Attachment_1_-_Specifications_.pdf

PDF 593 KB Posted

Attached to
Locks and Dam Branch Office Paving Federal contract opportunity
Solicitation number
W911WN18T8002
Issued by
Department of the Army Corps of Engineers Engineering District Pittsburgh

About this file

Attachment 1 - Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Locks and Dam Branch Office Paving, newest first.
File Type Posted
Attachment_3_-_Price_Schedule.XLS XLS spreadsheet
RFQ_W911WN18T8002_-_L&D_Paving.pdf PDF
Attachment_4_-_Wage_Determination.pdf PDF
Attachment_2_-_Plans.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W911WN18T8002

L/D Branch Office Parking Lot Paving PEWARS, Neville Island Ohio River Pennsylvania

Certified Final Documents Technical Specifications March 2018

Locks and Dam Branch Office Paving

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00.00 08 SUMMARY OF WORK

01 22 00.00 10 MEASUREMENT AND PAYMENT

01 30 00.00 08 ADMINISTRATIVE REQUIREMENTS

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION

02 42 00.00 08 DISPOSAL OF MATERIALS

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 05 19 GEOTEXTILE

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 11 23 AGGREGATE BASE COURSES

32 12 13 BITUMINOUS TACK AND PRIME COATS

32 12 17 HOT MIX BITUMINOUS PAVEMENT

32 15 00 AGGREGATE SURFACING

32 92 19 SEEDING

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION 01 11 00.00 08

SUMMARY OF WORK

PART 1 GENERAL REQUIREMENTS

1.1 LOCATION AND DESCRIPTION OF WORK

The work is located at PEWARS Locks and Dam Branch Office, 3900 Grand Avenue, Bldg 1002, Pittsburgh, PA 15225-1510, near the Ohio River, on Neville Island, near Pittsburgh, Pennsylvania. The site of the work may be reached from state and local roads.

The general description of the work is to furnish all equipment, labor, materials, layout of work, and supervision to improve the existing bituminous-surfaced parking area and gravel-surfaced entrance apron in accordance with the following specifications and as shown contract drawings.

The proposed improvements include removal of existing asphalt, placement of new asphalt surfacing, placement of new gravel surfacing, and modifications to existing manhole frame/covers to accommodate proposed grading adjustments.

All work, including cleanup of the premises, shall be completed as follows no later than 90 calendar days after the date of receipt of the Notice to Proceed.

1.2 SAFETY

All work shall be performed in accordance with the Corps of Engineers Safety Manual EM 385-1-1. Latest version includes updates 1 through 15 and is available online at:

http://www.publications.usace.army.mil/USACE-Publications/Engineer-Manuals/

The Contractor shall complete and submit an Accident Prevention Plan. A template/example of an Accident Prevention Plan is included in this specification as a separate attachment. The Contractor shall modify and edit the attached Accident Prevention Plan to reflect the project's scope of work.

Safety features shall include, but not be limited to:

- Safety Shoes: All employees engaged in construction operations shall wear safety shoes meeting the requirements of EM 385-1-1, Section 05.E.

- Protective Eyewear: All workers on the site shall wear, as a minimum, protective eyewear meeting the requirements of EM 385-1-1, Section 05.A. Additional eye protection may be required in accordance with EM 385-1-1, Section 05.B.

- Hearing Protection: Hearing protection shall be provided for workers in accordance with EM 385-1-1, Section 05.C.

- Protective Headgear: All workers on the site shall wear protective headgear in accordance with EM 385-1-1, Section 05.D.

SECTION 01 11 00.00 08 Page 1

- Employee Acknowledgement: All personnel used during this contract, including those of subcontractors, shall sign a formal written notice supplied by the Contractor, attesting that they have been provided and will utilize the above required safety equipment. Copies of these signed acknowledgements shall be furnished to the Contracting Officer.

- Safe Access: Safe access shall be continuously provided for project personnel and personnel of the Contracting Officer. Access shall be provided and maintained during every phase of the operations.

1.3 PROJECT SUBMITTALS

The Contractor shall provide submittals for Government review. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications.

1.3.1 Submittals

SD-01 Preconstruction Submittals

Environmental Protection Plan; G, RO Verification of Field Conditions; G, RO E-Verify; G, RO

1.3.2 Environmental Protection Plan

The Contractor shall submit an Environmental Protection Plan for review.

The Environmental Protection Plan shall include procedures to provide for safe conduct of the work, protection of property, equipment and machinery which is to remain undisturbed, protection and support of existing features. The plan shall include a detailed description of the proposed method(s) and equipment to be used.

1.4 COORDINATION MEETING AND POINTS OF CONTACT

Prior to commencement of any work being performed on site, the Contractor shall participate in the preconstruction meeting with the Administrative Contracting Officer (ACO) and the Resident Engineer.

Ms. Denise M. Polizzano, Resident Engineer Upper Ohio Area Office 3510 Grand Ave.

Pittsburgh, PA 15225

(412) 395-7680

1.5 VERIFICATION OF FIELD CONDITIONS

The Contractor shall verify all dimensions and condition in the field and shall advise the Contracting Officer of any discrepancy before performing any work.

1.6 PROJECT/SITE CONDITIONS

1.6.1 Work Areas

As required by 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.236-10

SECTION 01 11 00.00 08 Page 2

OPERATIONS AND STORAGE AREAS, all operations of the Contractor shall be confined to areas shown on the drawings required to accomplish the work under this contract, and as authorized and approved by the Contracting Officer. All work areas shall be coordinated with the Contracting Officer prior to commencement of work.

1.6.2 Storage Areas

A storage area for materials and equipment will be provided as shown on the drawings at a location designated by the Contracting Officer. Use of the storage area shall not interfere with Government personnel in the operation of the project.

1.6.3 Utilities

The Contractor shall provide all necessary utilities.

1.6.4 Time of Performance

The Contractor shall confine all operations at the work site between 7:30 AM and 4:00 PM EST, Monday through Friday, unless otherwise approved. Work will not be permitted on weekends or Federal Holidays unless otherwise approved.

Federal Holidays include: New Year's Day, Birthday of Martin Luther King, Jr., Washington's Birthday, Memorial Day, Independence Day, Labor Day, Columbus Day, Veteran's Day, Thanksgiving Day, and Christmas Day.

1.7 DUST CONTROL

Dust resulting from site activities shall be controlled to prevent the spread of dust to avoid creation of a nuisance in the surrounding area.

Use of water will not be permitted when it will result in, or create, hazardous or objectionable conditions such as ice, flooding, and pollution.

1.8 ENVIRONMENTAL PROTECTION

Environmental protection is the prevention/control of pollution and habitat disruption that may occur to the environment during construction and associated activities. The control of environmental pollution and damage requires consideration of land, water, and air; biological and cultural resources; and includes management of visual aesthetics; noise; solid, chemical, gaseous, and liquid waste; radiant energy and radioactive material as well as other pollutants.

Minimize environmental pollution and damage that may occur as the result of construction operations. The environmental resources within the project boundaries and those affected outside the limits of permanent work must be protected during the entire duration of this contract. Comply with all applicable environmental Federal, State, and local laws and regulations.

Any delays resulting from failure to comply with environmental laws and regulations will be the Contractor's responsibility.

Waste water from construction activities will not be allowed to enter waterways or to be discharged prior to being treated to remove pollutants.

Dispose of the construction related waste water off-Government property in accordance with Federal, State, and Local laws and regulations. Secondary containment will be required for debris or waste water. Spill containment and cleanup supplies shall be furnished by the Contractor and kept onsite.

SECTION 01 11 00.00 08 Page 3

Any spills or releases of debris into the water or other environmental violations shall be immediately reported to the Contracting Officer.

1.9 PROTECTION OF GOVERNMENT PROPERTY

The Contractor shall protect all Government property during the performance of this contract. All damage to existing Government property as a result of Contractor's work shall be repaired or replaced to the satisfaction of the Contracting Officer. Work area shall be cleaned by the Contractor daily as needed and after construction is complete. Before beginning any concrete saw cutting work, carefully survey the structure to determine the extent of the work. Take all necessary precautions to insure against damage to existing concrete or other structures to remain in place, and repair or replace any damage to such items as approved by the Contracting Officer at no additional cost to the Government.

1.10 PROTECTION OF PERSONNEL

Ensure that adequate measures are in place to protect workers, facility operation personnel, and the public from injury due to operations being performed. All protective measures shall be in accordance with EM 385-1-1.

1.11 IDENTIFICATION OF EMPLOYEES

The Contractor shall be responsible for furnishing an identification badge/card to each employee prior to the employee working onsite and for requiring each employee engaged on the work to display identification.

Identification shall consist of name tags with the name of the Contractor and the employee's name. Additionally, a valid state driver's license or other Government issued photo identification card is required for positive identification.

1.12 SECURITY REQUIREMENTS

This paragraph contains information for security requirements for work on Government property. The purpose of these security requirements is to ensure that all Contractor and subcontractor employees working on this contract have received proper clearance for access to Government property.

Identification of critical infrastructure and submission of required employee identification will be discussed at the Preconstruction Meeting.

Required employee information shall be submitted to the Contracting Officer or Pittsburgh Office of Security and Law Enforcement, as applicable, at least 15 calendar days prior to required employee access to the project.

1.12.1 Access and General Protection/Security Policy and Procedures

The Contractor and subcontractors' employees shall comply with applicable installation, facility, and area commander installation and facility access and local security policies and procedures (provided by the Government Representative). The Contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the USACE Security Office. The contractor workforce must comply with all personal identity verification requirements as directed by DoD, HQDA, and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes. The contractor must submit the full name, Social Security

SECTION 01 11 00.00 08 Page 4

Number, Date of Birth, and Place of Birth for all associated contractor or subcontractor employees to the USACE Security Specialist Paul M. Surace, 412-395-7162, paul.m.surace@usace.army.mil or USACE Chief of Security and Law Enforcement Stephen Davidson, 412-395-7504, stephen.davidson@usace.army.mil. The District retains the right to deny any contractor and subcontractor employee from working on one of its contracts based on final background investigation results.

1.12.1.1 Contractors Requiring Common Access Card (CAC)

The contractor and all sub-contractors employees will be issued a CAC only if duties involve one of the following: (1) Both physical access to a DoD facility and access, via logon, to DoD networks on-site or remotely; (2) Remote access, via logon, to a DoD network using DoD-approved remote access procedures; or (3) Physical access to multiple DoD facilities or multiple non-DoD federally controlled facilities on behalf of the DoD on a recurring basis for a period of 6 months or more. At the discretion of the sponsoring activity, an interim CAC may be issued based on a favorable review of the FBI fingerprint check and a successfully scheduled NACI at the Office of Personnel Management.

1.12.2 E-Verify

The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.

1.12.3 Changes in Security Requirements

Security requirements are subject to change in accordance with HSPD-12, Office of Personnel Management, US Army Force Protection Measures, regulation or policy changes, etc. Changes to any security requirements shall be added to the contract by modification.

The Pittsburgh District Office of Security and Law Enforcement may be contacted by phone or e-mail at the following number/address:

Steve Davidson Phone: 412-395-7504 E-mail: stephen.davidson@usace.army.mil

Paul Surace Phone: 412-395-7162 E-mail: paul.m.surace@usace.army.mi

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 11 00.00 08 Page 5

-- End of Section --

SECTION 01 11 00.00 08 Page 6

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 JOB PAYMENT ITEMS

1.1.1 General

Payment items for the work of this contract for which contract lump sum payments will be made are listed in the PRICE SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, shall be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.1.2 Reimbursement For Actual Performance And Payment Bond Premiums

Payment for reimbursement for actual performance and payment bond premiums will be made as specified in FAR 52.228-13, ALTERNATIVE PAYMENT PROTECTION.

1.1.2.1 Unit of Measure

Unit of Measure: Job

1.1.2.2 Payment Items

0001 REIMBURSEMENT FOR ACTUAL PAYMENT BONDS PREMIUMS

1001 REIMBURSEMENT FOR ACTUAL PAYMENT BONDS PREMIUMS, AWARDABLE OPTION

1.1.3 Selective Demolition

Payment shall be made for costs associated with removal of existing concrete slab ramp and concrete slab at grit separator manhole. Price shall include all materials, labor, equipment, and supplies associated with this work.

1.1.3.1 Unit of Measure

Unit of Measure: Job

1.1.3.2 Payment Items

0003 SELECTIVE DEMOLITION

1.1.4 Grading

Payment will be made for costs associated with placing, grading, and compacting fill material as shown in the contract drawings and as specified. Price shall include all materials, labor, equipment, and

SECTION 01 22 00.00 10 Page 1 supplies associated with this work.

1.1.4.1 Unit of Measure

Unit of Measure: Job

1.1.4.2 Payment Items

0007 SITE GRADING

1.1.5 Raise Existing Manhole Rim and Water Valve Boxes

This work is specified in Section 31 00 00 EARTHWORK. Payment for raising existing manhole rim and water valve boxes shall constitute full compensation for furnishing all materials, equipment, plant, tools, and for labor and other incidentals necessary to complete the work required as specified, and as shown on the Contract Drawings. Water valve boxes must be adjusted to accomodate Contractor's Grading Plan.

1.1.5.1 Unit of Measure

Unit of Measure: Job

1.1.5.2 Payment Items

0008 RAISE EXISTING MANHOLE RIM AND WATER VALVE BOXES

1.1.6 Remove and Replace Manhole Frame and Cover

This work is specified in Section 31 00 00 EARTHWORK. Payment will be made for removal, disposal, and replacement of existing manhole cover and frame as indicated. Price shall include all materials, equipment, plant, tools, and for labor and other incidentals necessary to complete the work required as specified, and as shown on the Contract Drawings.

1.1.6.1 Unit of Measure

Unit of Measure: Job

1.1.6.2 Payment Items

0009 REMOVE AND REPLACE MANHOLE FRAME AND COVER

1.1.7 Restoration of Surfaces

Payment will be made for costs associated with furnishing and installing acceptable seed and mulch in disturbed areas as specified. Price shall also include costs associated with maintaining clean entrance road during and after construction. Payment will also be made for removing, storing, and reinstalling picnic table and wooden planter as necessary. Price shall include all materials, labor, equipment, and supplies associated with this work.

1.1.7.1 Unit of Measure

Unit of Measure: Job

SECTION 01 22 00.00 10 Page 2

1.1.7.2 Payment Items

0016 RESTORATION OF SURFACES

1.2 UNIT PRICE PAYMENT ITEMS

1.2.1 General

Payment items for the work of this contract on which the contract progress payments will be based are listed in the PRICE SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.

1.2.2 Digital Progress Images

1.2.2.1 Payment

This work is specified in Section 01 32 33 DIGITAL PROGRESS IMAGES.

Payment will be made for costs associated with taking, processing, labeling, and delivering the images.

1.2.2.2 Measurement

Measurement will be made of the number of sets of photographs taken and delivered to the Contracting Officer as approved or directed by the Contracting Officer. Each set shall consist of all specified prints and slides for each photographic session as specified.

1.2.2.3 Unit of Measure

Unit of measure: Set.

1.2.2.4 Payment Item

0002 DIGITAL PROGRESS IMAGES

1.2.3 Remove and Dispose of Existing Bituminous Surfacing

1.2.3.1 Payment

This work is specified in Section 32 12 16.00 08 BITUMINOUS PAVEMENT CONSTRUCTION. Payment will be made for costs associated with removal and disposal of existing bituminous surfacing as specified and as shown on the drawings. The price shall include the cost of all labor, materials, and the use of all equipment and tools required to complete the work.

1.2.3.2 Measurement

Measurement for removal of existing bituminous pavement and aggregate base course will be by the square yard of bituminous pavement and aggregate material removed. Measurement will be based on the area of the existing bituminous pavement upon completion of removal.

1.2.3.3 Unit of Measure

Unit of Measure: Square Yard

SECTION 01 22 00.00 10 Page 3

1.2.3.4 Payment Items

0004 REMOVE AND DISPOSE OF EXISTING BITUMINOUS SURFACING

1.2.4 Earthwork

1.2.4.1 Payment

This work is specified in Section 31 23 00 EARTHWORK. Payment will be made for costs associated with excavation of the existing surfaces to the grades as indicated, including but not limited to: grades required for proper placement of material at the entrance road, entrance apron, and acces drive, as well as surface preparation in the parking area and access drive area. Payment will also be made for costs associated with loading, hauling, and disposal of excavated materials from excavations on site. It is the Contractor's sole responsibility to ensure that the material is disposed of in accordance with all local, state and federal guidelines, ordinances and laws governing materials of the character to be disposed. Price shall include all materials, labor, equipment, and supplies associated with this work.

1.2.4.2 Measurement

Measurement of excavation quantities will be made for the actual area of common excavation and disposal completed within the limits, lines and grades shown on the contract drawings. No allowance will be made for overdepth excavation or for the removal of any material outside the required lines unless authorized by the Contracting Officer.

1.2.4.3 Unit of Measure

Unit of measure: Square Yard.

1.2.4.4 Payment Item

0005 ENTRANCE APRON: EXCAVATION

0006 PARKING AREA AND ACCESS DRIVE: SURFACE PREPARATION

1002 ENTRANCE ROAD: (ASPHALT PORTION) EXCAVATION, AWARDABLE OPTION

1005 ENTRANCE ROAD: (GRAVEL PORTION) EXCAVATION, AWARDABLE OPTION

1.2.5 Aggregate

1.2.5.1 Payment

This work is specified in Section 32 11 23 AGGREGATE BASE COURSES. Payment will be made for costs associated with furnishing and placing geotextile and aggregate material as shown in the contract drawings. Price shall include all materials, labor, equipment, and supplies associated with this work.

1.2.5.2 Measurement

Measurement for payment will be made for the actual area of stone placed, to the depth as indicated, within the limits, lines and grades shown on the contract drawings.

SECTION 01 22 00.00 10 Page 4

1.2.5.3 Unit of Measure

Unit of measure: Square Yard.

1.2.5.4 Payment Item

0010 ENTRANCE APRON: BASE COURSE, 6" THICK (PennDOT No. 2A)

0015 ACCESS DRIVE: GRAVEL SURFACING, 4" DEPTH

1.2.6 Bituminous Pavement

1.2.6.1 Payment

This work is specified in Section 32 12 16.00 08 BITUMINOUS PAVEMENT CONSTRUCTION. Payments for bituminous binder course and bituminous wearing course shall constitute full compensation for furnishing all materials, equipment, plant, and tools; and for labor and other incidentals necessary to complete the work required as specified, including, but not limited to, base preparation (aggregate) and joint treatment at the interfaces of new paving with existing paving. No separate payment will be made for bituminous tack coat, and all costs in connection therewith shall be included in the applicable pavement to which the work applies.

1.2.6.2 Measurement

The volume of bituminous binder or wearing course in place and accepted will be determined by a two-dimensional measurement of the actual area of pavement. The Contracting Officer shall approve all methods and procedures for quantity surveys. Quantities shall be calculated in square yards in place.

1.2.6.3 Unit of Measure

Unit of measure: Square Yards.

1.2.6.4 Payment Items

0011 ENTRANCE APRON: BITUMINOUS BINDER COURSE, 4-1/2" THICK (SUPERPAVE

HMA 25.0 MM)

0012 ENTRANCE APRON: BITUMINOUS WEARING COURSE, 1-1/2" THICK

(SUPERPAVE HMA 9.5 MM)

0013 PARKING AREA: BITUMINOUS BINDER COURSE, 2-1/2" THICK (SUPERPAVE

HMA 19.0 MM)

0014 PARKING AREA: BITUMINOUS WEARING COURSE, 1-1/2" THICK (SUPERPAVE

HMA 9.5 MM)

1003 ENTRANCE ROAD: BITUMINOUS WEARING COURSE, 1-1/2" THICK (SUPERPAVE

HMA 9.5 MM), AWARDABLE OPTION

1004 ENTRANCE ROAD: BITUMINOUS BINDER COURSE, 2-1/2" THICK (SUPERPAVE

HMA 19.0 MM), AWARDABLE OPTION

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 22 00.00 10 Page 5

SECTION 01 22 00.00 10 Page 6

SECTION 01 30 00.00 08

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 SUMMARY

This sections contains contract administrative requirements which are not covered in Section 00 70 00 CONDITIONS OF THE CONTRACT or Section 00 73 00

SUPPLEMENTARY CONDITIONS.

1.2 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.3 ACRONYMS

DFARS - Defense Federal Acquisition Regulations Supplement EP - Engineer Pamphlet FAR - Federal Acquisition Regulations SAT - Simplified Acquisition Threshold UAI - USACE Acquisition Instructions

1.4 POINT OF CONTACT

Inquiries may be made by writing this office, or by calling (collect calls not accepted), the following individuals:

Joseph Williams 412-395-7275 for Technical Information

Matt Reed 412-395-7157 for Contracting Questions

Email: Matthew.W.Reed@usace.army.mil

Requests for hardcopies of the specifications will not be honored by telephone. Vendors must register at http://www.fbo.gov/. This site is also used for obtaining bid results and award information.

1.5 USACE ACQUISITION INSTRUCTIONS (AUI)

1.5.1 UAI 5152.231-9000 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

(a) This clause does not apply to terminations. See UAI 5152.249-9000, Basis for Settlement of Proposals, and Federal Acquisition Regulation (FAR) part 49.

(b) Allowable costs for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost

SECTION 01 30 00.00 08 Page 1 data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, Region I. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer.

For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.

(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii), CONSTRUCTION AND ARCHITECT-ENGINEER CONTRACTS and FAR 31.205-36, RENTAL COSTS. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.

(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the simplified acquisition threshold (SAT), the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.

1.5.2 UAI 5152.232-9000 PAYMENT FOR MATERIALS DELIVERED OFF-SITE (MAR 2009)

(a) Pursuant to Federal Acquisition Regulation (FAR) 52.232-5, PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS, materials delivered to the contractor at locations other than the site of the work may be taken into consideration in making payments if included in payment estimates and if all the conditions of the General Provisions are fulfilled. Payment for items delivered to locations other than the work site shall be limited to:

(1) Materials required by the technical provisions; or

(2) Materials that have been fabricated to the point where they are identifiable to an item of work required under this contract;

or

(3) Items specifically listed below.

(b) Payment for materials delivered off-site shall be made only after receipt of paid invoices listing the value of material and labor incorporated in the items along with a canceled check showing the prime contractor's title to the items delivered off site.

1.5.3 5136.249-9000 BASIS FOR SETTLEMENT OF PROPOSALS (MAR 2009)

Actual costs will be used to determine equipment costs for a settlement proposal submitted on the total cost basis under Federal Acquisition Regulation (FAR) 49.206-2(b), BASES FOR SETTLEMENT OF PROPOSALS. In evaluating a termination settlement proposal using the total cost basis, the following principles will be applied to determine allowable equipment

SECTION 01 30 00.00 08 Page 2 costs:

(a) Actual costs for each piece of equipment, or groups of similar serial or series equipment, need not be available in the contractor's accounting records to determine total actual equipment costs.

(b) If equipment costs have been allocated to a contract using predetermined rates, those charges will be adjusted to actual costs.

(c) Recorded job costs adjusted for unallowable expenses will be used to determine equipment operating expenses.

(d) Ownership costs (depreciation) will be determined using the contractor's depreciation schedule (subject to the provisions of Federal Acquisition Regulation (FAR) 31.205-11, DEPRECIATION.

(e) License, taxes, storage and insurance costs are normally recovered as an indirect expense and unless the contractor charges these costs directly to contracts, they will be recovered through the indirect expense rate.

1.6 REQUIRED INSURANCE

a. The Contractor shall procure and maintain during the entire performance period of this contract, the following minimum insurance.

Type Bodily Injury Amount Property Damage

Comprehensive General Liability $500,000 Per Occurrence $100,000

Automobile Liability $200,000 Each Person -- $500,000 Per Occurrence $ 20,000

Workmen’s Compensation $100,000 (PA) And Employer’s Liability

b. The Contracting Officer will notify the Contractor of any noncompliance with the foregoing provisions. The Contractor shall, after receipt of such notice, immediately comply. Such notice, when delivered to the Contractor or his representative at the site or mailed to the Contractor's address, will be deemed sufficient for the purpose.

If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until the Contractor complies. No part of the time lost due to any such stop orders shall be made the subject of a claim for extension of time or for excess costs or damages by the Contractor. Compliance with the provisions of this article by subcontractors will be the responsibility of the Contractor

c. Longshoreman and Harbor Worker's Insurance MAY be required for this work. Please consult with your insurance carrier and applicable statutes (33 USC 901, et. seq.).

SECTION 01 30 00.00 08 Page 3

1.7 SUPERVISION

1.7.1 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.

1.7.2 Superintendent Qualifications

The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

1.7.2.1 Duties

The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.

The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.7.3 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.8 PRECONSTRUCTION CONFERENCE

After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.

1.9 PARTNERING

To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key

SECTION 01 30 00.00 08 Page 4 personnel from the Supported Command, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.

The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.

1.9.1 Informal Partnering

The Contracting Officer will organize the Partnering Sessions with key personnel of the project team, including Contractor personnel and Government personnel.

The Initial Partnering session should be a part of the Preconstruction Meeting. Partnering sessions will be held at a location agreed to by the Contracting Officer and the Contractor (typically a conference room provided by the Resident Engineer office or the Contractor). The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the Contracting Officer. The Partners will determine the frequency of the follow-on sessions.

1.10 ELECTRONIC MAIL (E-MAIL) ADDRESS

Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 calendar days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats. Multiple email addresses are not allowed.

It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.

1.11 WORK UNDER OTHER CONTRACTS

Attention is directed to the fact that other Contractors may be employed by the Government or by local interests at or in the vicinity of the work covered by these specifications. All Contractors shall have equal rights to the use of all roads and grounds so far as practicable and this Contractor shall cooperate with other Contractors so that the work may be performed with the maximum efficiency. Should a disagreement occur between Contractors as to the use of facilities or in other matters, the decision of the Contracting Officer shall govern. (See also the Section 00 73 00

CONDITIONS OF THE CONTRACT, FAR 52.236-8 OTHER CONTRACTS).

SECTION 01 30 00.00 08 Page 5

1.12 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

a. This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with FAR 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied.

(1) The weather experienced at the project site during the contract period must be found to be unusually severe; that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project. This delay must be beyond the control and without the fault or negligence of the Contractor.

b. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS BASED ON (5) DAY

WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

15 12 8 7 6 5 5 5 4 5 7 13

c. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more on the Contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph b. above, the Contracting Officer will convert any qualifying delays to work days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with FAR 52.249-10, DEFAULT

(FIXED-PRICE CONSTRUCTION.

d. The anticipated adverse weather work days listed above are based on days with precipitation greater than 0.1 inch and/or maximum temperature below 32 degrees F. The numbers shown represent the number of work days (not calendar days) normally expected to have these particular weather conditions based on historical data. The actual number of days will vary. This information is furnished for computation of possible time extensions due to weather delays and is not intended to imply that no work can be done on these days. The Contractor shall make his own determination of the effect of these conditions on his operations under this contract, and schedule his work accordingly.

SECTION 01 30 00.00 08 Page 6

1.13 WORK PERFORMED BY CONTRACTOR

Within ten (10) calendar days after award of the contract, the successful bidder will be required to furnish a description of the work which he intends to perform with his own organization, the percentage of the total work this represents, and the estimated cost thereof.

1.14 CONTRACTOR QUALITY CONTROL

Quality Control System Manager or person responsible for Contractor Quality Control complete the Corps of Engineers' "Construction Quality Management for Contractors" course not later than 90 calendar days after receipt of the Notice to Proceed. The course consists of approximately 12 hours of classroom instruction and is offered periodically by the Pittsburgh District. For additional information on scheduling and location of the training, contact U.S. Army Engineer District, Pittsburgh, Theresa Bonanno, Upper Ohio Area Office, 3510 Grand Ave, Pittsburgh, PA 15225-1510, telephone (412)395-7677. Certification of course completion is valid for 5 years. Completion of training offered by other Corps of Engineers Districts will be acceptable provided a valid certification is presented.

1.15 SAFETY AND HEALTH REQUIREMENTS MANUAL

A copy of the current US Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1 and its changes are available at http://www.publications.usace.army.mil/USACE-Publications/Engineer-Manuals/.

The contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.

1.16 PAYMENT FOR PERFORMANCE AND PAYMENT BONDS

a. In order to ensure that sufficient funds have been set-aside for payment of performance and payment bond premiums, bidders shall insert in Bid Item No. 0001, an appropriate not-to-exceed dollar amount.

Failure of bidders to insert a not-to-exceed dollar amount in Bid Item No. 0001 will cause the bid to be rejected as non-responsive.

b. The Contractor shall be reimbursed the actual bond costs only, as established by evidence of full payment to the surety, up to the dollar amount set forth in Bid Item No. 0001. In no case will the Contractor be reimbursed an amount which exceeds the dollar amount set forth in Bid Item No. 0001.

c. The Government will reimburse only the Prime Contractor for actual paid bond premiums. The Government will not reimburse any subcontractor's paid bond premiums.

1.17 WAGE RATES

The following schedule of wage rates contains rates applicable to all work under the contract:

General Decision Number: PA180004 03/16/2018 PA4 Superseded General Decision Number: PA20170004 State: Pennsylvania Construction Types: Heavy and Highway Counties: Allegheny, Armstrong, Beaver, Bedford, Blair, SECTION 01 30 00.00 08 Page 7

Butler, Cambria, Cameron, Centre, Clarion, Clearfield, Clinton, Crawford, Elk, Erie, Fayette, Forest, Franklin, Fulton, Greene, Huntingdon, Indiana, Jefferson, Lawrence, McKean, Mercer, Mifflin, Potter, Somerset, Venango, Warren, Washington and Westmoreland Counties in Pennsylvania https://www.wdol.gov/dba.aspx

PART 2 PRODUCTS

NOT USED

PART 3 EXECUTION

NOT USED

-- End of Section --

SECTION 01 30 00.00 08 Page 8

SECTION 02 41 00

DEMOLITION

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)

ASSE/SAFE A10.6 (2006) Safety Requirements for Demolition Operations

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

40 CFR 61 National Emission Standards for Hazardous Air Pollutants

1.2 PROJECT DESCRIPTION

The project includes demolition and removal of existing bituminous surfacing, unsuitable gravel surfacing, and reinforced concrete slabs.

1.2.1 Demolition Plan

Prepare a Demolition Plan and submit proposed demolition and removal procedures for approval before work is started. Include in the plan procedures for careful removal of materials specified and a detailed description of methods and equipment to be used for each operation and the sequence of operations. Provide procedures for safe conduct of the work in accordance with EM 385-1-1. Plan shall be approved by the Contracting Officer prior to work beginning.

1.2.2 General Requirements

Do not begin demolition or deconstruction until authorization is received from the Contracting Officer. Remove rubbish and debris from the project site; do not allow accumulations inside or outside the buildings. The work includes demolition, and removal of resulting rubbish and debris. Remove rubbish and debris from Government property daily, unless otherwise directed. Store materials that cannot be removed daily in areas specified by the Contracting Officer. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1, Section 23, Demolition, and other applicable Sections.

SECTION 02 41 00 Page 1

1.3 ITEMS TO REMAIN IN PLACE

Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the Contracting Officer.

Coordinate the work of this section with all other work indicated.

Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Increase structural supports or add new supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the Contracting Officer prior to performing such work.

1.3.1 Existing Construction Limits and Protection

Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction. Provide temporary shoring and bracing for support of building components to prevent settlement or other movement. Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove dust, dirt, and debris from work areas daily.

1.3.2 Utility Service

Maintain existing utilities indicated to stay in service and protect against damage during demolition operations.

1.3.3 Facilities

Protect electrical and mechanical services and utilities. Where removal of existing utilities and pavement is specified or indicated, provide approved barricades, temporary covering of exposed areas, and temporary services or connections for electrical and mechanical utilities. Floors, roofs, walls, columns, pilasters, and other structural components that are designed and constructed to stand without lateral support or shoring, and are determined to be in stable condition, must remain standing without additional bracing, shoring, or lateral support until demolished or deconstructed, unless directed otherwise by the Contracting Officer. Ensure that no elements determined to be unstable are left unsupported and place and secure bracing, shoring, or lateral supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract.

1.4 BURNING

The use of burning at the project site for the disposal of refuse and debris will not be permitted.

1.5 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

SD-01 Preconstruction Submittals

SECTION 02 41 00 Page 2

Demolition Plan; G, RO Existing Conditions

1.6 QUALITY ASSURANCE

Submit timely notification of demolition projects to Federal, State, regional, and local authorities in accordance with 40 CFR 61, Subpart M.

Notify the Contracting Officer in writing 10 working days prior to the commencement of work in accordance with 40 CFR 61, Subpart M. Comply with federal, state, and local hauling and disposal regulations. In addition to the requirements of the "Contract Clauses," conform to the safety requirements contained in ASSE/SAFE A10.6. Comply with the Environmental Protection Agency requirements specified. Use of explosives will not be permitted.

1.7 PROTECTION

1.7.1 Traffic Control Signs

Where pedestrian and driver safety is endangered in the area of removal work, use traffic barricades with flashing lights.

1.7.2 Protection of Personnel

Before, during and after the demolition work continuously evaluate the condition of structures adjacent to demolition work and take immediate action to protect all personnel working in and around the project site.

Coordiante with Contracting Officer to direct pedestrian traffic away from the construction area.

1.8 EXISTING CONDITIONS

Before beginning any demolition or deconstruction work, survey the site and examine the drawings and specifications to determine the extent of the work. Record existing conditions showing the condition of structures and other facilities adjacent to areas of alteration or removal. Photographs sized 4 inch (or electronic) will be acceptable as a record of existing conditions. Submit survey results to the Contracting Officer.

PART 2 PRODUCTS

2.1 FILL MATERIAL

a. Comply with excavating, backfilling, and compacting procedures for materials used as backfill material.

PART 3 EXECUTION

3.1 EXISTING FACILITIES TO BE REMOVED

Inspect and evaluate existing structures onsite for reuse.

3.1.1 Structures

a. Remove existing structures indicated to be removed to accommodate new asphalt pavement and site drainage.

b. Demolish structures in a systematic manner from the top of the structure to the ground.

SECTION 02 41 00 Page 3

c. Locate equipment during demolition so as to not impose excessive loads to nearby building structures and buried utilities.

3.1.2 Utilities and Related Equipment

3.1.2.1 General Requirements

Do not interrupt existing utilities serving occupied or used facilities, except when authorized in writing by the Contracting Officer. Do not interrupt existing utilities serving facilities occupied and used by the Government except when approved in writing and then only after temporary utility services have been approved and provided.

3.1.3 Paving and Slabs

Remove concrete and asphaltic paving and slabs, including aggregate base, as indicated or as necessary to accomodate new asphalt placement with adequate drainage. Provide neat sawcuts at limits of pavement removal as indicated.