QA_25 August 2022.pdf

PDF 118 KB Posted

Attached to
Garrison Project Rip Rap Supply Purchase Federal contract opportunity
Solicitation number
W9128F22Q0097
Issued by
Department of the Army Corps of Engineers Engineering District Omaha

About this file

This document contains questions and answers regarding solicitation number W9128F22Q0097 from the Department of the Army Corps of Engineers Engineering District Omaha for furnishing and stockpiling stone protection at the Government Bay and Wolf Creek Recreation Areas. Offerors must price their offers to account for risk in fluctuating market prices, as economic price adjustments will not be included. The contract shall plan on blading and watering the last mile of County Road 15 and the road to the stockpile areas, with approval required from the McLean County Road Department. Offerors must account for this in their unit prices. The contractor will be responsible for uniformly stockpiling the material within the areas provided, and may need equipment to push the material into the stockpiles depending on their operations. The target award date is no later than September 30th, 2022, with deliveries to begin upon notice to proceed and be completed within 270 days of award.

View the file

Other files for this federal contract opportunity

Other files attached to Garrison Project Rip Rap Supply Purchase, newest first.
File Type Posted
AM0002_W9128F22Q0097.pdf PDF
QA_29 August 2022.pdf PDF
QA_29 August 2022.pdf PDF
Specification_Amended.pdf PDF
AM00001_W9128F22Q0097.pdf PDF
Wolf Creek_Map.pdf PDF
Government Bay_Map.pdf PDF
W9128F22Q0097.pdf PDF
Specification.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers W9128F22Q0097, Government Bay/Wolf Creek Rip Rap

Updated 25 August 2022

1. Does the government anticipate a start date for the project? If there is not a timeframe known, would the government be open to including the EPA Far Clause 52.216-4 Economic Price Adjustment-Labor and Material?

a. As the solicitation states, the delivery should be within 270 days from the award of the contract. The target award for this solicitation is no later than 30 September 2022.

The awardee may begin delivering rock upon receiving notice to proceed. EPA FAR Clause 52.216-4 Economic Price Adjustment – Labor and Material will NOT be included. Offerors should price their offers to account for risk in fluctuating market prices.

2. In the contract solicitation, it mentions the requirement of a water truck and blading of the haul road. This is not mentioned in the price schedule. Could it be confirmed this needs to be accounted for in our unit price? If so, how long are the haul roads?

a. This needs to be accounted for in the unit price. Contract shall plan on blading and watering the last mile of County Road 15 and the road to the stockpile area within the recreation area. The McLean County Road Department receives a lot of complaints from the residences on this section of county road about the dust and condition of the road. Contractor will need to get approval from the McLean County Road Department to blade and water the road.

3. Do you anticipate that the trucks can just dump the material at the stockpile locations? Or will this require equipment to push the material up into the stockpile.

a. This will be based on the contractor’s operation to make sure the volume of rock is stockpiled uniformly within the area provided in the contract documents. No additional stockpile area is available.