Answers to Requests for Information

View the file

Other files for this federal contract opportunity

Other files attached to Temporary Trailers, newest first.
File Type Posted
PWS.pdf PDF
CombinedSynopsis.pdf PDF
UtilityDrawing.pdf PDF
Drawings.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 Question

A2Please confirm that new (fabricated) are required?
answer:Yes.
A3Are there any Anti-Terrorism Force Protection (ATFP) Requirements for any of the buildings?
answer:No.
A4Will a fire sprinkler system be required in the modular buildings?No. Fire extinguishers are required per PWS section 1.1.
A5If a fire sprinkler system is required, who is responsible for the fire sprinkler system work?N/A
A6If a Fire Sprinkler System is required, please clarify fire sprinkler specifications, scope of work/delineation of responsibility and water flow available.N/A
A7What type of fire alarm system/transmitter does the base use and will the fire alarm system be connected to an existing building on site? Or will they be a stand-alone system?
answer:Stand alone smoke detector system required.
A8Who is providing electric to site?
answer:Government.
A9Please clarify the electrical scope of work and details.
answer:See PWS Section 5.1.4. Each trailer shall be wired to a 100A, single phase 208V subpanel. Final connection shall be by the Government in a separate contract.
A10Comment 5.1.4.1. states“Each modular unit shall be wired back to a 100A, single phase 208V subpanel”. Typically the modular panels are minimum 150 amp. Will this impact the site electrical available?
answer:Electrical service to site is insufficient to support 150 amp per trailer subpanels
A16Please confirm that the NEANG site contractor will bring the utilities into the Wet Modular Building footprint?
answer:Trailer contractor responsible for providing a single connection point for the Wet Modular Building for water and sewer. The Government will make final utility connections. The trailer contractor will also be responsible for providing a backflow preventor. This information will be included in a subsequent addendum to the bidding documents.
B2Who will run the mains and make the final connection of the site utilities?
answer:Government.
C3Will manifolding of all the utilities and final connections be made by others?
answer:See previous answers. Individual electrical connections to each 100A subpanel made by the Government. Water/Sewer connection made by the Government to a single connection point provided by trailer contractor.
A11Are there any site plans showing underground utilities and elevations on site?
answer:Partially. The existing plans will be submitted with a subsequent addendum to the bidding documents. A topographic survey with elevations is not currently available.
A13Are there any plans (an official Site Plan) that shows the modular unit locations on site; to include grades and site utilities?
answer:No.
A14Please clarify comment from 5.1.3 Site requirements; and what is existing and was is required in the scope of work. We need more information to work out this requirement.
answer:Contractor responsible for leveling and securing the individual modular units together into one cohesive pod.
A17Can ABS “foundation” Pads be used on grade for the building foundations; with a NE P.E. Sealed Blocking Plan by the modular building contractor?
answer:Yes.
A25Subject to the General Layout Plan showing each building having different building standoffs from ~ 13’-0” up to 18’-8”; do any or all modular buildings require exterior fire rated walls? If so, please clarify the specific requirements for each building exterior wall.
answer:No.
B1The RFP states that the contractor is responsible for any site elevation corrections to allow for the installation of the modular buildings. Are there any civil drawings or site photos that could be supplied to provide the needed information to have this scope included in our pricing.
answer:Topo drawings are unavailable, however site visit is recommended and will be coordinated through the contracting office.
B6Will there be any other prints requried, for example will there need to be a foundation drawing provided during the course of the project? Not due with the bid, but what engineering do we need to account for?
answer:No engineered drawings required other than final trailer floor plans as laid forth in PWS.
A18Please provide a geotechnical soils report, so we can determine the foundation design and requirements.
answer:Not available.
A21Are canopies over decks required? Please specify each building door canopy requirement.
answer:No.
A22Are there any ADA requirements for the building and/or access systems? Please clarify.No.
A20Does each building have to have a handicap ramp? Please specify each building door ADA Ramp requirement.
answer:No
A23the modular units require gutters and downspouts by the modular building contractor? If so, please clarify spec and scope of work.No.
A24If downspouts are required by modular building contract, please confirm that they can drain to splash blocks on grade.
answer:N/A
A26Can you please provide us with the anticipated off-rent (dismantle/removal) dates for each modular building, so we can make sure a unit(s) will not be in the way of another unit; restricting it from removal.
answer:See PWS Section 5.3. - anticipated off-rent dates can be calculated from initial and follow-on phases.
B5Who will be handling the inspections on the work performed on site?
answer:Government/COR.
C2Correct Submittal Method?
answer:Submit through the contracting officer.
C4What material do the steps need to be?Exterior grade material and shall comply with building code.
A19Can aluminum access systems (decks, steps, ramps) be used? Please specify each building door access system requirement.
answer:Yes - minimum access requirement is stairs.
A15Can J Hooks above the suspended ceiling be used for all low voltage wiring (data, fire alarm, etc..)?
answer:Yes.