SOW-_Expand_Fire_Suppression_System_Bldg._1001.pdf

PDF 261 KB Posted

Attached to
Expand Fire Suppression System Bldg 1001 Federal contract opportunity
Solicitation number
W911YN18B5001
Issued by
Department of the Army Florida Army National Guard

About this file

Statement Of Work

View the file

Other files for this federal contract opportunity

Other files attached to Expand Fire Suppression System Bldg 1001, newest first.
File Type Posted
Questions_and_Answers.docx DOCX document
Abstract_(W911YN18B5001).pdf PDF
Q_and_A's_09062018.pdf PDF
W911YN18B5001-0002.pdf PDF
Site_Visit.pdf PDF
PreBidSlides_W911YN18B5001.pdf PDF
W911YN18B5001-0001.pdf PDF
Question_and_Answers.docx DOCX document
W911YN18B5001.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL

125th FIGHTER WING

FLORIDA AIR NATIONAL GUARD

BASE CIVIL ENGINEERING

14300 FANG ROAD, JACKSONVILLE IAP, FL. 32218-7933

Project #: LSGA170650

STATEMENT OF WORK

16 March 2018

EXPAND

FIRE SUPPRESSION SYSTEM

BUILDING 1001

Flt. Line Avionics / Tool Room / Tire Shop

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL

Table of contents

1. SCOPE OF WORK

2. DESIGN AND CALCULATIONS

3. FIRE NOTIFICATION EQUIPMENT

4. SYSTEM TESTING

5. AREA OF WORK

6. DRAWINGS

7. GOVERNMENT WORKING HOURS

8. CONTRACTOR MANPOWER REPORTING APPLICATION (CMRA)

9. PERIOD OF PERFORMANCE

10. MATERIALS

11. MATERIAL SUBMITTALS

12. DIFFERING SITE CONDITIONS

13. UTILITIES

14. DISPOSAL OF MATERIALS AND CLEANUP

15. MATERIAL & EQUIPMENT ACCOUNTABILITY

16. SECURITY

17. ESCORTS

18. HAZARDOUS MATERIALS PROCEDURES

19. ENVIRONMENTAL PROTECTION

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL

1. SCOPE OF WORK

1.1. The contractor shall provide all personnel, equipment, tools, materials, supervision, transportation, and other items and services necessary to complete the work as described in this Statement of Work. Work location is at the Air National Guard Base, Jacksonville International Airport, in Duval County, Florida.

1.2. The project scope is to expand the automatic fire suppression system in Building 1001, to include the Flight Line Avionics offices and the Tool Room / Tire Shop under the mezzanine (combined 4652 SQ

FT.).

1.3. Design and install the additional wet pipe fire extinguishing sprinkler systems for complete fire protection coverage throughout the Flight Line Avionics offices and the Tool Room / Tire Shop under the mezzanine (combined 4652 SQ FT.). Work shall include field surveys, analysis, flow calculations and drawings as required.

1.4. Remove the addressable fire alarm detection devices that are located in the newly protected areas, as they are no longer required. Reprogram the Fire Alarm Control Panel (FACP) and D21 Monaco Radio Reporting system with central receivers located in Buildings 5 and 44 as needed and recertify system.

1.5. Construction of all fire protection systems (Suppression and detection) is intended to be of the design-build nature, wherein the construction contractor is given all performance requirements, standards, quality expectations and data necessary for provision of the specified systems. The contractor will use this information to design (hydraulic calculations, shop drawings, equipment selections, equipment location and layout, trade coordination, etc.) and to provide the actual systems.

1.6. References. In addition to the references cited in the contract's general statement of work, the work under this specific statement of work shall conform to the following documents, as applicable:

(1) ANGETL 15-01-03 FIRE PROTECTION DESIGN GUIDANCE

(2) UFC 3-600-01 FIRE PROTECTION ENGINEERING FOR FACILITIES

(3) NFPA 13 STANDARD FOR THE INSTALLATION OF SPRINKLER

SYSTEMS

(4) NFPA 72 NATIONAL FIRE ALARM AND SIGNALING CODE

(5) ALL NATIONAL, STATE AND LOCAL STANDARDS & CODES THAT MAY APPLY

2. DESIGN AND CALCULATIONS

2.1. The building shall be protected in accordance with UFC 3-600-01, NFPA 13 and International Building Code. Provide a design narrative and hydraulic calculations as required by the above references. A registered fire protection engineer shall prepare preliminary calculations and provide the requirements for the fire protection system. The fire protection system shop drawings and hydraulic calculations shall be prepared by a NICET Level III or IV certified fire protection specialist or a Registered Fire Protection Engineer. Water velocity in the fire sprinkler system piping shall not exceed 20 feet per second. The Contractor shall be responsible for the installation, testing and field certifying of the entire system. The

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL hazard classification requirements for this facility with regard to sprinkler protection are defined per the following:

2.1.1. Extra Hazard Group 1 Classified Areas. These areas include, but are not limited to, controlled waste and flammable storage areas.

2.1.2. Ordinary Hazard Group 2 Classified Areas. These areas include, but are not limited to, open storage bays, maintenance shops, circulation bays, mechanical rooms, and electrical rooms.

2.1.3. Ordinary Hazard Group 1 Classified Areas. These areas include, but are not limited to, kitchens, armorer’s rooms, and arms vaults.

2.1.4. Light Hazard Group Classified Areas. All areas not classified as ordinary hazard or extra hazard areas including combustible attic space.

2.2. The following component details shall be designed into all suppression systems.

2.2.1. All sprinkler system piping shall be minimum schedule 40 steel. All fittings in a system shall be of one manufacturer.

2.2.2. All sprinkler system piping shall be finish painted red, and all piping shall be provided with identification and flow markings at not to exceed intervals of 8.0 meters (26feet).

2.2.3. Installation of cleated (e.g. Uni-Flange or split ring type flanges) flanges on any piping is prohibited. Do not use grooved or rolled end type connections upstream of each alarm valve for each sprinkler riser on piping systems greater than 4 inches.

2.2.4. Specifications shall require sprinkler pendant placement to be carefully coordinated with all other trades.

All heads shall be symmetrically placed centered in the ceiling tile. Provide architecturally coordinated, single piece sprinkler trim rings in all occupied spaces.

2.2.5. Recessed or concealed heads will be used in areas with ceilings such that sprinkler ceiling plates or escutcheons are of a uniform depth throughout the finished space. Upright or pendant heads will be used in exposed areas with no ceilings. Provide dry heads in areas subject to freezing.

2.2.6. Sprinkler piping shall be capable of being fully and completely drained for maintenance purposes.

Auxiliary drain valves shall be fully accessible and located no higher than 7’-0” AFF Main drains and end of line drains to facility exterior shall be provided. Drains shall have cast in place concrete splash block or similar method to control runoff and erosion at the facility exterior.

2.2.7. A test valve (inspectors test station) shall be installed for each wet pipe system. Provide smooth bore stainless steel orifice giving a flow rate equivalent to one sprinkler head. Installation at the riser is acceptable.

2.2.8. Provide heavy gauge galvanized steel hoods and shields (or stainless steel) that are shop fabricated for electrical rooms and communications rooms to protect the electrical equipment from water spray where a sprinkler system is installed. Drainage from these hoods shall be directed to floor drains.

2.2.9. Fire protection piping support shall be directly from the facility structural system. No other equipment or materials may be supported from the fire protection support system. Do not hang from the underside of roofing deck or from other equipment or materials. All support systems shall include full lateral and

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL horizontal bracing. Design of support shall comply as a minimum, with seismic criteria as outlined in

NFPA 13.

2.2.10. All system valves shall have tamper switches provided and integrated into the addressable fire alarm system as a supervisory alarm.

2.2.11. All wall and floor penetrations for fire protection piping shall be fully sleeved and sealed.

2.3. Penetrations into SCIF areas shall be performed by a single penetration. All penetrations shall be installed using a DI-ELECTRIC BREAK.

2.4. Verify and Replace Hydraulic Data Nameplate if needed.

3. FIRE NOTIFICATION EQUIPMENT

3.1. If necessary provide a flow switch in sprinkler piping – tie into the Buildings Addressable Fire Alarm Control Panel

3.2. Circuits shall be Class A and Initiating Device Circuits shall not share the same conduits.

3.3 Program changes made to FACP’s programming into the Monaco D-21 workstations to report alarm and supervisory conditions and removed devices.

3.4. Circuits shall be continuous from device to device. No terminal blocks or wire nuts are allowed.

4. SYSTEM TESTING

5.1. Provide acceptance testing. Provide preliminary testing as required to complete system in accordance with

NFPA 13

5. AREA OF WORK

5.1. Building 1001, Flight Line Avionics offices has suspended ceiling grid with acoustical tiles (3255 Sq.

Ft.) and the Tool Room and Tire Shop under the mezzanine is open warehouse space (1397 Sq. Ft.).

(Combined 4652 SQ FT.)

6. DRAWINGS

6.1. Drawings shall show the general layout of the systems involved and indicate clearly the extent, type and detailed requirements for all contract work. Drawings shall include but not be limited to:

(1) Site plan.

(2) Proposed fire suppression system

(3) New Fire Alarm drawing

(4) Schedules as required.

(5) Typical sections and construction details.

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL

6.2. The final submittal will be forwarded to the 125th Fighter Wing for its approval.

7. GOVERNMENT WORKING HOURS

7.1. Work hours shall be Monday thru Friday 0700-1600 hours, with the exception of Federal holidays.

Contractor must have prior approval in writing to work outside these guidelines.

7.2. Recognized Holidays:

New Year’s Day Independence Day Thanksgiving Day Martin Luther King Jr.’s Birthday Labor Day Christmas Day President’s Day Columbus Day Memorial Day Veteran’s Day

8. CONTRACTOR MANPOWER REPORTING APPLICATION (CMRA)

8.1. The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for AIR FORC via a secure data collection site.

The contractor shall completely fill in all required data fields using the following web address:

http://www.ecmra.mil/. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk at http://www.ecmra.mil/.

Unit Identification Code (UIC) for the Requiring Activity: FFTX50 Issuing Office DoDAAC: W911YN

9. PERIOD OF PERFORMANCE

9.1. Work must be completed in 150 calendar days.

10. MATERIALS:

10.1. Construction materials must meet all required NFPA and UL requirements.

11. MATERIAL SUBMITTALS:

11.1. The contractor shall submit to the Contracting Officer for approval all items listed on attached Material

Submittal Schedule, within 10 calendar days of the notice to proceed (NTP) - or - provide a copy indicating when each material submittal shall be submitted for approval. Ensure that any disapproved material submittal will not impact the approved project execution schedule, as disapproved submittal shall not be considered grounds for a time extension. Allow for a minimum of 5 calendar days for the Government’s processing of material submittals. The contractor shall not order, deliver or install any materials without CO’s material approval or remove any materials on site, which have not been properly approved.

http://www.ecmra.mil/

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL

Description Item Submitted Type QTY Due Remarks

Preconstruction Submittals

Project Baseline Schedule

Material Submittal AF Form 3000

1 EA.

Within 10 calendar days of

NTP

Base Contracting

COR

Contractor

Shop Drawings Shop Drawings Material Submittal AF Form 3000

1 EA.

Within 10 calendar days of

NTP

Base Contracting

COR

Contractor

Design Data Hydraulic Calculations

Material Submittal AF Form 3000

1 EA.

Within 10 calendar days of

NTP

Base Contracting

COR

Contractor

Product Data Pipe

Material Submittal AF Form 3000

1 EA.

Within 10 calendar days of

NTP

Base Contracting

COR

Contractor

Product Data Fittings

Material Submittal AF Form 3000

1 EA.

Within 10 calendar days of

NTP

Base Contracting

COR

Contractor

Product Data Valves

Material Submittal AF Form 3000

1 EA.

Within 10 calendar days of

NTP

Base Contracting

COR

Contractor

Product Data Sprinklers

Material Submittal AF Form 3000

1 EA.

Within 10 calendar days of

NTP

Base Contracting

COR

Contractor

Product Data

Pipe hangers and supports

Material Submittal AF Form 3000

1 EA.

Within 10 calendar days of

NTP

Base Contracting

COR

Product Data

Mechanical couplings

Material Submittal AF Form 3000

1 EA.

Within 10 calendar days of

NTP

Base Contracting

COR

Certificates

Fire Protection Engineer

Material Submittal AF Form 3000

1 EA.

Within 10 calendar days of

NTP

Base Contracting

COR

Certificates

Sprinkler System Installer

Material Submittal AF Form 3000

1 EA.

Within 10 calendar days of

NTP

Base Contracting

COR

Contractor

Form

Contractor Hazardous Material Identification Form

Material Submittal AF Form 3000

1 EA.

Prior to bringing any Hazmat on base

COR

Environmental

Form

125th Fighter Wing Solid Waste Disposal and Diversion Tracking Form (V2.0)

Material Submittal AF Form 3000

1 EA. FINAL INVOICE COR

Environmental

Test Reports Final Acceptance Test Report

Material Submittal AF Form 3000

1 EA. FINAL INVOICE

Base Contracting

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL

Closeout Submittals As-built drawings

Material Submittal AF Form 3000

1 EA. FINAL INVOICE

Base Contracting

12. DIFFERING SITE CONDITIONS

12.1. Bring any unforeseen project conditions to the attention of the CO immediately. Differing site conditions, which may alter the scope of work, shall be approved by the CO prior to such work being performed.

13. UTILITIES

13.1. The Government shall provide at no cost to the Contractor reasonable amounts of water and electricity to support the contract. Hook up will be to existing outlets and will be the contractors responsibility.

14. DISPOSAL OF MATERIALS AND CLEANUP

14.1. The contractor shall not use any government disposal bins, dumpsters or trash receptacles for any reason at any time. The contractor shall provide appropriate disposal bins/trash receptacles. Approval of disposal bins/trash receptacles location(s) shall be coordinated through government project manager. The contractor shall not allow debris to leave the work area due to potential damage to aircraft engines. Contractor shall coordinate with the base Environmental Management Office (EMO) prior to disposing any materials off base. All debris or trash shall be disposed of off base. All demolition debris shall be disposed of at a permitted landfill, with landfill authorization, unless other arrangements have been coordinated through the EMO. Provide proof of landfill disposal from the landfill that accepts the materials. This may be accomplished by providing the government project manager with landfill receipts; waste manifests, or weight tickets from the landfill that accepts the construction debris along with the 125th Fighter Wing Solid Waste Disposal and Diversion Tracking Form. Contractor shall clean up after each work period and dispose of all debris at the close of each day.

15. MATERIAL & EQUIPMENT ACCOUNTABILITY

15.1. Notify the government project manager prior to delivery of any material or equipment to the site. The contractor shall ensure someone is available to receive delivered materials and able to store them safely in an area to be coordinated with the government project manager. Any materials delivered without prior coordination and without having someone to take receipt, shall not be accepted and turned away.

16. SECURITY

The Florida Air National Guard base has 24-hour security and entry control procedures. Contractors will be briefed on an ‘as needed’ basis concerning traffic routing and work site security restrictions.

Base Access Letters for contractors are required and will be obtained at either the preconstruction conference or when requesting a construction permit. Information required for the Base Access Letters shall include individual’s complete name, company name, driver’s license number, project or contract

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL number and title of the project. Base Access Letters are provided by the Base Civil Engineer and approved by The Chief of Security. A 125FW Contractor Badge will be issued to all workers prior to work start. This badge will be required to enter the base and worn at all times while on base. To obtain a 125FW Contractor Badge, all workers must submit a police records check from the Jacksonville’s Sherriff’s Office (JSO) to the 125th Security Forces Squadron Pass and ID Office. This records check must be the original and signed copy issued from JSO. Furthermore, before the request is accepted and processed, each member must present a government issued photo ID to the Pass and ID Office when submitting the request. Each identified contractor will ensure that the identified badge is properly displayed while performing work on the installation. Also, each individual who is issued a badge must maintain control of his or her assigned badge at all times. If lost or misplaced, it must be reported to Security Forces immediately. Any contractor driving on the installation will be required to have valid driver’s license, proof of insurance, and vehicle registration. Weapons and firearms are not allowed on the base regardless of any issued weapon/firearm permits. One escort badge will be issued to the site super for the purpose of receiving deliveries.

Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR).

The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation.

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

Advanced Distributed Learning Service (ADLS). All contractor employees and associated sub-contractor employees assigned to work on a government site and/or requiring access to a DoD network will be required to register with ADLS at commencement of services in order to complete the necessary training required of them initially and annually for the duration of the contract (i.e., DoD Information Assurance, OPSEC, Security Administration). ADLS website:

https://golearn.csd.disa.mil/kc/rso/login/ADLS_login.asp.

AT Level I Training. This standard language is for contractor employees with an area of performance within a Government controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access to Government Installations, Facilities and Controlled Access areas shall complete AT Level I awareness training within 10 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable.

Certificates of completion for each affected contractor employee and subcontractor employee will be maintained by the COR or Antiterrorism Representative. AT level I Training is available through JKO by completing the CBT at http://jko.jten.mil/courses/atl1/launch.html (no CAC required).

https://golearn.csd.disa.mil/kc/rso/login/ADLS_login.asp

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL

17. ESCORTS

17.1. Security Forces shall monitor the incoming and outgoing of work personnel during the duration of the project. Pass & ID will issue (1) escort badge to the site super for the purpose of receiving deliveries.

18. ENVIRONMENTAL PROTECTION

1 Part 1 - GENERAL

1.1 SCOPE OF WORK

A. The work covered by this section concerns the furnishing all labor, materials, and equipment required for the prevention of environmental degradation during, and as a result of, construction operations under this contract.

1. For the purpose of this specification, environmental pollution is defined as “the presence of chemical, physical, or biological elements or agents, not naturally occurring at the site, which adversely affect human health or welfare; unfavorable alter ecological balances important to human life; affect other species of importance to man;

or degrade the utility of the environment for aesthetic and recreational purposes.”

2. The control of environmental pollution by Contractor of this Project requires consideration of air, water, and land and involves noise control, solid waste management and management of radiant energy and radioactive materials, as well as other pollutants.

3. This section also requires the protection of cultural and historic resources.

B. The requirements listed in this Section are in addition to any environmental protection requirements listed in other provisions of these specifications. Contractor shall coordinate the work of this Section with the Work called for under the various sections of the Contract.

C. The basic environmental installation environmental protection guidelines are contained in the “Environmental Protection Plan for Contractors”.

D. Contact the Contracting Officer’s Representative (COR), concerning the content of these requirements.

1.2 125th FIGHTER WING ENVIRONMENTAL MANAGEMENT SYSTEM (EMS) BaSE

ENVIRONMENTAL STATEMENT VISA VIE CONTRACTOR RESPONSIBILITIES

A. Protecting the environment is one of our highest priorities and will be a major factor in the decision making of Contractor selection of materials to be used on Base. The 125th Fighter Wing (FW) is dedicated through the use of a pro-active Environmental, Safety, and Occupational Health (ESOH) Council to the continued improvements of our processes to prevent and reduce waste generation by all means possible that are fiscally reasonable to implement. The Wing endorses the development and execution of an installation-wide EMS and a commitment to compliance with federal, state, and local environmental laws and regulations. We and the Contractor by presence on base will continue to pursue a course of responsible environmental stewardship in support of our environmental policy for the Base.

1.3 Contractor’S GENERAL ENVIRONMENTAL COMPLIANCE OBLIGATIONS A. Contractor and any subcontractor, agent or representative shall comply with all applicable

Federal, State, and local laws and regulations providing for environmental protection and pollution control and abatement including but not limited to the following:

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL

1. Clean Air Act;

2. Clean Water Act;

3. Resource Conservation and Recovery Act;

4. Comprehensive Environmental Response, Compensation and Liability Act (CERCLA);

5. Toxic Substances Control Act;

6. Federal Insecticide Fungicide and Rodenticide Act;

7. Coastal Zone Management Act;

8. Endangered Species Act;

9. National Historic Preservation Act;

10. Safe Drinking Water Act;

11. National Pollutant Discharge Elimination System (NPDES)

12. Emergency Planning and Community Right-to-Know Act;

13. Oil Pollution Act and Pollution Prevention Act.

B. Contractor is responsible for determining where such laws and regulations apply, although Contractor may request assistance from the COR in delineating applicable environmental laws and regulations. Contractor has an independent responsibility to make its own determination and to do so in a timely fashion.

C. Hazardous Material Spills: Spills shall be immediately contained, if possible, and reported to the base authorities in accordance with the installation’s “Oil and Hazardous Substances Spill Prevention and Response Plan” and also cross referenced in the “Environmental Protection Plan for Contractors.”

D. Contractor shall not discharge anything into the Base’s sanitary sewer system without coordination and approval from the COR who will coordinate with the Base Civil Engineer and Base Environmental Manager.

E. The Base Civil Engineer and Base Environmental Manager may conduct inspections without notice at on-base work sites to ensure environmental compliance. Any items of non-compliance will be reported to the Contracting Officer.

F. The contractor shall use the 125th Fighter Wing “Environmental Protection Plan for Contractors” for basic installation specific guidelines.

1.4 CONTACTS WITH ENVIRONMENTAL REGULATORY OFFICIALS

A. Contractor shall, through the Contracting Officer, immediately advise the installation environmental management function of the content of all contact with federal, state or local environmental regulators, before during and after the performance of this contract concerning the performance of this contract.

1.5 Contractor’S LIABILITY FOR ENVIRONMENTAL DAMAGES

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL

A. Contractor agrees to hold harmless and indemnify the Air Force for any and all damages of any kind resulting from environmental violations by Contractor, Contractor’s employees, or agents or subcontractors.

1. Damages include, but are not limited to, personal injury, property damage (including diminution of value), or death, environmental restoration and response costs, natural resource damages, expert witness and attorney’s fees.

2. Reimbursement of any and all expenses incurred to obtain permits as a result of

Contractor’s failure to identify or obtain permits shall be borne by the Contractor.

1.6 FINES OR PENALTIES FOR ENVIRONMENTAL NON-COMPLIANCE

A. Contractor shall be responsible for paying any fines or penalties assessed against the Air Force for environmental violations resulting from acts or omissions of Contractor or its employees, subcontractors, or agents.

1. This obligation is in addition to any fines or penalties that may be assessed against

Contractor for the same conduct.

2. Contractor may either reimburse these fines or penalties through the Contracting Officer, or with the consent of the Base Civil Engineer, conveyed through the Contracting Officer, Contractor may pay such fines or penalties directly to the regulatory agency or agencies concerned.

1.7 WASTE DISPOSAL FOR CONTRACTS TO BE PERFORMED ON GOVERNMENT

FACILITIES

A. Hazardous Waste Generation, Handling and Disposal: Work under this contract is to be performed on a government facility. According to rules and procedures of the United States Environmental Protection Agency (EPA), a federal facility is required to have a generator identification number under the Resource Conservation and Recovery Act (RCRA) and to be responsible for hazardous wastes (as defined under RCRA) produced, managed, stored, disposed on or transported from the facility.

1. Contractor shall, to the greatest extent practicable, use materials, processes and techniques that will avoid the creation of hazardous waste.

2. The Department of Defense (DOD) Solid Waste Measure of Merit (MoM) requires the Air Force to report all solid waste that is disposed in landfills, and also diverted from landfills through reuse or recycling. Of the inevitable waste that is generated, as many of the waste materials as is economically feasible shall be reused, salvaged or recycled.

Waste disposal in landfills shall be minimized.

3. With regard to this directive, the Contractor shall develop a written Waste Management

Plan for this project prior to the generation of hazardous materials and hazardous waste resulting from demolition and new construction. This plan, including disposal policies, shall be reviewed and approved by both the Contracting Officer and the Base Civil Engineer before such activities begin.

4. Contractor shall follow this plan once is has been approved by the Contracting Officer.

Contractor shall coordinate all planned activities regarding hazardous materials and hazardous waste with the Base Civil Engineer office through the Contracting Officer.

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL

5. Under no circumstances will the Contractor bring hazardous waste onto the facility.

B. Waste Management Plan:

1. Draft of Plan: Within THIRTY (30) CALENDAR DAYS after receipt of the Notice to

Proceed, the Contractor shall submit to the Contracting Officer a draft of the Waste Management Plan for review by the Installation Solid Waste Manager. This draft plan shall contain the following:

a. Analysis of the jobsite waste that is anticipated to be generated, including types of materials and their quantities; a manifest will be generated for each load off base, an electronic copy shall be provided to the COR for approval prior to its departure from the base. This will carry forward till the end of the job.

b. The name of the landfill(s) where trash will be disposed of, the applicable landfill tipping fee(s), and the projected cost of disposing of all project waste in the landfill(s).

2. Alternates to Landfilling: Contractor to provide a list of each material proposed to be salvaged, reused or recycled during the course of the Project, the probable local market for each material, and the projected net cost savings or additional costs resulting from separating and recycling, versus landing, of each material.

a. “Net” means that the materials listed below have been subtracted from the cost of separating and recycling, including revenues from the sale of recycle or salvaged materials and landfill tipping fees saved due to diversion of materials from the landfill.

3. Materials Effected: The list of materials is to include, at a minimum, the following items:

a. Cardboard;

b. Clean dimensional lumber;

c. Beverage containers;

d. Land clearing debris;

e. Concrete;

f. Bricks;

g. Concrete masonry units (CMU);

h. Asphalt;

i. Galvanized sheet metal;

j. Stainless steel;

k. Aluminum;

l. Copper;

m. Zinc;

n. Lead;

o. Brass;

p. Bronze, and

q. Metals from banding, stud trim, ductwork, piping, reinforcing rods, roofing, other trim, steel, iron;

4. Final Waste Management Plan: Once the Contracting Officer has determined which of the recycling options listed in the draft Waste Management Plan are acceptable, the Contractor shall submit, within TEN (10) CALENDAR DAYS, a Final Waste Management Plan. The Waste Management Plan shall be implemented in the following fashion:

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL

a. Manager: Contractor shall designate an on-site party or parties to be responsible for instructing workers, and overseeing and documenting results of the Waste Management Plan.

b. Distribution: Contractor shall distribute copies of the Waste Management Plan to the Job Site foreman, each Subcontractor, the Contracting Officer and the Contracting Officer’s Representative.

c. Instruction: Contractor shall provide on-site training on appropriate separation, handling and recycling procedures, as well as instruction on salvage, reuse and return of materials to be used by all parties at appropriate stages of the project.

d. Separation Facilities: Contractor shall lay out and label a specific area of the job-site to facilitate separation of materials for potential recycling, salvage, reuse or return. Recycling and waste bin areas are to be kept clean and clearly marked as to contents in order to avoid contamination of materials.

e. Hazardous Materials: Such materials shall be separated, stored and legally disposed of according to federal, state and local regulations.

f. Documentation of Compliance: Each quarter, the contractor shall submit a solid waste disposal and diversion tracking form (attachment 1) to the COR, who in turn will send it to the base environmental office. Failure to provide these quarterly reports may delay progress payments. The report contains the following information:

1) The amount in tons of material land filled from the Project, the identity of the landfill(s), the total amount of tipping fees paid at the landfill(s), and total disposal costs.

2) For each material recycled, reused or salvaged from the Project, the amount in tons, the date removed for the Job Site, the receiving party, the transportation costs, the amount of any money paid or received for the recycled or salvaged materials, and the net cost or savings of salvage or recycling each material.

5. Contractor shall follow this Plan without deviation once Contracting Officer has approved it. Contractor shall not dispose refuse or construction debris on installation dumpsters. Wastes shall not be created until the Waste Management Plan has been approved by the Contracting Officer.

1.8 PERMITS FOR CONSTRUCTION WORK ON A government INSTALLATION

a. CONSTRUCTION, EXCAVATION, MODIFICATION, RENOVATION, DEMOLITION, INSTALLATION, OR OTHER ALTERATION OF BUILDING STRUCTURES, EQUIPMENT, INSTALLATIONS, REAL PROPERTY, OR SYSTEMS ON A GOVERNMENT INSTALLATION

1. General: Some activities such as excavation, demolition, or renovation, equipment installation or other alteration of building structures, equipment, real estate or systems may require permits to allow that work to occur.

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL

2. Contractor shall, after consultation with the Base Civil Engineer, identify all Federal, State or Local permit requirements under all applicable environmental laws and regulations as defined in Paragraph 1.2.A above.

3. Contractor shall then prepare and submit in draft all applicable permit applications and all supporting data to the Contracting Officer, who will submit these documents to the Base Civil Engineer.

4. Applications for permits that must be submitted by Contractor will be returned to

Contractor after review.

1.9 COMPLIANCE WITH EXISTING INSTALLATION-HELD PERMITS

A. General: The United States Air Force (USAF) holds permits at the 125th Fighter Wing.

1. Contractor shall provide the Contracting Officer with notice of any activities it plans to undertake which may require the Base Civil Engineer to perform any action regarding these permits such as requesting a permit modification or reporting of required information.

2. Contractor will provide such notice as far in advance of planned activity as is practicable.

Part 2 - MATERIALS

2.1 RECYCLED MATERIALS

A. Materials used in this contract shall be, to the greatest extent practicable and consistent with financial prudence, made of recycled materials or with materials that are recyclable.

1.2 ASBESTOS

A. No asbestos containing materials shall be brought onto the Base. Should this be discovered, the Contractor shall be solely responsible for all and any cost associated with the removal and subsequent corrective measures taken to correct the mishap.

B. Removal of asbestos material will be included in the project as required.

1. Identification of 125th Fighter Wing buildings to be demolished or renovated that are affected by this project is as noted on Civil Engineering drawings and should be coordinated with the base asbestos manager prior to commencing work.

2. Procedures and criteria for accomplishing asbestos abatement in these buildings are established in Division 2 Section “Asbestos Abatement Procedures“.

3. Additional information is available in the “Asbestos Management Plan” for 125th Fighter Wing as published by the Air National Guard, Civil Engineering Services Center, Minot, North Dakota

a. Copies of this report can be obtained through the Base Civil Engineer.

b. This report is part of the bidding documents if required.

c. Asbestos abatement work shall also comply with the Florida Administrative

Code, Chapter 62-257, (Asbestos Program) and can be obtained from the Florida Department of Environmental Protection, Tallahassee, Florida (http://www.dep.state.fl.us/air/rules/current.htm#62-257) http://www.dep.state.fl.us/air/rules/current.htm#62-257

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL

2.3 POLYCHLORINATED BIPHENYL’S (PCBs)

A. PCBs will not be used or included in the new construction portion of this project.

2.4 LEAD-BASED PAINT

A. No lead based paint containing materials for any project shall be brought onto the Base.

Should this be discovered, the Contractor shall be solely responsible for all and any cost associated with the removal and subsequent corrective measures taken to correct the mishap.

B. If the presence of lead-based paint is encountered during the building demolition or renovation portion of this project, communicate with the Contracting Officer’s Representative and Base Environmental Manager. A subsequent change order upon confirmation will be submitted to the Contracting Officer. Related lead-based paint management procedures will be performed in accordance with applicable regulations, including, but not limited to, those established by the following agencies and governmental acts:

1. U.S Environmental Protection Agency, Region 4, Atlanta GA (http://www2.epa.gov/lead)

2. Florida Department of Environmental Protection, Northeast District, 8800 Baymeadows Way West, Suite 100, Jacksonville, Florida. (904) 256—1700 (http://www.dep.state.fl.us/northeast/ )

3. Section V, Chapter 3 of the Technical Manual of the Occupational Safety and Health

Administration (OSHA), dealing with controlling lead exposures in the construction Industry, in regards to engineering and work practice controls.

2.5 OZONE-DEPLETING SUBSTANCES

A. “Class I substance,” as used in this clause means any substance designated as class I by the Environmental Protection Agency (EPA) (40 CFR Part 82), including but not limited to chlorofluorocarbons, halons; carbon tetrachloride and methyl chloroform.

B. “Class II substance,” as used in this clauses means any substance designated as class II by EPA (40 CFR Part 82), including but not limited to hydro-chlorofluorocarbons.

C. As required by 42 USC 7671j(b), (g) and (d) and 40 CFR Part 82, Subpart E. Contractor shall label products which contain Class I or Class II ozone-depleting substances or are manufactured with a process that uses Class I or Class II ozone-depleting substances, or containers of Class I or Class II ozone-depleting substances as follows:

“WARNING: Contains (or manufactured with, if applicable). ________ * ________ (a) substance(s) which harm(s) public health and the environment by destroying ozone in the upper atmosphere.” *Contractor shall insert the name of the substance(s).

“Contractor shall ensure no Class I ozone-depleting substances are used on the 125th Fighter Wing.

“”Contractor shall comply with the applicable requirement of Sections 608 and 609 of the Clean Air Act (42 IS 7671g, National Recycling and Emission Reduction Program and 7671h. Servicing of Motor Vehicle Air Conditioners) as each or both apply to the contract.””

1.3 PESTICIDES

A. Except as may be specified elsewhere in this contract, Contractor shall not apply any pesticides such as herbicides (weed-killers), insecticides, or rodenticides, without the specific written prior approval of the Base Civil Engineer.

2 part 3 – EXECUTION

3.1 PROTECTION OF WATER RESOURCES

A. General: Contractor shall not pollute storm drainage ways, streams, lakes or reservoirs with fuels, oils, bitumens, calcium chloride, acids, construction wastes or other harmful materials.

http://www2.epa.gov/lead http://www.dep.state.fl.us/northeast/

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL

It is the responsibility of Contractor to investigate and comply with all applicable federal, state and municipal regulations.

1. Contractor shall take particular care to prevent chemical, fuels, oils, greases, bituminous materials, waste washings, herbicides, cement and surface drainage from entering public waters.

2. In the event of a spill, the contractor shall follow spill response actions in the

“Environmental Protection Plan for Contractors. In addition, the Base Fire Department and Environmental Office shall be notified immediately. Subsequent communication shall be accomplished to the Contracting Officer’s Representative who will notify the Contracting Officer of the mishap.

B. Waste and Curing Water: Water used in aggregate processing, concrete curing, foundation and concrete lift clean-up and other waste water shall not be allowed to enter the storm drainage system.

3.2 POLLUTION PREVENTION

A. General: Contractor should use prior planning to find those materials that will minimize the creation of waste in general and hazardous waste in particular.

3.3 UNEXPECTED SIDE CONDITIONS

A. Contaminated Soil or Groundwater: Unless otherwise specified elsewhere in the Contract Documents, the job-site has been inspected and is, consistent with best professional judgment, free of environmental contamination or pollution.

1. However, unexpected conditions can always arise. Contractor or subcontractor personnel may encounter soil or groundwater that is suspected to be contaminated, either because of odors, colors, free liquids or other suspicious conditions.

2. Should this occur, the Contractor shall immediately notify the Base Civil Engineer and the Base Environmental Manager and take necessary initial measures to protect workers, the site and other personnel.

B. Unexploded Munitions: No munitions or munitions-related materials are known or expected to be present on site. However, should suspected munitions-type material be encountered, Contractor should immediately Stop Work, Turn Off and Leave Equipment where it Rests, and Remove all personnel from the area and notify the COR and receive advice before disturbing the questionable material.

3.4 SITE DISTURBANCE DURING CONSTRUCTION ACTIVITIES

A. Contractor shall use industry-recognized best management practices to avoid creation of fugitive dust emissions, and to avoid and control storm water runoff from the construction site and any temporary roads that may be used for access to it.

1. Water sprinkling may be used to control dust.

2. Contractor shall perform all work under this contract in such a manner that no pollutants of any kind are released into ditches, storm drains, streams, lakes or other surface waters of the site.

3.5 PROTECTION OF LAND RESOURCES

A. General: It is intended that the land resources within the project boundaries and outside the limits of permanent work performed under this Contract be preserved in their present condition, or be restored to a condition after completion of construction that will appear to the natural and not detract from the

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL appearance of the project. Contractor shall limit his construction activities to those areas defined by the Drawings or Specifications.

B. Prevention of Landscape Defacement: Except in area marked on the plans to be cleared, Contractor shall not deface, remove, cut, injure or destroy trees or shrubs without special authority.

1. Trees designated to be saved shall be protected from either excavation or filling within the root zone.

2. No ropes, cables or guys shall be fastened or attached to any existing trees for anchorage unless specifically authorized by the Contracting Officer.

3. Contractor shall, in any event, be responsible for any damage resulting from such use.

C. Restoration of Landscape Damage: Any trees or other landscape features scarred or damaged by Contractor s equipment or operations shall be restored as nearly as possible to the original condition at Contractor’s expense.

1. The Contracting Officer will decide what method of restoration shall be used, and whether damaged trees shall be treated and heeled or removed and disposed of.

2. All scars made on trees not designated on the plans to be removed by equipment construction operations or by the removal of limbs larger than 1-inch in diameter shall be coated immediately with an approved tree wound dressing.

3. Experienced landscape personnel shall perform all trimming or pruning in an approved manner. Tree trimming with axes shall not be permitted.

4. Trees that are to remaining either within or outside established clearing limits that are subsequently damaged by Contractor, and that are beyond saving in the opinion of the Contracting Officer shall be immediately removed and replaced with a nursery-grown tree of the same species.

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL

Flt Line Avionics and Tool Room / Tire Shop Fire Suppression System 125th Fighter Wing FANG LSGA LSGA170650 Jacksonville IAP, FL

END OF STATEMENT OF WORK

BASE CIVIL ENGINEERING
Project #: LSGA170650
STATEMENT OF WORK

File details come from the government source that posted it.