W91236-17-R-0003_Final_RACP.pdf
PDF 376 KB Posted
- Attached to
- Access Control Point at DLA Richmond VA Federal contract opportunity
- Solicitation number
- W91236-17-R-0003
About this file
W91236-17-R-0003 Solicitation DLA Access Control Point
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| DLA_Access_Control_Pt._Questions_&_Answers.pdf | ||
| W91236-17-R-0003_-Posted_Access_Control_Point.pdf | ||
| PRO-16-01PlanApprovalLetter.pdf | ||
| All_Full_Size_Drawings.pdf | ||
| RACP_FY15_DSCR1501-_Specs_Vol_2_Subm._Register.pdf | ||
| RACP_FY15_DSCR1501-_Specs_Vol_1.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation Number W91236-17-R-0003 for the construction of an Access Control Point at DLA Richmond, VA.
This project is for the construction of an Access Control Point at DLA Richmond, VA
The magnitude of construction for this project is betw een $5,000,000 and $10,000,000.
The NAICS Code apolicable to this procurement is 236220 - Commercial and Institutional Building Construction.
The Bid / Performance / Payment bonds w ere revised in August 2016 - Contractors must use the correct forms.
This is an competetive 8(a) acquisition.
KEVIN E COMEGYS
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
07-Nov-2016
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________913 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________4 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________07 Dec 2016 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
USA ENGINEER DISTRICT, NORFOLK
803 FRONT STREET
NORFOLK VA 23510-1096
W91236
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
12:00 PM (hour) Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
757-201-7183FAX:TEL: TEL: FAX:
W91236-17-R-0003 62
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W91236-17-R-0003
Section 00 01 10 - Table of Contents
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 1 All Full Size Drawings 82 09-AUG-2016 Attachment 2 RACP FY15 DSCR1501
Specs Vol 1
470 09-AUG-2016
Attachment 3 RACP FY15 DSCR1501 Specs Vol 2
714 09-AUG-2016
Attachment 4 PRO-16 Plan Approval 2
Section 00 11 00 - SF 1442 and CLIN Schedule
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job DSCR Access Control Point
FFP
Base Bid - All work related to the construction of the DSCR Access Control Point, complete, as shown on the drawings and specifications.
FOB: Destination
NET AMT
0002 50 Cubic
Yard
OPTION Option
FFP
Option Bid - Unit price for 50 cubic yards of trench over-excavation and replacement with compacted imported suitable fill material, beyond the requirements specified in the project drawings and specifications. Exclusive of CLIN 0001 and 0003.
0003 20 Cubic
Yard
OPTION Option
FFP
Option Bid - Unit price for 20 cubic yards of additional bulk excavation and replacement with compacted imported controlled structural fill, beyond the requirements specified in the project drawings and specifications. Exclusive of CLIN 0001 and 0002
Section 00 21 00 - Instructions, Conditions & Notices to Offerors
NOTICE TO OFFERORS
NOTICE TO OFFERORS
A. Project Overview:
The contractor shall provide all labor, equipment, tools, materials, transportation, management, supervision and other items and services necessary to build a standard design Access Control Point to include: Gate House, guard booths, inspection canopies and search area shelter, roadways, parking, lighting, traffic control signals, passive and active vehicle barriers with comprehensive control systems, information systems, fire protection, alarm systems, Intrusion Detection System Installation, and Energy Monitoring Control Systems connection. This project will be constructed on a constrained site with limited and controlled physical access and restricted/limited laydown area; and adjacent to an active client operation directly adjacent to or surrounded by activities or normal operations which cannot be stopped or eliminated during construction.
B. OFFEROR'S QUESTIONS AND COMMENTS
Note: All questions and/or comments should reach the above referenced Contracting Office via ProjNet no later than 30 November 2016 in order that they may be given consideration or actions taken prior to receipt of offers. ProjNet will close at 8am EST on 30 November 2016.
Specific instructions:
1. Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://www.projnet.org/projnet.
2. To submit and review inquiry items, offerors will need to be a current registered user or self-register into system.
To self-register go to web page, click BID tab select Bidder Inquiry, select agency USACE, enter Key for this solicitation listed below, and your e-mail address, click login. Fill in all required information and click create user. Verify that information on next screen is correct and click <continue>. From this page you may view all inquiries or add inquiry. Offerors will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.
3. The Solicitation Number is : W91236-17-R-0003
4. The Bidder Inquiry Key is: CM9XRD-QPMMFY
5. The Bidder Inquiry System will be unavailable for new inquires 10 days prior to proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.
6. Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
7. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
C. AWARD TO RESPONSIBLE OFFEROR
In accordance with FAR Subpart 9.1, the Contracting Officer will perform an affirmative responsibility determination to ensure that the Offeror has (a) adequate financial resources to perform; (b) ability to comply with the required performance schedule; (c) a satisfactory performance record; (d) a satisfactory record of integrity and business ethics; (e) the necessary equipment and facilities to perform or the ability to obtain them; and (f) be otherwise qualified and eligible to receive award.
D. WAGE DETERMINATION:
The Davis Bacon Act is applicable to this solicitation.
E. CONTRACT TERM:
This contract has one (1) base CLIN and two (2) option CLINs not to exceed 913 days.
F. SMALL BUSINESS ADMINISTRATION (SBA):
The assigned SBA Requirement Number is 0304/16/608101
G. EVIDENCE OF AUTHORITY TO SIGN OFFERS
Evidence of the authority of individuals signing offers to submit firm offers on behalf of the offeror is required except where the offer is signed, and shows that it is so signed, by: the President, Vice-President, or Secretary of an incorporated offeror; a partner in the case of a partnership; or the owner in the case of a sole proprietorship. Failure to submit with the offer satisfactory evidence of the authority of all other persons may be cause for rejection of the offer as invalid or nonresponsive.
H. PREAWARD SAFETY CONFERENCE
(1) Where an apparent successful offeror, in performance of contracts during the previous three-year period, incurred one or more accidents, or where, in the opinion of the Contracting Officer, there is any question regarding this compliance with any safety or accident prevention requirement, such bidder, on request of the Contracting Officer prior to any award under this solicitation, shall attend a conference with representatives of the Contracting Officer to discuss any such accidents or non-compliance, the reason for their occurrence, and measures which will be taken to preclude any recurrence thereof.
(2) Information elicited at this conference will be used by the Contracting Officer, in conjunction with other information obtained in a preaward survey, in determining the offeror's responsibility.
(3) The items discussed, the preventive measures considered, and any conclusions reached in this conference shall be recorded in minutes of the meeting which will be provided within 10 days of the conference and shall be authenticated by the signatures of representatives of the bidder and the Contracting Officer, and any procedures noted therein as agreed upon shall become an obligation of the offeror, along with all other safety and accident prevention requirements of the contract, if award is made to him.
I. INSPECTION OF THE SITE
Prospective offerors are invited to attend a site visit 16 November 2016. Arrangements for inspection of the site shall be made in accordance with the guidance as provided in clause 52.236-27, entitled "SITE VISIT
(CONSTRUCTION)."
J. INCURRING COSTS
The Government is not liable for any costs incurred by the offeror submitting an offer in response to the this solicitation.
K. AGENTS
Offers signed by an Agent must be made in the name of the Principal and must be accompanied by evidence of said Agent’s authority to act on behalf of its Principal.
L. UNBALANCED BIDS
Any offer which is materially unbalanced as to prices for the Base Items and the Optional Items may be rejected as non-responsive or otherwise not considered for award. An unbalanced offer is one which is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.
M. UNAUTHORIZED INSTRUCTIONS FROM GOVERNMENT OR OTHER PERSONNEL
The contractor shall not accept instructions issued by any person, employed by the U.S. Government or otherwise, other than the Contracting Officer or the Authorized Representative of the Contracting Officer acting within the limits of his/her authority as defined in the Designation of Authority letter. A copy of the Designation of Authority letter will be furnished to the contractor at time of contract award.
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government 0002 Destination Government Destination Government 0003 Destination Government Destination Government
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
0001 913 dys. ADC 1 N/A
0002 N/A N/A N/A N/A
0003 N/A N/A N/A N/A
CLAUSES INCORPORATED BY REFERENCE
52.204-16 Commercial and Government Entity Code Reporting JUL 2016 252.236-7008 Contract Prices-Bidding Schedules DEC 1991
CLAUSES INCORPORATED BY FULL TEXT
52.215-1 INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION (JAN 2004)
(a) Definitions. As used in this provision--
“Discussions” are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer's discretion, result in the offeror being allowed to revise its proposal.
“In writing or written” means any worded or numbered expression which can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.
“Proposal modification” is a change made to a proposal before the solicitation's closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.
“Proposal revision” is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.
“Time”, if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include Saturdays, Sundays, and legal holidays. However, if the last day falls on a Saturday, Sunday, or legal holiday, then the period shall include the next working day.
(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).
(c) Submission, modification, revision, and withdrawal of proposals. (1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and (ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror.
Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.
(2) The first page of the proposal must show--
(i) The solicitation number;
(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);
(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;
(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror's behalf with the Government in connection with this solicitation; and
(v) Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent's authority, unless that evidence has been previously furnished to the issuing office.
(3) Submission, modification, or revision, of proposals.
(i) Offerors are responsible for submitting proposals, and any modifications, or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.
(ii)(A) Any proposal, modification, or revision received at the Government office designated in the solicitation after the exact time specified for receipt of offers is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and--
(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or
(2) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government's control prior to the time set for receipt of offers; or
(3) It is the only proposal received.
(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(v) Proposals may be withdrawn by written notice received at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at 52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.
(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.
(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225-17, Evaluation of Foreign Currency Offers, is included in the solicitation.
(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.
(7) Offerors may submit revised proposals only if requested or allowed by the Contracting Officer.
(8) Proposals may be withdrawn at any time before award. Withdrawals are effective upon receipt of notice by the Contracting Officer.
(d) Offer expiration date. Proposals in response to this solicitation will be valid for the number of days specified on the solicitation cover sheet (unless a different period is proposed by the offeror).
(e) Restriction on disclosure and use of data. Offerors that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall--
(1) Mark the title page with the following legend: This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed--in whole or in part--for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of--or in connection with-- the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and
(2) Mark each sheet of data it wishes to restrict with the following legend: Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.
(f) Contract award. (1) The Government intends to award a contract or contracts resulting from this solicitation to the responsible offeror(s) whose proposal(s) represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.
(2) The Government may reject any or all proposals if such action is in the Government's interest.
(3) The Government may waive informalities and minor irregularities in proposals received.
(4) The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror's initial proposal should contain the offeror's best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
(5) The Government reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit cost or prices offered, unless the offeror specifies otherwise in the proposal.
(6) The Government reserves the right to make multiple awards if, after considering the additional administrative costs, it is in the Government's best interest to do so.
(7) Exchanges with offerors after receipt of a proposal do not constitute a rejection or counteroffer by the Government.
(8) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more contract line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.
(9) If a cost realism analysis is performed, cost realism may be considered by the source selection authority in evaluating performance or schedule risk.
(10) A written award or acceptance of proposal mailed or otherwise furnished to the successful offeror within the time specified in the proposal shall result in a binding contract without further action by either party.
(11) If a post-award debriefing is given to requesting offerors, the Government shall disclose the following information, if applicable:
(i) The agency's evaluation of the significant weak or deficient factors in the debriefed offeror's offer.
(ii) The overall evaluated cost or price and technical rating of the successful and the debriefed offeror and past performance information on the debriefed offeror.
(iii) The overall ranking of all offerors, when any ranking was developed by the agency during source selection.
(iv) A summary of the rationale for award.
(v) For acquisitions of commercial items, the make and model of the item to be delivered by the successful offeror.
(vi) Reasonable responses to relevant questions posed by the debriefed offeror as to whether source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities were followed by the agency.
(End of provision)
52.215-20 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA OR INFORMATION OTHER
THAN CERTIFIED COST OR PRICING DATA (OCT 2010)—ALTERNATE IV (OCT 2010)
(a) Submission of certified cost or pricing data is not required.
(b The Government request a price breakdown (i.e., labor, equipment, and material) as backup to the pricing provided in the CLIN Schedule. The breakdown shall set forth a summary of the total estimate costs by cost element and major subcontractor for the proposal cost of each CLIN separately, including all direct and indirect charges, fee, profit, and overhead. The price breakdown shall submitted in Excel format in a sealed envelope marked “Price Breakdown Information”. The price breakdown is required to be submitted no later than three (3) working days following the date of request by the Contracting Officer. This information is required for the initial price proposal as well as any revised price proposals.
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a firm fixed-price contract resulting from this solicitation.
52.217-5 EVALUATION OF OPTIONS (JUL 1990)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY
2014)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
28% 6.9%
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Defense Logistics Agency Defense Supply Center Richmond (DSCR) Richmond, VA.
52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT--CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American --Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225- 9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested--
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.
The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be _20_ percent of the bid price or $3,000,000.00, whichever is less.-
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for-- 16 Nov 2016 – 10:00am
(c) Participants will meet at—
Project Site – Route 301 Jeff Davis Hwy.
North Feeder Rd.
Section 00 22 11 - Proposal Submission Requirements, Evaluation Criteria, Basis of Award
PROPOSAL SUBMISSION REQUIRE
Section 00 22 11
1. OVERVIEW
This is a Best Value Lowest Price Technically Acceptable (LPTA) solicitation for the construction of an Access Control Point at the Defense Logistics Agency located in Richmond, VA.
2. BASIS OF AWARD
The Contracting Officer/Source Section Authority will award a firm fixed-price contract based on the best overall (i.e., best value) proposal that is determined to be technically acceptable to the Government in accordance with LPTA evaluation procedures and has the lowest evaluated price. To be considered technically acceptable and receive consideration for award, a rating of no less than “Acceptable” must be achieved for Factor 1 - Specialized Experience and Factor 2 - Past Performance. The Government will not award a contract to an Offeror whose proposal contains a deficiency, as defined in FAR 15.001. Factor 3 – Price will not be rated or scored, but will be evaluated for fairness and reasonableness through use of a price analysis.
3. FACTORS TO BE EVALUATED
3.1 Proposal Evaluation: The proposal will be evaluated on an “Acceptable” / “Unacceptable” basis using the following evaluation factors:
3.1.1 Factor 1 - Specialized Experience: Each Offeror’s documented specialized experience will be reviewed to determine if the Offeror demonstrates recent and relevant specialized experience meeting or exceeding the minimum requirements and criteria set out in the solicitation.
3.1.2 Factor 2 - Past Performance: Each Offeror’s past performance will be reviewed to determine if the Offeror’s performance record supports a reasonable expectation that the Offeror will successfully perform the required effort.
3.1.3 Factor 3 - Price: The resulting award will be a firm fixed-price contract. Price reasonableness will be utilized in the evaluation of the firm-fixed price effort.
3.2 Price Proposal Evaluation: The LPTA procedure is applied to known firm requirements, usually readily available in the commercial marketplace, where a fair and reasonable price determination is based on adequate competition. Therefore, price analysis will normally be used to determine the total evaluated price to support the selection of the lowest price, technically acceptable offeror. Although in exceptional cases when the determination of a fair and reasonable price requires additional information, the Contracting Officer may conduct a cost analysis to support the determination of whether the proposed price is fair and reasonable.
3.3 Source Selection Decision: The award will be made to the lowest price Offeror who submits a proposal that is otherwise “acceptable” when reviewed against all of the evaluation factors outlined in the RFP.
4.0 PROPOSAL SUBMISSION
4.1 Any legally organized Offeror who agrees to follow the conditions of the RFP may submit a proposal.
4.2 Do not submit any materials not required by this solicitation (such as company brochures, etc).
4.3 Offerors shall submit their proposal packages to US Army Corps of Engineers, Norfolk District at the address shown in Block 7 of the Standard Form 1442. Proposals must be received in the Norfolk District not later than the time and date specified in Block 13 of Standard Form 1442.
4.4 The Government is not liable for any costs incurred by the Offerors submitting an offer in response to this solicitation.
4.5 Offerors are cautioned that “parroting” of the requirements with a statement of intent to perform does not reflect an understanding of the requirement or capability to perform. Offerors are responsible for including sufficient details to permit a complete and accurate evaluation of their proposal. Failure to provide sufficient detail may result in an unacceptable rating. Proposals received will be considered proprietary information and shall be clearly marked as such by the Offeror.
4.6 Proposal Submission Requirements:
4.6.1 The Offeror’s proposal shall consist of two (2) volumes. They are Volume I – Performance Capability and Volume II – Price and Pro Forma Information. The proposal shall not contain classified data. The use of hyperlinks in proposals is prohibited.
4.6.2 Each volume of the proposal shall be submitted in a separate three-ring binder with a table of contents and tabbed section dividers in accordance with paragraphs 5.1 and 5.2. The cover of each volume shall be labeled with the project name, installation name, solicitation number, volume number, and the Offeror’s name. Submit one (1) original and four (4) copies of Volume 1 and submit one (1) original and one (1) copy of Volume 2. The original hardcopy of each volume shall be clearly marked “Original” and the original signatures shall be in blue ink. Copies of each volume shall be clearly marked as “COPY XX of XX”. In addition to the hard copy proposals, submit one
(1) electronic, non-editable, copy of each volume on a separate CD ROM labeled to match its respective hard copy volume.
4.6.3 The proposal shall be submitted in an 8-½ inch x 11 inch format (except that tables and graphic representations may be submitted on folded 11 inch x 17 inch pages). Pages may be single-sided or double-sided and shall be numbered. Text shall have a minimum twelve (12) point Arial or Times New Roman font. No proposal information may be included by reference. Volume I of the proposal shall be limited to no more than 75 pages, excluding Past Performance Questionnaires which are not included in the page count. Text printed on two sides of a page will be counted as two (2) pages. There are no page limitations for Volume II of the proposal.
4.6.4 Any pages that are changed as a result of negotiations or proposal revisions should be of a different color and have changed information clearly marked by a vertical line in the right margin of the page. The revised pages shall be dated.
4.6.5 All pages of each volume shall be appropriately numbered and identified by the complete project name, installation name, solicitation number, and the Offeror’s name in the header and/or footer. A Table of Contents should be created using the Table of Content feature in MS Word. MS Word (doc) files shall use the following page setup parameters:
Margins – Top, Bottom, Left, Right – 1”
Gutter – 0”
From Edge – Header, Footer 0.5”
Page Size, Width – 8.5”
Page Size, Height – 11”
NOTE: 11 inch X 17 inch folded pages are acceptable for tables/graphic representations and will be counted as one page.
The following additional restrictions apply:
a. File Packaging. PDF Files shall be submitted in read-only format. All price breakdown information shall be submitted in Microsoft Office Excel Read/Write format and viewable in Microsoft Excel 2007 to aide in the cost/price evaluation. Each Offeror is responsible for ensuring that the hardcopy is consistent with the electronic copy of the proposal. In the event of any conflict between the electronic and hard copy submissions, the hard copy submission will govern and will be the material upon which the Government will base its evaluation and ultimately, its decision.
b. Content Requirement. All information shall be confined to the appropriate volume. The Offeror shall confine submissions to essential matters, sufficient to define the proposal in a concise manner and to permit a complete and accurate evaluation.
5.0 PROPOSAL INFORMATION AND RELATED EVALUATION FACTORS
5.1 VOLUME 1 – PERFORMANCE CAPABILITY
Factor Location Description
TAB A SF 1442 and Proposal Data Sheet (Included at Attachment 1, Section 00 22 11)
Factor 1 TAB B Specialized Experience
Factor 2 TAB C Past Performance
5.2 VOLUME 2 – PRICE AND PRO FORMA INFORMATION
Factor Location Description
FACTOR 3 TAB A Price (Standard Form 1442 and Contract Line Item Schedule)
N/A TAB B Bid Guarantee
N/A TAB C Required Pre-Award Information
6.0 EVALUATION APPROACH – VOLUME 1 – PERFORMANCE CAPABILITY
All proposals will be subject to evaluation by the Source Selection Evaluation Board (SSEB).
6.1 The overarching evaluation approach for all factors is as follows:
6.1.1 Adequacy of Response. The Government will evaluate the proposal to determine if, based on the Offeror’s record of specialized experience and past performance, it has a reasonable expectation that the Offeror will be able to successfully perform the required effort.
6.2 TAB B – FACTOR 1 – SPECIALIZED EXPERIENCE
6.2.1 SUBMISSION REQUIREMENTS:
6.2.1.1 The Offeror and key subcontractor(s) (if being proposed) shall each demonstrate recent, relevant experience on similar projects, using the form provided in Attachment 2, entitled “Company Specialized Experience – Offeror or Key Subcontractor.” The Offeror is defined as the company or firm that is proposed to serve as the prime contractor under the contract. A key subcontractor is defined as any subcontractor that the Offeror plans to use to perform any of the key features of work identified in paragraphs 6.2.2.3.a thru 6.2.2.3.d below. If the Offeror plans to use a key subcontractor(s), then each key subcontractor(s) shall provide a Letter of Commitment on key subcontractor letterhead following the format provided in Attachment 3, entitled “Letter of Commitment of Key Subcontractor.”
6.2.1.2 If the Offeror is a joint venture, the proposal shall describe the role that each firm in the joint venture will play in executing the project. The demonstrated experience may come from any of the entities involved in the venture so long as they served as a prime contractor on the example project.
6.2.1.3 When proposing as a joint venture, all members of the joint venture shall sign the SF 1442 and the bid bond unless a written agreement by the joint venture is furnished with the proposal designating one firm with the authority to bind the other member(s) of the joint venture. In addition, a copy of the joint venture agreement shall be submitted with the proposal. Failure to comply with this requirement may eliminate the proposal from further consideration.
6.2.1.4 In the case of mentor/protégé relationships, the relationship must be established by the partners and approved by the Contracting Officer prior to proposal submission. Once the relationship has been approved, the demonstrated experience of the Offeror can come from any of the entities involved in the relationship. The approved mentor/protégé document from the Contracting Officer must be submitted along with the teaming agreement.
6.2.1.5 If after award, any key subcontractor(s) identified in the proposal is not able to fulfill this obligation, replacement key subcontractor(s) with equal or better skills and experience shall be presented for acceptance and approval by the Contracting Officer. Replacement key subcontractor(s) for this solicitation shall be required to have the qualifications and experience meeting or exceeding those identified in the proposal. The Offeror shall obtain the Contracting Officer’s written consent before making any substitution for these designated subcontractors.
6.2.1.6 If any firm included in the proposal, either as a joint venture partner, prime contractor, or key subcontractor(s) has multiple divisions, units, or functions, then the Government will consider only project examples performed by the division, unit, or function submitting the offer.
6.2.1.7 The Offeror and key subcontractor(s) (if being proposed) may submit no more than twelve (12) project examples to demonstrate the type/scope key features of work and complexity attributes identified in in the Evaluation Criteria.
6.2.1.8 The Government will consider submitted projects involving contracts with private concerns, local and state governments, or the federal government.
6.2.2 EVALUATION CRITERIA:
The Government will evaluate the example projects submitted by the Offeror and key subcontractor(s), if applicable, to determine if they demonstrate recent, relevant Specialized Experience as specified below:
6.2.2.1 Recent. For a submitted project to be considered “Recent” it shall be well underway; i.e., at least 80% construction progress complete, or has been completed within the ten (10) years preceding the date of this Solicitation. A project that does not meet the definition of “recent” will not be considered by the Government.
6.2.2.2 Relevant. The Offeror’s submitted projects will be considered “Relevant” if taken together they clearly demonstrate the requirements for “similar in type/scope” and “similar in complexity” defined below.
6.2.2.3 Type/Scope. Submitted projects must demonstrate “similar in type/scope” key features of work in accordance with the following criteria:
a. Roadway construction while maintaining two-way traffic flow through the construction site.
b. Active vehicle barriers (K-12 or M50 rated type) and associated safety and control system.
c. Passive vehicle barriers (K-4, K-8, K-12, M30, M40, or M50 rated type) with the project(s) having a crash-rated cable-based passive barrier system or a crash-rated fence barrier system.
d. Gatehouse or similar structure. Similar structure would include any structure that is built of the same general materials and methods of construction and is at least 800 sq-ft in size. Pre-manufactured structures do not meet this requirement.
The Offeror and key subcontractor(s) (if being proposed) each shall submit three (3) project examples for each key feature of work identified in paragraphs a. thru d. above. A single project may, but need not, demonstrate more than one key feature of work.
If the Offeror plans to self-perform any of the above key features of work, then the Offeror must demonstrate having self-performed this type of work on their example projects. If the Offeror does not plan to self-perform this work, then the Offeror’s key subcontractor(s) shall demonstrate this experience on their submitted projects.
Failure to submit three (3) project examples for each key feature of work identified in paragraphs a. thru d. above will result in a “Deficiency” rendering the proposal “Unacceptable” for Factor 1 and ineligible for award.
6.2.2.4 Complexity. Submitted projects must demonstrate “similar in complexity” attributes in accordance with the following criteria:
a. Construction within a constrained site.