B3_W9126G16R1399_Amend_03.pdf
PDF 57 KB Posted
- Attached to
- Upgrade Elevators @ Big Spring TX Federal contract opportunity
- Solicitation number
- W9126G16R1399
About this file
Post Closing Amendment
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B3_1-Acknowledgement_Sheet_DONE.pdf | ||
| B3_W9126G16R1399_Amend_02.pdf | ||
| B3_W9126G16R1399_Amend_01.pdf | ||
| B3_W9126G16R1339_drawings.pdf | ||
| B3_W9126G16R1339_specs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Post Closing Amendment is to change evaluation criteria. Closing date Monday September 26, 2016 at 11AM CST. Period of performance is changed to 420 days.
Amendment must be acknow ledged.
POC: Natasha Kennedy, natasha.p.kennedy@usace.army.mil
1. CONTRACT ID CODE PAGE OF PAGES
J 1 11
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 23-Sep-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9126G-16-R-1399
X 9B. DATED (SEE ITEM 11)
15-Aug-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
23-Sep-2016
CODE
US ARMY ENGINEER DISTRICT, FORT WORTH
ATTN: CESWF-CT
819 TAYLOR ST, ROOM 2A17
FORT WORTH TX 76102-0300
W9126G 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9126G-16-R-1399
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SECTION SF30 - CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 11 00 - STANDARD FORM (SF) 1442 AND CLIN SCHEDULE
The required response date/time has changed from 16-Sep-2016 01:00 PM to 26-Sep-2016 11:00 AM.
The contractor period of performance end date has increased by 100 days from 320 days to 420 days.
SECTION 00 22 11 - PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION CRITERIA, AND BASIS
OF AWARD ONE STEP - BEST VALUE, DESIGN-BUILD (SINGLE AWARD)
The following have been modified:
INSTRUCTION TO OFFERORS
This section was updated on 9/23/16. New text is in red. Deleted text has been struck through.
PART I – GENERAL INFORMATION
1. INQUIRIES
a. Submit general questions and comments and questions relating to proposal procedures or bonds via e-mail to:
Contract Specialist – Natasha Kennedy
U.S. Army Corps of Engineers, CECT-SWF
Email: natasha.p.kennedy@usace.army.mil
Phone: 817-886-1075
b. Submit technical inquiries via: Bidder Inquiry in ProjNet at http://www.projnet.org/projnet
To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system. To self-register go to web page, click BID tab select Bidder Inquiry, select agency USACE, enter Key for this solicitation listed below, and your e-mail address, click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue.
From this page you may view all bidder inquiries or add inquiry.
Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.
The Solicitation Number is: W9126G-16-R-1399
The Bidder Inquiry Key is: 4B878H-F28BIY
The Bidder Inquiry System will be unavailable for new inquires five days prior to the proposal submission date in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.
Offerors are requested to review the specification in its entirety and review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry. A Call Center is available for assistance with the Bidder Inquiry System weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago) at 800-428-HELP.
c. As this is a competitive negotiation acquisition, there is no public bid opening and no information will be given out as to the number of offerors or the results of the competition until all awards are made.
d. Oral explanations or instructions are not binding. Any information given to an offeror which impacts the solicitation and/or offer will be given in the form of a written amendment to the solicitation.
PART II -- PROPOSAL PREPARATION
1. PROPOSAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS
a. REQUIREMENT FOR SEPARATE PRICE AND TECHNICAL PROPOSALS.
(1) Each offeror must submit both a Price Proposal and a Technical Proposal. The Price Proposal and the Technical Proposal must be submitted as separate files. Ensure each separate file is clearly marked to indicate its contents and the identity of the offeror.
(2) Both the Price Proposal and the Technical Proposal must be received by the closing date and time set for receipt of proposals.
(3) No dollar amounts from the Price Proposal are to be included in the Technical Proposal.
(4) All information intended to be evaluated as part of the Technical Proposal must be submitted as part of the Technical Proposal. Do not merely cross-reference similar material in the Price Proposal, or vice versa. Also, do not include links to websites in lieu of incorporating information into your proposal.
(5) Do not include exceptions to the terms and conditions of the solicitation in either the technical or price proposal. Should the offer include any standard company terms and conditions that conflict with the terms and conditions of the solicitation, the offer may be determined "unacceptable" and thus ineligible for award. Should the offeror have any questions related to specific terms and conditions, these shall be resolved prior to submission of the offer.
b. DISCUSSIONS: The Government intends to evaluate proposals and award a stand alone contract without discussions with offerors, in accordance with FAR 52.215-1, Instructions to Offerors—Competitive Acquisitions, however the Government reserves the right to conduct discussions if the Contracting Officer determines them to be necessary.
c. GENERAL INSTRUCTIONS
(1) All pages must be numbered.
(2) Submit only the information/documents specifically required. Do not submit excess information, to include audio-visual materials, electronic media, etc.
(3) Do not use a font size smaller than 10, an unusual font style such as script, or condensed print for any submission. All page margins must be at least 1 inch wide, but may include headers and footers.
(4) The proposals must be organized by the TABs indicated in this section.
(5) “Confidential” projects cannot be submitted to demonstrate capability unless all of the information required for evaluation as specified herein can be provided to the Government as part of the Offeror’s technical proposal. Offerors that include in their proposals information that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, must be clearly marked in accordance with the instructions at FAR 52.215-1, “Instructions to Offerors—Competitive Acquisition”, paragraph (e), “Restriction on disclosure and use of data”.
(6) In the case of an Offeror that is part of a large, multi-segmented business concern, provide information directly pertaining to the specific segment of the business concern (i.e., the division, group, unit, etc.) that will perform work under the prospective contract.
(7) For submissions with page limitations, the pages furnished for organizational purposes only, such as a “Table of Contents” or divider tabs, are not included in the page limitation.
d. INSTRUCTIONS FOR THE PRICE PROPOSAL
The Price Proposal shall be appropriately labeled as such and shall be organized as follows:
Acknowledgement Sheet (File sent with RFP)
Section 00 11 00, Pricing Schedule (to be completed in its entirety by all Offerors.
Copy of Bid Guarantee as required by FAR clause 52.228-1, Bid Guarantee. The original Bid Guarantee shall be posted via mail on the date proposals are due.
e. INSTRUCTIONS FOR THE TECHNICAL PROPOSAL
The Technical Proposal will be appropriately labeled as follows:
Factor 1: EXPERIENCE
Factor 2: TECHNICAL APPROACH
Factor 3: PAST PERFORMANCE
Page Limitations. The following page limitations are established for each factor described above:
Factor 1, Experience - Limited to 5 pages
Factor 2: Technical Approach – Limited to 5 pages
Factor 3, Past Performance - No page limitation
FACTOR 1, EXPERIENCE/PERFORMANCE CAPABILITY: TECHNICAL NARRATIVE ON PROJECTS
OF SIMILAR SCOPE, MAGNITUDE, AND COMPLEXITY
Offeror shall identify at least one two projects of similar scope, magnitude (projects no less than $800,000 $400,000) and complexity as the RFP requirement it and/or its proposed team (i.e., predecessor companies, key personnel who have relevant experience or subcontractors that will perform major or critical aspects of the requirement) has/have successfully completed within the past five eight years and provide a technical narrative of those projects identified with the following: experience on similar projects.
Projects referenced in Factor 1 are highly recommended to be referenced in Factor 3.
The Offeror and its proposed team will be evaluated based on identifying at least one two successfully completed projects within the past eight five years and providing a narrative of experience on similar projects. The narrative shall include a description of the project; total dollar value of the project at the time of award and at the time of completion, the Offeror’s role in the project (i.e., as a prime or a subcontractor), and the name, address and telephone number of the owner. In the case of a federal, state or local government project, provide the name, address and telephone number of the Contracting Officer.
The offeror may include projects completed by predecessor companies. The offeror must explain why it believes the projects are similar in scope, magnitude and complexity to the RFP requirement. When relying on the specific, relevant experience of key personnel, and/or major subcontractor, the description must include, in addition to all the above information, and explanation of what role the key person or subcontractor played in the former project, and what specific role that company, key person or subcontractor would perform in this project.
Standard for Acceptability: This standard is met when the Offeror can provide a technical narrative of construction experience in one two or more completed projects within the past eight five years; similar in scope, magnitude (no less than $400,000 $800,000) and complexity on the following: experience on similar projects. Experience of predecessor companies, key personnel, and major subcontractors may be used to qualify for this factor so long as the key person and/or major subcontractor will participate in this project in a meaningful way. Projects referenced in Factor 1 are highly recommended to be referenced in Factor 3.
The specific elements of experience that must be demonstrated are:
- Experience with elevator construction and/or upgrades of similar size and/or scope with predominance of management and responsibility for the project.
- Experience working on a project ensuring continuity of adjacent existing operations throughout construction.
- Experience managing the upgrade of elevators without loss of facility ability to move sensitive items via elevators throughout the project period of performance.
- Experience working with the USACE including Safety Manual EM385-1-1, 3 phase inspection process, Quality Control, Scheduling
If using subcontractors as team members in demonstrating experience, describe the role they will play in the project and the percentage of work they will be performing.
If submitted project(s) fail Failure to demonstrate the required experience level described within this factor or do not or provide all required information will result in an “UNACCEPTABLE” rating and possible elimination from further consideration for award. Offerors who do not submit experience examples will receive a rating of “acceptable” and may still be considered for award.
FACTOR 2, TECHNICAL APPROACH: TECHNICAL NARRATIVE ON TECHNICAL APPROACH,
METHODS AND PROCEDURES AND SCHEDULE
Proposals will be evaluated as to the Offeror’s ability to perform and to satisfy all contract requirements.
Offeror shall discuss: the technical understanding of the work requirements, and the commitment to accomplish all the work in accordance with the solicitation requirements and schedule; the quality of the Offeror’s approach, methodology, the plan for customer service, Quality Control procedures, and its approach for construction safety protocols and procedures; the workability of the Offeror’s approach as well as the technical feasibility to successfully perform.
Schedule: The Offeror shall provide a narrative that includes, at a minimum, discussion of proposed sequence of work, mandatory phasing, testing and balancing, interim and final acceptance (to include commissioning). Offers shall include a Gantt chart reflecting the major construction activities with the completion period from the applicable contract Notice to Proceed (NTP). The proposal schedule shall be graphically presented, and may be on a maximum paper size of 11”x17”. The schedule shall reflect the major construction milestones, and the sequence of work required for this project. The schedule shall indicate start/finish dates of events and durations. A detailed network analysis is not required as a proposal submittal item.
Offerors are cautioned that if they do not meet the project duration shown in Section 00 73 00 Paragraph 52.211-10, Commencement, execution and Completion of Work of this Request for Proposal their response for Evaluation Factor 2 may be rated Non-Acceptable. Schedules showing Government submittal review durations to be shorter than are contractually mandated may be rated Non-Acceptable.
Standard of Acceptability: This standard is met when the Offeror demonstrates a commitment to accomplish all the work in accordance with the solicitation requirements, committing to meet scheduling requirements. The standard is met when the Offeror demonstrates an understanding of the work requirements has an adequate plan for customer service and the Quality Control, and has construction safety procedures that are adequate for the work to be performed. The standard is met when the Offeror demonstrates a technically feasible approach to meeting the Government’s requirements. This standard is met when the Offeror has demonstrated that it understands the project requirements and that the project will be completed within the contract performance period.
FACTOR 3, PAST PERFORMANCE: For each project submitted under the Experience factor that does not have an evaluation in the Past Performance Information Retrieval System (PPIRS), which includes evaluations submitted in ACASS, CCASS, and CPARS, offerors shall forward a copy of the Past Performance Evaluation Questionnaire (PPQ) included at Attachment 2a to the points of contact responsible for monitoring performance under those contracts. Ensure correct phone numbers and email addresses are provided for the client point of contact.
Completed PPQs can be returned to the offeror or submitted directly from the client to the Government’s point of contact, Natasha Kennedy, via e-mail at: Natasha.P.Kennedy@usace.army.mil. Offerors are responsible for ensuring completed PPQs are received by the Government prior to the proposal closing date/time. If unable to obtain a completed PPQ for a project timely the Offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s).
If any negative past performance information is received to which the Offeror has not previously had an opportunity to respond, the Offeror will be given an opportunity to provide rebuttal. If a PPQ is received on a project that has an evaluation in PPIRS, the PPQ will not be considered.
Offerors who do not submit past performance examples will receive a rating of “acceptable” and may still be considered for award.
f. DIRECTIONS FOR SUBMITTING PROPOSALS
Securely submit your proposal at the AMRDEC SAFE website, https://safe.amrdec.army.mil/SAFE2/
1) At the AMRDEC SAFE website select the link: “I do not have a CAC or this machine is not configured to read my CAC and I would like to access SAFE as a Guest User”.
2) Complete the required information. At “Files:” upload your proposal documents.
3) In the “Recipient Information” section, enter email address “mailto:natasha.p.kennedy@usace.army.mil” and click “Add”
4) In the “Email Setting” section, select:
“FOUO”,
“Encrypt email message when possible”
“Notify me when files are downloaded”
“Require CAC for Pick-up”
5) In the “File Submission” section, click on “Upload”
Contractors are responsible for ensuring the Contracting Office receives their proposal by the due date/time.
Part III. EVALUATION OF PROPOSALS
1. GENERAL ELIGIBILITY FOR TASK ORDER AWARD: In accordance with the FAR, no contract shall be entered into unless the contracting officer ensures that all requirements of law, executive orders, regulations, and all other applicable procedures, including clearances and approvals, have been met.
2. BASIS OF AWARD: Selection for award will be determined using the Low-Priced, Technically Acceptable Process. An evaluation for technical acceptability will be performed on each proposal.
The technically acceptable proposal that provides the lowest price will be selected for award.
Tradeoffs are not permitted. Proposals are not ranked using the non-price factor.
3. EVALUATION OF THE PRICE PROPOSALS
a. Price will be evaluated and considered but will not be scored or combined with other aspects of the proposal evaluation. The proposed prices will be analyzed for reasonableness. They may also be analyzed to determine whether they are realistic for the work to be performed, reflect a clear understanding of the requirements, and are consistent with the information provided by the Offeror. Additionally, all offers will be analyzed for unbalanced pricing.
b. An offeror may be required to confirm its price on either a CLIN, element, or total price basis, and/or provide additional information in support of their price prior to task order award at the Government’s request and discretion.
4. GENERAL TECHNICAL CRITERIA
a. Failure to include all required information may cause the proposal to be considered non-responsive and not considered further for award.
b. Proposals which are generic, vague, or lacking in detail may be considered unacceptable.
5. EVALUATION OF THE TECHNICAL PROPOSAL:
FACTOR 1, EXPERIENCE/PERFORMANCE CAPABILITY:
Rating Description
Acceptable Proposal meets the requirements of the solicitation.
Unacceptable Proposal does not meet the requirements of the solicitation.
The Government will review the project experience submitted up to the limits specified. Offerors must meet all of the following minimum acceptability standards to receive a “ACCEPTABLE” rating:
Receipt of a minimum of one three (3) completed “Experience Information” forms that demonstrate the experience of the offeror and/or proposed team, including subcontractors, on recent, relevant projects.
All blocks must be filled in and all data must be accurate, current, and complete.
Recent: All projects submitted must have been completed within the last 8 5 years by with the Offeror’s being the the prime contractor. proposed team (i.e., predecessor companies, key personnel who have relevant experience or subcontractors that will perform major or critical aspects of the requirement)
Relevant: All projects submitted must be similar in size, scope, and complexity to that described in the solicitation.
The specific elements of experience that must be demonstrated are:
- Experience with elevator construction and/or upgrades of similar size and scope with predominance of management and responsibility for the project.
- Experience working on a project ensuring continuity of adjacent existing operations throughout construction.
- Experience managing the upgrade of elevators without loss of facility ability to move sensitive items via elevators throughout the project period of performance.
- Experience working with the USACE including Safety Manual EM385-1-1, 3 phase inspection process, Quality Control, Scheduling
If using subcontractors as team members in demonstrating experience, the role they will play in the project and the percentage of work they will be performing must be described.
If any of the required information is not included in the form the contractor may be considered non-responsive and not considered further for award.
Failure to demonstrate the minimally acceptability standards under this factor will result in an “UNACCEPTABLE” rating and possible elimination from further consideration for award.
FACTOR 2, TECHNICAL APPROACH
Rating Description
Acceptable Proposal meets the requirements of the solicitation.
Unacceptable Proposal does not meet the requirements of the solicitation.
The Government will review the technical approach submitted up to the limits specified. Offerors must meet all of the following minimum acceptability standards to receive a “ACCEPTABLE” rating:
Provide a thorough and logical narrative describing the proposed approach to fulfilling the project requirements demonstrating the following:
- a commitment to accomplish all the work in accordance with the solicitation requirements
- commitment to meet scheduling requirements
- an understanding of the work requirements
- an adequate plan for customer service and Quality Control
- contains construction safety procedures that are adequate for the work to be performed
- a technically feasible approach to meeting the Government’s requirements
- an understanding of the project requirements and that the project will be completed within the contract performance period.
FACTOR 3, PAST PERFORMANCE:
The Government will review the past performance information for the projects submitted for Factor 1, Experience and assign a rating of Acceptable or Unacceptable, as defined above. The Government will also review recent and relevant evaluations in the PPIRS as well as any other source deemed appropriate by the Government.
Recent: All projects submitted must have been completed within the last 8 5 years with the Offeror being the the prime contractor.
Relevant: All projects submitted must be similar in size, scope, and complexity to that described in the solicitation.
If any negative past performance information is received to which the Offeror has not previously had an opportunity to respond, the Offeror will be given an opportunity to provide rebuttal.
One of the Following Ratings will be Assigned:
Rating Description
Acceptable Based on the offeror’s performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror’s performance record is unknown. (See note below.)
Unacceptable Based on the offeror’s performance record, the Government has no reasonable expectation that the offeror will be able to successfully perform the required effort.
Note: In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror shall be determined to have unknown past performance and shall be rated “acceptable.”
(End of Summary of Changes)