ICC.pdf | ||
| Am-0001_W9128F23R0022.pdf | ||
| JA_F.E. Warren AFB_Fire Alarm Control Panels_Final_Redacted.pdf | ||
| W9128F23R0022_GBSD-ICC_RTA (Int-Other).pdf | ||
| JA_F.E.Warren AFB_Generators_Final_Redacted.pdf | ||
| JA_F.E. Warren AFB_HVAC Chillers_Final_Redacted.pdf | ||
| Solicitation_W9128F23R0022.pdf | ||
| JA_F.E. Warren AFB_HVAC Chillers_Final_Redacted.pdf | ||
| JA_F.E. Warren AFB_Fire Alarm Control Panels_Final_Redacted.pdf | ||
| W9128F23R0022_GBSD-ICC_RTA (Gen-Arch).pdf | ||
| JA_F.E.Warren AFB_Generators_Final_Redacted.pdf |
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CUI/UNCLASSIFIED
BUILDING STRONG
CUI/UNCLASSIFIED
REQUEST FOR PROPOSAL
(FOR CONSTRUCTION CONTRACT)
Specifications (Divisions 01 – 33)
SOLICITATION NO. W9128F23R0022
GBSD Integrated Command Center
PNGHLN231990 (FY23)
F.E. WARREN AFB, WYOMING
JUNE 2023
US ARMY CORPS OF ENGINEERS
OMAHA DISTRICT
This page was intentionally left blank for duplex printing.
PROJECT TABLE OF CONTENTS - 1
REQUEST FOR PROPOSAL
FOR
GBSD INTEGRATED COMMAND CENTER
PNGHLN231990 (FY23)
FE WARREN AFB, WYOMING
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 30 00.24 OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS
FEW-Badge FE WARREN CONTRACTOR BADGE TEMPLATE
AF103 BASE CIVIL ENGINEERING WORK CLEARANCE REQUEST
PROJSIGN PROJECT SIGN DETAILS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
REGISTER SUBMITTAL REGISTER
E4025 ENG FORM 4025 TRANSMITTAL FORM
01 33 29 SUSTAINABILITY REQUIREMENTS AND REPORTING
01 33 29AT1 SUSTAINABILITY REQUIREMENTS SCORESHEET
01 33 39.00 10 ADVANCED MODELING (BIM/CIM/GIS/CAD) REQUIREMENTS
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 41 26.04 24 (WYOMING) NPDES PERMIT REQUIREMENTS FOR STORM WATER DISCHARGES
FROM CONSTRUCTION SITES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 00.00 10AT SAMPLE QUALITY CONTROL REPORT
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 35 SPECIAL INSPECTIONS
01 45 35AT-A SCHEDULE OF SPECIAL INSPECTIONS
01 45 35AT-B STATEMENT OF SPECIAL INSPECTIONS
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL
01 62 35 RECYCLED / RECOVERED MATERIALS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 24.00 10 FACILITY DATA REQUIREMENTS
01 78 36.00 24 WARRANTY OF CONSTRUCTION
01 78 39.00 24 AS-BUILT DRAWINGS
01 78 39.00 24AT MODIFICATIONS AND TITLE BLOCK EXAMPLES
01 91 00.15 10 TOTAL BUILDING COMMISSIONING
01 91 00.15 10AT1 DRAFT DESIGN PHASE CX PLAN
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL
02 82 00 ASBESTOS REMEDIATION
02 84 33 REMOVAL AND DISPOSAL OF POLYCHLORINATED BIPHENYLS (PCBs)
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
03 42 13.00 10 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE CONSTRUCTION
03 45 00 PRECAST ARCHITECTURAL CONCRETE
PROJECT TABLE OF CONTENTS - 2
DIVISION 05 - METALS
05 05 20.00 27 POST-INSTALLED CONCRETE AND MASONRY ANCHORS
05 05 23.13 10 ULTRASONIC INSPECTION OF WELDMENTS
05 05 23.16 STRUCTURAL WELDING
05 12 00 STRUCTURAL STEEL
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 51 00 METAL STAIRS
05 51 33 METAL LADDERS
05 52 00 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 06 60 PLASTIC FABRICATIONS
06 10 00 ROUGH CARPENTRY
06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
06 61 16 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 RESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS
07 13 53 ELASTOMERIC SHEET WATERPROOFING
07 21 16 MINERAL FIBER BLANKET INSULATION
07 22 00 ROOF AND DECK INSULATION
07 27 10.00 10 BUILDING AIR BARRIER SYSTEM
07 27 19.01 SELF-ADHERING AIR BARRIERS
07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 27 36 SPRAY FOAM BARRIERS
07 42 93 FLUSH SEAM METAL PANEL
07 54 19 POLYVINYL-CHLORIDE ROOFING
07 60 00 FLASHING AND SHEET METAL
07 61 14.00 20 STEEL STANDING SEAM ROOFING
07 72 53 SNOW GUARDS
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 14 00 WOOD DOORS
08 31 00 ACCESS DOORS AND PANELS
08 33 23 OVERHEAD COILING DOORS
08 34 73 SOUND CONTROL DOOR ASSEMBLIES
08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 ACOUSTICAL CEILINGS
09 62 38 STATIC-CONTROL FLOORING
09 65 00 RESILIENT FLOORING
09 67 23.13 STANDARD RESINOUS FLOORING
09 68 00 CARPETING
09 69 13 RIGID GRID ACCESS FLOORING
PROJECT TABLE OF CONTENTS - 3
DIVISION 09 – FINISHES (CONTINUED)
09 83 00 ELASTOMERIC COATINGS
09 84 20 ACOUSTICAL WALL PANELS
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 11 00 VISUAL DISPLAY UNITS
10 14 00.20 INTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 26 00 WALL AND DOOR PROTECTION
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
DIVISION 11 - EQUIPMENT
11 81 29 FACILITY FALL PROTECTION
DIVISION 12 - FURNISHINGS
12 24 13 ROLLER WINDOW SHADES
12 50 00.13 10 FURNITURE AND FURNITURE INSTALLATION
12 59 00 SYSTEMS FURNITURE
DIVISION 13 - SPECIAL CONSTRUCTION
13 21 48 ACOUSTICAL PANELIZED WALL SYSTEM
13 27 54.00 10 PROTECTIVE TECHNICAL BARRIER
13 48 73 SEISMIC CONTROL FOR MECHANICAL EQUIPMENT
13 49 20.00 10 RFI/EMI SHIELDING
DIVISION 21 - FIRE SUPPRESSION
21 13 13 WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION
21 22 00.00 40 CLEAN AGENT FIRE EXTINGUISHING SYSTEMS
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 05 15 COMMON PIPING FOR HVAC
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING
CONTROL SYSTEMS
23 11 20 FACILITY GAS PIPING
23 21 23 HYDRONIC PUMPS
23 25 00 CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS
23 30 00 HVAC AIR DISTRIBUTION
23 44 00.00 10 CHEMICAL, BIOLOGICAL, AND RADIOLOGICAL (CBR) AIR FILTRATION SYSTEM
23 52 00 HEATING BOILERS
23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 CHILLED AND CONDENSER WATER PIPING SYSTEMS
23 65 10 HYDRAULIC DRIVE CONDENSER WATER COOLING SYSTEMS
23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT
23 81 23 COMPUTER ROOM AIR CONDITIONING UNITS
PROJECT TABLE OF CONTENTS - 4
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.21 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS FIRE AND LIFE
SAFETY (FLS)
25 05 11.23 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS ENERGY
MANAGEMENT AND CONTROL SYSTEM (EMCS)
25 05 11.26 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS UTILITY
CONTROL SYSTEM (UCS)
25 10 10 UTILITY MONITORING AND CONTROL SYSTEM (UMCS) FRONT END AND
INTEGRATION
DIVISION 26 - ELECTRICAL
26 08 00 APPARATUS INSPECTION AND TESTING
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 24 13 SWITCHBOARDS
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 29 23 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS UNDER 600 VOLTS
26 32 15.00 ENGINE-GENERATOR SET STATIONARY 15-2500 KW, WITH AUXILIARIES
26 33 53 STATIC UNINTERRUPTIBLE POWER SUPPLY (UPS)
26 36 23 AUTOMATIC TRANSFER SWITCHES AND BY-PASS/ISOLATION SWITCH
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 05 13.43 TELEVISION DISTRIBUTION SYSTEM
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
27 41 00 AUDIOVISUAL SYSTEMS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 10 05 ELECTRONIC SECURITY SYSTEMS (ESS)
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 11 00 CLEARING AND GRUBBING
31 21 13 RADON MITIGATION
31 62 50 DENSIFIED AGGREGATE PIERS
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19.61 SEALING OF JOINTS IN RIGID PAVEMENT
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 20 SUBBASES FOR FLEXIBLE PAVING
32 11 23 AGGREGATE BASE COURSES
32 11 23.23 BASE COURSE DRAINAGE LAYERS
32 12 13 BITUMINOUS TACK AND PRIME COATS
32 12 16.16 ROAD-MIX ASPHALT PAVING
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE FACILITIES
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 PAVEMENT MARKINGS
32 31 13.53 HIGH-SECURITY FENCES (CHAIN LINK AND ORNAMENTAL) AND GATES
32 92 19 SEEDING
32 93 00 EXTERIOR PLANTS
DIVISION 33 - UTILITIES
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 11 23 NATURAL GAS AND LIQUID PETROLEUM PIPING
PROJECT TABLE OF CONTENTS - 5
DIVISION 33 – UTILITIES (CONTINUED)
33 30 00 SANITARY SEWERAGE
33 40 00 STORM DRAINAGE UTILITIES
33 51 39 MONITORING WELLS
33 52 40 FUEL SYSTEMS PIPING (NON-HYDRANT)
33 56 10 FACTORY-FABRICATED FUEL STORAGE TANKS
33 57 55 FUEL SYSTEM COMPONENTS (NON-HYDRANT)
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
GBSD Integrated Command Center - FE Warren AFB, WY FEA5
CUI
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 30 00.24
OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS
07/20
PART 1 GENERAL
1.1 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
1.2 CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR PROCESSING
CONSTRUCTION WAGE RATE REQUIREMENTS STATUTE CERTIFIED LABOR
PAYROLLS
1.3 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
1.4 CONTRACTOR PERFORMANCE EVALUATIONS
1.5 EXCEPTION TO COMPLETION TIME AND LIQUIDATED DAMAGES
1.6 CONTRACT DRAWINGS AND SPECIFICATIONS
1.6.1 SETS FURNISHED
1.6.2 REPRODUCTION AND DISTRIBUTION
1.6.3 NOTIFICATION OF DISCREPANCIES
1.6.4 OMISSIONS
1.7 SUBMITTALS
1.8 CONCURRENT CONSTRUCTION
1.9 PAYMENT
1.9.1 PROMPT PAYMENT ACT
1.9.2 PAYMENT FOR MATERIALS STORED OFFSITE
1.10 AVAILABILITY OF UTILITY SERVICES
1.11 UTILITY SERVICE INTERRUPTIONS
1.12 DIGGING PERMITS AND ROAD CLOSINGS
1.13 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1.14 INSURANCE REQUIRED
1.15 SECURITY REQUIREMENTS
1.15.1 Contractor's Employee Identification
1.15.2 Entry Requirements
1.15.3 F.E. Warren AFB Entry Requirements
1.15.4 F.E. Warren AFB DBIDS Sponsor Privileges
1.16 CONTRACTOR QUALITY CONTROL (CQC)
1.17 NONDOMESTIC CONSTRUCTION MATERIALS
1.18 DAILY WORK SCHEDULES AND WEEKLY COORDINATION MEETINGS
1.19 AS-BUILT DRAWINGS
1.20 SIGN
1.21 EQUIPMENT ROOM DRAWINGS
1.22 CONTRACTOR FURNISHED EQUIPMENT DATA
1.23 ACCOMMODATIONS FOR GOVERNMENT INSPECTORS
1.24 PARTNERING
1.25 PROFIT
1.26 LABOR CONDITIONS APPLICABLE TO TEMPORARY FACILITIES
1.27 DRAWING SCALES
1.28 FEDERAL HOLIDAYS
1.29 BASE HOURS
1.30 COST AND TIME IMPACT (CTI) LOG
SECTION 01 30 00.24 Page 1
PART 2 NOT USED
PART 3 EXECUTION
3.1 APPENDIX A- CONTRACT DOCUMENT DISTRIBUTION LIST
ATTACHMENTS:
Appendix A - Contract Document Distribution List
F.E. Warren Contractor Badge Template
Air Force Form 103: Base Civil Engineering Work Clearance Request
Project Sign Details
-- End of Section Table of Contents --
SECTION 01 30 00.24 Page 2
SECTION 01 30 00.24
OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS
07/20
PART 1 GENERAL
Attachments:
Appendix A - Contract Document Distribution List F.E. Warren Contractor Badge Template Air Force Form 103: Base Civil Engineering Work Clearance Request Project Sign Details
1.1 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
In accordance with FAR 31.105(d)(2)(i)(b), for the predetermined schedule of construction equipment use rates, use Engineer Pamphlet (EP) 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule. Copies of each regional schedule may be obtained through the following internet site:
https://www.publications.usace.army.mil/USACE-Publications/Engineer-Pamphlets/ on pages 10 and 11 of 13.
1.2 CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR PROCESSING
CONSTRUCTION WAGE RATE REQUIREMENTS STATUTE CERTIFIED LABOR PAYROLLS
a. Use a commercially-available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing and providing certified labor payrolls are established by the Wage Rate Requirements statute.
b. Obtain and provide for all access, licenses, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the Contractor to comply with the Wage Rate Requirements statute. Use the electronic payroll service to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract. The electronic payroll service must be capable of preserving these payrolls and related basic records for the required three years after contract completion. Obtain and provide electronic system access to the Government, as required to comply with the Wage Rate Requirements over the duration of the construction contract.
(c) The Contractor's provision and use of an electronic payroll processing system must meet the following basic functional criteria:
(1) commercially available;
(2) compliant with appropriate Wage Rate Requirements statute payroll provisions in the FAR;
(3) able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract;
(4) capable of producing an Excel spreadsheet-compatible electronic output
SECTION 01 30 00.24 Page 3 of weekly payroll records for export into an Excel spreadsheet to be imported into the contractor's mode of Resident Management System 3.0;
(5) demonstrated security of data and data entry rights;
(6) ability to produce Contractor-certified electronic versions of weekly payroll data;
(7) ability to identify erroneous entries and track the data/time of all versions of the certified Wage Rate Requirements statute payrolls submitted to the government over the life of the contract;
(8) capable of generating a durable record copy in a Compact Disc (CD) or Digital Versatile Disc (DVD) and Portable Document Format (PDF) file record of data from the system database at the end of the contract closeout. This durable record copy of data from the electronic payroll processing system must be provided to the Government during contract closeout.
d. All Contractor-incurred costs related to the Contractor's provision and use of an electronic payroll processing service must be included in the Contractor's price for the overall work under the contract. The costs for compliance with the Wage Rate Requirements statute by using electronic payroll processing services must not be a separately bid or reimbursed item under this contract.
1.3 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
- U.S. Department of Labor Veterans’ Employment and Training Service
(VETS):
https://www.dol.gov/vets/
- Federal Veteran Employment Information: https://www.fedshirevets.gov/
- Veterans Opportunity to Work (VOW) Program:
https://www.benefits.va.gov/vow/
- U.S. Army Warrior Transition Command Employment Index:
https://wct.army.mil/modules/employers/index.html
- Hiring Our Heroes: https://www.uschamberfoundation.org/hiring-our-heroes
1.4 CONTRACTOR PERFORMANCE EVALUATIONS
See Federal Acquisition Regulation (FAR) Subpart 42.1502(e) for the requirements on past performance evaluations for construction contracts.
For construction contracts valued at or above $750,000.00, including all modifications, the USACE will evaluate Contractor's performance using the web-based Contractors Performance Assessment Reporting System (CPARS).
After the USACE drafts an evaluation (interim or final), the Contractor will have the opportunity to access, review, comment and either concur or non-concur with the evaluation in the CPARS system for a period of 60
SECTION 01 30 00.24 Page 4 days. Access to the CPARS system requires either specific software called PKI certification (recommended method) or a username and password. The PKI certification is a Department of Defense recommendation and to provide security in electronic transactions. The certification software could cost approximately $110 - $125 per certificate per year and may be purchased from an External Certificate Authorities (ECA) vendor. Current information about the PKI certification process and contacting vendors can be found on the web site: https://www.cpars.gov .
1.5 EXCEPTION TO COMPLETION TIME AND LIQUIDATED DAMAGES
In case the Contracting Officer determines that seeding, sodding, and/or planting and/or the specified maintenance thereof is not feasible during the construction period, such work will be exempt from the completion time and liquidated damages. Accomplish this work during the first seeding, sodding, and/or planting period and the specified maintenance period following the completion date.
1.6 CONTRACT DRAWINGS AND SPECIFICATIONS
1.6.1 SETS FURNISHED
Make copies of conformed specifications with amendments or changes incorporated. Utilize the bid drawings and specifications as amended in the performance of the work until CD-ROM or DVD-ROM or electronic copy containing the conformed specifications and contract drawings (i.e., bid drawings that have been posted with all amendment changes) is mailed or sent electronically. See Appendix A for Document Distribution list. See paragraph below for contract drawing reproduction and distribution requirements. The work must conform to the contract drawings, set out in the drawing index, all of which form a part of these specifications. The work must also conform to any of the standard details bound or referenced herein.
1.6.2 REPRODUCTION AND DISTRIBUTION
Reproduce multiple legible hard copy sets (half-size English unless directed otherwise) of contract drawings. Within 14 calendar days after receipt of conformed specifications and drawings consisting of read-only Adobe Acrobat.pdf drawing files, provide legible hard copy drawing and conformed specification sets to the addressees contained in the Contract Document Distribution List for Project in Appendix A to this specification. The Government will process no progress payments prior to receipt of the legible contract drawings and conformed specification sets. After receipt and distribution of the legible hard copy drawing and conformed specification sets, the Government will provide the Contractor with editable CAD file drawings (format defined in Section 01 33 39.00 10 ADVANCED MODELING (BIM/CIM/GIS/CAD) REQUIREMENTS). Prepare final record as-built drawings as defined in Section 01 78 39.00 24 AS-BUILT DRAWINGS.
1.6.3 NOTIFICATION OF DISCREPANCIES
Check all electronically sent drawing files furnished by the government immediately upon their receipt and promptly notify the Contracting Officer of any discrepancies. Follow dimensions marked on drawings in lieu of scale measurements. Enlarged plans and details govern where the same work is shown at smaller scales. All scales shown are based on a standard drawing size of 22" x 34". If any other size drawings are furnished or plotted adjust the scales accordingly. The Contractor must also advise
SECTION 01 30 00.24 Page 5 his sub-contractors of the above. The Contractor must compare all drawings and verify the figures before laying out the work and will be responsible for any errors which might have been avoided thereby.
1.6.4 OMISSIONS
Omissions from the drawings or specifications or the misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or which are customarily performed, does not relieve the Contractor from performing such omitted or misdescribed details of the work but work must be performed as if fully and correctly set forth and described in the drawings and specifications.
1.7 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit items below in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Equipment Room Drawings; G-RO.
1.8 CONCURRENT CONSTRUCTION
Construction work closely related to and/or located at the site of the work under a concurrent contract, including the Integrated Training Center may be in progress simultaneously with work under this contract.
Cooperate with others as necessary in the interest of timely completion of all work. In the event of interference, the notify the Contracting Officer (CO) immediately for resolution and the CO decision is final.
1.9 PAYMENT
1.9.1 PROMPT PAYMENT ACT
Pay requests authorized in GENERAL CONDITIONS (CONTRACT CLAUSES) clause:
"Payments Under Fixed-Price Construction Contracts", will be paid pursuant to the clause, "Prompt Payment for Construction Contracts". Submit pay requests on ENG Form 93 and 93a, "Payment Estimate-Contract Performance" and "Continuation". All information and substantiation required by the identified contract clauses must be submitted with the ENG Form 93, and the required certification included on the last page of the ENG Form 93a, signed by an authorized contractor official and dated when signed. The designated billing office is the Office of the Area Engineer.
1.9.2 PAYMENT FOR MATERIALS STORED OFFSITE
a. As allowed under (FAR) 52.232-5 "Payments Under Fixed Price Construction Contracts", the Administrative Contracting Officer, at their discretion, may authorize progress payments for any material stored off-site provided:
(1) The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract, SECTION 01 30 00.24 Page 6
(2) Material is stored in such a manner to protect it from damage, fire, theft, etc .
(3) The Contractor provides evidence of insurance for material, and,
(4) Material is clearly identified and delineated by contract number for use on the applicable project.
b. The Administrative Contracting Officer reserves the right to inspect any off-site material prior to authorizing progress payments. Provide paid invoices listing the value of material and labor incorporated in the items.
1.10 AVAILABILITY OF UTILITY SERVICES
All reasonably required amounts of domestic water and electricity will be made available to the Contractor by the Government from existing system outlets and supplies. The Contractor is responsible to , at their own expense, make all temporary connections and install distribution lines.
Furnish to the Contracting Officer a complete system layout drawing showing type of materials to be used and method of installation for all temporary electrical systems. Make arrangements with the Using Service, through the Contracting Officer, as to the method of determining the amount of water and electricity to be used by and the method of payment therefore. All temporary lines must be maintainedin a workmanlike manner satisfactory to the Contracting Officer and removed by the Contractor in like manner prior to final acceptance of the construction. Normal quantities of electricity and water used to make final tests of completely installed systems will be furnished by the Government.
1.11 UTILITY SERVICE INTERRUPTIONS
Submit written notification not less than 15 calendar days in advance of each interruption of each utility and communication service to or within existing buildings and facilities being used by others. No single outage will exceed 4 hours unless approved in writing. The time and duration of all outages will be coordinated and approved with the Using Agency by the Contracting Officer.
1.12 DIGGING PERMITS AND ROAD CLOSINGS
The Contractor must allow 14 calendar days from date of written application to receive permission to dig and to close roads. Only close roads one lane at a time and allow vehicular traffic to pass through the construction area. Flag work on or near roadways in accordance with the safety requirements in Safety and Health Requirements Manual EM 385-1-1, which forms a part of these specifications. Do not cause blockage of work located along the alert force route and maintain unobstructed access for alert force traffic at all times.
1.13 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
a. This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the GENERAL CONDITIONS (CONTRACT CLAUSES) clause entitled "Default:
(Fixed-Price Construction)." In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
SECTION 01 30 00.24 Page 7
(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the contractor.
b. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON (5) DAY WORK WEEK
Jan 6 Feb 7 Mar 6 Apr 4 May 4 Jun 4 Jul 4 Aug 3 Sep 2 Oct 3 Nov 5 Dec 9
c. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor will record on the RMS daily CQC report, any occurrence of adverse weather and resultant impact to normally scheduled work, within 24 hours of the event. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the contractor's scheduled work day. Describe in the RMS daily CQC reports the critical path item that is being affected and provide the critical path activity number(s) from the current schedule. The COR must acknowledge and accept the agreed upon occurrence of each adverse weather delay in RMS for the delays to be considered as adverse weather delays.
At the end of each month, identify the number of actual adverse weather delay days that includes days impacted by actual adverse weather (even if adverse weather occurred in previous month), calculated chronologically from the first to the last day of each month, and recorded as full days.
If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph b. above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the GENERAL CONDITIONS (CONTRACT CLAUSES) clause entitled "Default (Fixed Price Construction)". (ER 415-1-15)
1.14 INSURANCE REQUIRED
In accordance with GENERAL CONDITIONS (CONTRACT CLAUSES) clause:
"Insurance Work on a Government Installation," procure the following minimum insurance:
SECTION 01 30 00.24 Page 8
Type Amount
Workmen's Compensation and Employer's Liability Insurance $100,000
General Liability Insurance $500,000 per occurrence
Automobile Liability Insurance Bodily injury $200,000 per person and $500,000 per occurrence Property damage $ 20,000 per occurrence
(Coverages per FAR 28.307-2)
1.15 SECURITY REQUIREMENTS
1.15.1 Contractor's Employee Identification
The Contractor is responsible for furnishing to each employee and for requiring each employee engaged on the work to display such identification as may be approved and directed by the Contracting Officer. Deliver all prescribed identification immediately be delivered to the Contracting Officer, for cancellation upon release of any employees. When the contract involves work in restricted security areas, only employees who are U.S. citizens will be permitted to enter. Proof of U.S. citizenship is required prior to entry. When required by the Contracting Officer, obtain and submit fingerprints of all persons employed or to be employed on the project. (Based on FAR 52.204-2)
1.15.2 Entry Requirements
Base access may be more limited than usual due to COVID-19. Contractors will need to coordinate access with Resident Office personnel.
1.15.3 F.E. Warren AFB Entry Requirements
Submit the information shown on the attached ID Card Application on Contractor letterhead for each prime or subcontractor employee requesting access to F.E. Warren AFB, Wyoming. The information must be delivered to the F.E. Warren project office. Anticipate a minimum of 14 days to process pass requests.
1.15.4 F.E. Warren AFB DBIDS Sponsor Privileges
A maximum of two prime contractor employees may be granted DBIDS sponsor privileges after submitting the appropriate information to Security Forces via the COR. This will allow those individuals to sponsor contractor personnel on the premises of F.E. Warren AFB without accompanying government personnel.
1.16 CONTRACTOR QUALITY CONTROL (CQC)
See Section 01 45 00.00 10 QUALITY CONTROL.
1.17 NONDOMESTIC CONSTRUCTION MATERIALS
The list of excepted nondomestic construction materials or their components referenced in the Buy American Construction Material Contract
SECTION 01 30 00.24 Page 9
Clauses includes the list set forth in paragraph 25.104 of the Federal Acquisition Regulation.
1.18 DAILY WORK SCHEDULES AND WEEKLY COORDINATION MEETINGS
In order to closely coordinate work under this contract, prepare a written agenda/meeting minutes and attend a weekly coordination meeting with the Contracting Officer and Using Service at which time the Contractor must submit for coordination and approval, their proposed daily work schedule for the next two week period. Provide a copy of modifications (MODs), Serial Letters, Requests for Information (RFIs)and any other information that is needed in the minutes of the meeting.
Include required temporary utility services, time and duration of interruptions, and protection of adjoining areas with the Contractor's proposed 2-week work schedule. At this meeting, the Contractor must also submit their schedule of proposed dates and times of all preparatory inspections to be performed during the next 2 weeks. Develop all schedules in accordance with Section 01 32 01.00 10 PROJECT SCHEDULE. Coordination action by the Contracting Officer relative to these schedules will be accomplished during these weekly meetings. Daily reports must be completed and given to the Contracting Officer or Representative within 24 hours of work. All official correspondence such as serial letters and RFIs, with attachments are to be provided in one hardcopy original with original signatures and one electronic (Adobe pdf format) copy by email.
The Government will consider the correspondence to be received when the official hardcopy or electronic copy is received by the designated office.
1.19 AS-BUILT DRAWINGS
See SECTION 01 78 39.00 24 - AS-BUILT DRAWINGS.
1.20 SIGN
On commencement of work on this project, furnish and erect the temporary sign in the location selected by the Contracting Officer near the project site. Maintain the sign in good condition through the project construction period. Upon completion of the project remove the sign from the premises. The project sign must conform to standard drawing attached to this section. A decal of the "Engineer Castle" and the U. S. Air Force emblem will be furnished the Contractor upon request.
1.21 EQUIPMENT ROOM DRAWINGS
Prior to construction, prepare and submit room plans for all mechanical, electrical, and communication rooms or similar areas. The plans must be consolidated for all trades, be to scale, and show all pertinent structural features. In addition, other items such as doors, windows, and cabinets required for installation and which will affect the available space, must be shown. All mechanical and electrical equipment and accessories must be shown to scale in plan and elevation and/or section in their installed positions. All duct work and piping must be shown.
1.22 CONTRACTOR FURNISHED EQUIPMENT DATA
See Section 01 78 36.00 24 WARRANTY OF CONSTRUCTION for Contractor Furnished Equipment Data to be submitted as part of the Warranty Equipment Booklet.
SECTION 01 30 00.24 Page 10
1.23 ACCOMMODATIONS FOR GOVERNMENT INSPECTORS
Furnish furnish a temporary office facility approximately 10 feet x 20 feet with a minimum of 200 square feet of floor space. Locate the temporary office facility where directed and it must be reserved for Government personnel only. Furnish and maintain drinking water facilities, adequate lighting, air-conditioning, heating equipment, and a partition enclosed chemical toilet. The office must be furnished with one legal size filing cabinet with four drawers, one drafting table with stool, one plan rack, one desk, and three chairs. Used furniture, in good condition, will be acceptable. Equip entrance doors with a substantial lock. The Contractor must provide janitor service, fuel for the heating facilities, electricity, and water, all at no cost to the Government, except the Contractor will not be liable for Government long-distance calls. Construct the building so as to be easily moved and relocate the building twice during the contract, if so directed. The entire facility, including furniture, will remain the property of the Contractor and removed from the site after completion of the work.
1.24 PARTNERING
a. The Government intends to encourage the formation of a cohesive partnership with the Contractor. This partnership will be structured to draw on the strengths of each organization to identify and achieve reciprocal goals. The objective is effective contract performance in achieving completion within budget, on schedule and in accordance with plans and specifications. This partnership between the Contractor and the Government will be voluntary and its implementation will not be part of the contract requirements nor will it result in a change to contract price or terms.
b. It is anticipated that immediately after the preconstruction conference, the appropriate Contractor's key personnel and Government key personnel will attend a 2-3 hours informal team building workshop at the Area or Resident Office (as directed).
1.25 PROFIT
a. Use the weighted guidelines method of determining profit on any equitable adjustment change order or modification issued under this contract. The profit factors must be as follows:
Factor Rate Weight Value Degree of Risk 20 See Item Relative difficulty of work 15 b. below Size of Job 15 Period of performance 15 Contractor's investment 5 Assistance by Government 5 Subcontracting 25
b. Based on the circumstances of each procurement action, each of the above factors must be weighted from .03 to .12 as indicated below. Obtain the value by multiplying the rate by the weight. The value column when totaled indicates the fair and reasonable profit percentage under the circumstances of the particular procurement.
(1) Degree of Risk. Where the work involves no risk or the
SECTION 01 30 00.24 Page 11 degree of risk is very small, the weighting should be .03; as the degree of risk increases, the weighting should be increased up to a maximum of .12.
Lump sum items will have, generally, a higher weighted value than the unit price items for which quantities are provided. Other things to consider:
the portion of the work to be done by subcontractors, nature of work, where work is to be performed, reasonableness of negotiated costs, amount of labor included in costs, and whether the negotiation is before or after performance of work.
(2) Relative Difficulty of Work. If the work is most difficult and complex, the weighting should be .12 and should be proportionately reduced to .03 on the simplest of jobs. This factor is tied in to some extent with the degree of risk. Some things to consider: the nature of the work, by whom it is to be done, where, and what is the time schedule.
(3) Size of Job. All work not in excess of $100,000 shall be weighted at .12. Work estimated between $100,000 and $5,000,000 shall be proportionately weighted from .12 to .05.
(4) Periods of Performance. Jobs in excess of 24 months are to be weighted at .12. Jobs of lesser duration are to be proportionately weighted to a minimum of .03 for jobs not to exceed 30 days. No weight where additional time not required.
(5) Contractor's Investment. To be weighted from .03 to .12 on the basis of below average, average, and above average. Things to consider: amount of subcontracting, mobilization payment item, Government furnished property, equipment and facilities, and expediting assistance.
(6) Assistance by Government. To be weighted from .12 to .03 on the basis of average to above average. Things to consider: use of Government-owned property, equipment and facilities, and expediting assistance.
(7) Subcontracting. To be weighted inversely proportional to the amount of subcontracting. Where 80 percent or more of the work is to be subcontracted, the weighting is to be .03 and such weighting proportionately increased to .12 where all the work is performed by the Contractor's own forces.
1.26 LABOR CONDITIONS APPLICABLE TO TEMPORARY FACILITIES
It is the position of the Department of Defense that the Davis-Bacon Act, 40 U.S.C. 276a is applicable to temporary facilities such as job headquarters, tool yards, batch plants, borrow pits, sandpits, rock quarries, and similar operations, provided they are dedicated exclusively, or nearly so, to performance of the contract or project, and provided they are adjacent or virtually adjacent to the site of the work and are established after receipt of the proposal or bid. Clause "Payrolls and Basic Records" of the GENERAL CONDITIONS (CONTRACT CLAUSES) is applicable to such operations.
1.27 DRAWING SCALES
All scales shown are based on a standard drawing size of 22" x 34". If any other size drawings are furnished or plotted, the contractor adjust the scales accordingly. The Contractor must also advise their sub-contractors of the above.
SECTION 01 30 00.24 Page 12
1.28 FEDERAL HOLIDAYS
The following Federal legal holidays are observed by this installation:
New Year's Day 1 January Martin Luther King's Birthday Third Monday in January President's Day Third Monday in February Memorial Day Last Monday in May Juneteenth 19 June Independence Day 4 July Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day 11 November Thanksgiving Day Fourth Thursday in November Christmas Day 25 December
If a wage determination applies the number of holidays specified on it, it has priority over this requirement.
1.29 BASE HOURS
Base operation hours are 6:00 a.m. to 6:00 p.m. daily (Monday through Friday), excluding federal holidays. Access to the base during other times must be requested in writing from the Contracting Officer and will be granted only for extenuating circumstances. Federal Holidays and weekends are considered as scheduled non-workdays.
1.30 COST AND TIME IMPACT (CTI) LOG
a. Any changes with an absolute value under the Simplified Acquisition Threshold (SAT) at the time of initiation of the change and within the Administrative Contracting Officer's (ACO) authority, may be executed using the Cost and Time Impact Log (CTI Log) processes as described herein. The purpose of the CTI Log is to provide efficient and effective change management process for the mutual benefit of the Government and the Contractor while partnering to execute this contract.
b. The CTI Log process is a collaborative, proactive, and efficient change management process. In general, the CTI Log process is as described below.
1. The CTI Log is designated for use on work items determined to be changes where individual costs are anticipated to be less than the SAT. The process starts with a discussion between USACE on-site Contracting Officer's Representative (COR) or ACO and the prime contractor's authorized field representative. If it appears the issue cannot be resolved through a no-cost clarification of the contract requirements, the USACE COR will request the contractor to submit a confirming Request for Information (RFI).
Where the solution to the problem is not apparent and not initially resolvable at the field level, the Contractor may submit to USACE a “non-confirming” RFI and USACE shall provide technical direction. If the absolute value of the change is anticipated to exceed the SAT, the contractor will be advised that a Request for Proposal (RFP) for the change will be forthcoming and that the CTI Log process shall not be utilized.
2. The contractor submits the confirming RFI identifying the
SECTION 01 30 00.24 Page 13 potential Cost and/or Time impact issue as previously discussed between the USACE COR and the contractor's field representative, along with a proposed solution. In addition to the technical details, the RFI shall contain, to the maximum extent practicable, a proposal for the change from the contractor with an acceptable breakdown of all costs (representing both the prime and each of the applicable subcontractors' costs) to include labor, equipment and material. Time impacts, if applicable, must include a Time Impact Analysis (TIA) of work activities. The prime and subcontractor(s) will provide their markups for each of the individual changes as they arise, to include profit development in accordance with (IAW) the alternate Weighted Profit Guidelines approach per UAI 5115.404-73. If mutually agreed upon by both the Government and Contractor, the Contractor may submit the confirming RFI without the detailed cost proposal and/or the Time Impact Analysis, but shall contain a ROM of cost impacts and time impacts. If it is mutually agreed that the Contractor’s cost proposal and TIA may not be included in the confirming RFI, the Contractor shall submit both the proposal and TIA as soon as practicable or by the date specified in the Government’s response to the RFI, whichever is sooner.
3. If the proposal and TIA are included in the RFI from the Contractor, the Government shall evaluate the Contractor’s technical recommendation in the RFI, the Contractor’s proposal, and the TIA. When the technical solution is determined and any cost and/or time impacts are discussed, negotiated (if necessary), and determined to be fair and reasonable, the Government ACO will return the RFI with the technical solution and note that the formal price and time agreement will be captured on the CTI Log.
Under no circumstances will the RFI response act as a Notice to Proceed (NTP) to incur increased costs or time impacts. The official NTP for the applicable change will be granted upon signing of the CTI Log. If the RFI is submitted and signed by the Government without cost and time impacts known, the Government shall return the RFI with the technical direction and request the proposal and TIA by an established suspense date. In either instance, the CTI Log will note the agreed upon price for the change (if any), time extension (if any), and will establish the NTP for the technical direction captured in the RFI.
4. After arriving at a bilateral agreement on price and time impacts associated with the change, the ACO and the contractor’s representative will enter the RFI number and the agreed upon "reasonable price" on the contract CTI Log. At this time, the ACO will electronically sign the applicable log entries, authorizing the contractor to proceed with the scope described by the RFI and at the reasonable price agreed upon. The contractor's authorized representative must also acknowledge the cost and time impact by signing the CTI Log item, prior to proceeding with the work. The official NTP will occur when both the Government and Contractor have both signed the CTI Log.
5. When the aggregate absolute value of changes approaches the appointed ACO's warrant threshold, the individual CTI Log entries (and associated RFls) shall be captured in a single modification document (SF 30). The "SCOPE" paragraph of the modification will contain a summary list of the incorporated CTI Log items. These
SECTION 01 30 00.24 Page 14 aggregate modifications will be processed at least once every month, at a different interval as mutually agreed upon, or when expedited processes are needed to pay for critical features of work such that subcontractors have the ability to bill for work completed in the field. The ACO will sign the SF 30 and provide to the contractor for its signature and return. After the SF30 is executed, the Contractor can bill for the earnings included in the associated CTI Log items listed on the SF30.
6. The CTI Log process may be utilized during the performance of this contract unless termination or suspension of this change management process is desired by either party.
PART 2 NOT USED
SECTION 01 30 00.24 Page 15
PART 3 EXECUTION
3.1 APPENDIX A- CONTRACT DOCUMENT DISTRIBUTION LIST
Appendix A - Contract Document Distribution List
NOTE: Each of the quantities indicated below are for hardcopy sets of the indicated media. CD/DVD shall include PDF copies of the full-size drawings set and the project specifications.
Addressee No. of Sets Drawings Half-size Full-size CD/DVD USACE - Omaha District 2 0 2 CENWO-PMM (Tessin) 1616 Capitol Avenue Omaha, NE 68102
USACE - FE WARREN RO 3 2 2
CENWO-CDD-F (Galanopoulos) PO Box 9508 Cheyenne, WY 82003-9508
USACE - DENVER AO 1 1 2
CENWO-CD-RM (Parker) 98 Inverness Dr. East Ste. 370 Englewood, CO 80012
FE WARREN AFB 90th CES/CENM 2 1 2 ATTN: Charlie Radich Cheyenne, WY 82005
AFCEC 0 0 2
-- End of Section --
SECTION 01 30 00.24 Page 16
DateMEMORANDUM FOR 90 SFS/S5
FROM:
SUBJECT:
The following representative/contractor will require access to F. E. Warren AFB, Wyoming to perform the following contracted services:
Last Name:
First Name:
MI:
Address:
SS Number:
ID Num
State: Phone Number:
Date of Birth:
Eye Color: Employer:
Hair Color: Employee
Destination:Height:
Weight:
Gender:
The following will be completed by the Approval Official:
Hours of Operation (example 0600 – 1800):
Days of Operation: (Monday – Saturday):
Card Expiration Date: (Cannot exceed 1 year from date of issue):
Approving Official.
Last Name:
Approval Official Signature
First Name: Rank:
_______________________________ Digital
The following will be completed by Pass and Registration (90 SFS/S5 ):
Date: _________________ Time: _____________ S5 S Initials: ______________
I acknowledge that I am receiving a pass/card that is the property of F. E Warren AFB. I acknowledge that I must turn it in to my supervisor (Supervisor turn it into sponsoring agency) if I am terminated, it expires or the work is completed and access is no longer required.
Individuals Signature: ___________________________________
Company Name:
Address:
Phone Number:
DATE PREPAREDBASE CIVIL ENGINEERING WORK CLEARANCE REQUEST
(See Instructions on Reverse)
1. Clearance is requested to proceed with work at on Work Order No. , Contract No. , involving excavation or utility disturbance per attached sketch. This area has has not been staked or clearly marked.
2. TYPE OF FACILITY/WORK INVOLVED
G. AIRCRAFT OR VEHICULAR TRAFFIC FLOWA. PAVEMENTS D. FIRE DETECTION & PROTECTION SYSTEMS
H. SECURITYB. DRAINAGE SYSTEMS E. UTILITY OVERHEAD UNDERGROUND
I. OTHERC. RAILROAD TRACKS F. COMM OVERHEAD UNDERGROUND
3. DATE CLEARANCE REQUIRED 4. DATE OF CLEARANCE
5. SIGNATURE OF REQUESTING OFFICIAL 6. TELEPHONE NO. 7. ORGANIZATION
ORGANIZATION REMARKS (Use Reverse for additional comments) REVIEWER'S NAME AND INITIALS
8.
A. ELECTRICAL DISTRIBUTION
B
A
S B. STEAM DISTRIBUTION
E
C. WATER DISTRIBUTION
C
I
D. POL DISTRIBUTIONV
I L
E. SEWER DISTRIBUTION
E
N
F. ENVIRONMENTAL
G
I
G. PAVEMENTS/ GROUNDSN
E
E H. FIRE PROTECTION
R
I
I. ZONEN
G
J. OTHER (Specify)
9. SECURITY POLICE
10. SAFETY
11. COMMUNICATIONS
12. BASE OPERATIONS
13. CABLE TV
14. COMMERCIAL UTILITY COMPANY
TELEPHONE
GAS
ELECTRIC
15. OTHER (Specify)
16. REQUESTED CLEARANCE APPROVED DISAPPROVED
17. TYPED NAME AND SIGNATURE OF APPROVING OFFICER (Chief of Operations Flight or Chief of Engineering Flight) 17a. DATE SIGNED
PREVIOUS EDITIONS ARE OBSOLETE.AF IMT 103, 19940801, V3
AF103
INSTRUCTIONS
The BCE work clearance request is used for any work (contract or in-house) that may disrupt aircraft or vehicular traffic flow, base utility services, protection provided by fire and intrusion alarm system, or routine activities of the installation. This form is used to coordinate the required work with key base activities and keep customer inconvenience to a minimum. It is also used to identify potentially hazardous work conditions in an attempt to prevent accidents. The work clearance request is processed just prior to the start of work. If delays are encountered and the conditions at the job site change (or may have changed) this work clearance request must be reprocessed.
18. REMARKS. (This section must describe specific precautionary measure to be taken before and during work accomplishment. Specific comments concerning the approved method of excavation, hand or powered equipment, should be included.)
AF IMT 103, 19940801, V3 (REVERSE)
AF103
NOTES:
PLANNED COMPLETION DATE:
JAMES SMITH
GENERAL CONTRACTOR
JOHN DOE
ARCHITECT-ENGINEER
HANGAR
FIELD MAINTENANCE
U.S. ARMY CORPS OF ENGINEERS
IN PARTNERSHIP WITH
U.S. AIR FORCE PROJECT
U.S. AIR FORCE
8'-0"
LINE
A
B C
D
E
F
G
H
I
NO SCALE
PROJECT SIGN DETAILS
U.S. AIR FORCE MCP PROJECTS
4'-0"
SPACE
SCHEDULE
LETTER
FRONT VIEW END VIEW
I 4"
H 4" 8 PLANNED COMPLETION DATE 2.5" 1/4"
G 1" 7 GENERAL CONTRACTOR/A-E 1.5" 3/16"
F 5" 6 GENERAL CONTRACTOR/A-E 1.5" 3/16"
E 3" 5 PROJECT NAME CONT'D (IF REQ'D) 4" 1/2"
D 5" 4 PROJECT NAME 4" 1/2"
C 2" 3 U.S. ARMY CORPS OF ENGINEERS 1.5" 3/16"
B 2" 2 IN PARTNERSHIP WITH 1.5" 3/16"
A 4" 1 U.S. AIR FORCE PROJECT 1.5" 3/16"
SPACE HEIGHT LINE DESCRIPTION HEIGHT STROKE
EACH POST
AT 6" CTRS.
GALV. NAILS
NAIL WITH 8D
GROUND LINE
4" X 4" POST
EXTERIOR PLYWOOD
4' X 8' X 1/2"
GALV. BOLT
1/2" DIAM.
ANCHOR
2" X 6"
2" X 4" BRACE
GALV. BOLT
1/2" DIAM.
HELIOS BOLD II, HELVETICA BLACK ROMAN, OR HELVETICA BOLD ROMAN.
8. LETTERING STYLE SHALL BE EITHER HELIOS EXTRA BOLD CONDENSED,
THE SAME BACKGROUND COLOR AS THE SIGN.
7. ALL EXPOSED WOOD…
This is the start of the file's text. The full file is on GovTribe.